E. RESUMES OF KEY PERSONNEL PROPOSED FOR THIS CONTRACT
<br /> (Complete one Section E for each key person.) (y Z-11 r t
<br /> 12.NAME 13.ROLE IN THIS CONTRACT 14.YEARS EXPERIENCE
<br /> Catherine Hanna, EIT Civil Engineer a.TOTAL b.WITH CURRENT FIRM
<br /> 10 4
<br /> 15.FIRM NAME AND LOCATION(City and State)
<br /> Oceanit Laboratories, Inc., Honolulu, Hawai'i
<br /> 16.EDUCATION(Degree and Specialization) 17.CURRENT PROFESSIONAL REGISTRATION(State and Discipline)
<br /> MS Civil and Environmental Engineering/2012 Engineer in Training, New York, No. 088183
<br /> BS Civil Engineering/2011
<br /> 18.OTHER PROFESSIONAL QUALIFICATIONS(Publications,Organizations,Training,Awards,etc.)
<br /> Certifications: OSHA 10-Hour Training#36-005323436(2015), OSHA Asbestos Awareness Training#1360(2021), AHA Heartsaver
<br /> First Aid CPR&AED (2021)
<br /> Awards: Charles Lee Crandall Award Winner(2010 &2011), Margaret Arronet Corbin Award Winner(2011), Intel Foundation
<br /> Research Grant Recipient(2011)
<br /> 19. RELEVANT PROJECTS
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Water Infiltration into Basement of International Arrivals Building PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Honolulu, O'ahu, Hawai'i Ongoing
<br /> (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE 0 Check if project performed with current firm
<br /> a. Project Engineer. Prepared book specifications for and provided detailing of improvements intended to stop
<br /> water infiltration into the north and south portions of the Daniel K. Inouye International Airport basement.
<br /> Researched specialty products and collaborated with manufacturers, distributors and local contractors to
<br /> determine product suitability. Coordinated details with structural engineering consultant, SLSH.
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> State Irrigation System Reservoir Safety Improvements PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Waimea, Big Island, Hawai'i Ongoing
<br /> b. (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE 0 Check if project performed with current firm
<br /> Project Engineer. Civil design and detailing of 40 linear feet of subgrade outlet pipe extension, new concrete
<br /> intake box at the base, and new valve and valve stem system along the slope of Pu'ukapu Reservoir.
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Kahana Bay Erosion Mitigation PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Lahaina, Maui, Hawai'i Ongoing
<br /> (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE 0 Check if project performed with current firm
<br /> C. Project Engineer. Prepared conceptual plans and details using Civil 3D for the four(4) alternatives considered in
<br /> the project's Environmental Impact Statement (EIS), intended to develop a sustainable and resilient approach to
<br /> mitigate regional erosion along 3,700 linear feet of Kahana shoreline. Developed quantity take-offs for each
<br /> alternative for cost estimating purposes. Contributed to preparation of written content for EIS publication.
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Mantokuji Mission Shoreline Adaption PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Pa'ia, Maui, Hawai'i Ongoing
<br /> (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE 0 Check if project performed with current firm
<br /> Project Engineer. Prepared specifications and RFP package for an emergency temporary protection structure,
<br /> d. consisting of imported, beach-compatible sand wrapped in geotextile fabric, along 112 linear feet of shoreline
<br /> fronting the historic temple structure. Coordinated permitting efforts with regulatory agencies, and provided
<br /> construction administration, including reviewing submittals and responding to RFI5. Prepared preliminary plans
<br /> and design for the restoration of the sandy beach in Mantokuji Bay, as a permanent solution to the erosion and
<br /> consequent threat to the temple,to help facilitate discussions with the community and regulatory agencies.
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Ko'a Kea Resort Shoreline Protection PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Koloa, Kaua'i, Hawai'i Ongoing
<br /> (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE 0 Check if project performed with current firm
<br /> Project Engineer. Performed site reconnaissance, involving a site visit and local shoreline recession data
<br /> collection. Prepared an engineering assessment of the beach and shoreline erosion at the property, assessed
<br /> e.
<br /> adaption options considering cost, constructability, and permitting implications, and developed conceptual plans
<br /> and details for 165 linear feet of restored beach fronting the resort to reduce risks to public safety and natural
<br /> resources from shoreline recession. Also developed conceptual plan for comprehensive small-scale beach
<br /> restoration spanning seven (7) properties along 1,600 linear feet of Kiahuna Beach to incite collaborative
<br /> discussions between owners.
<br /> STANDARD FORM 330 ( REV. 7/2021) PAGE 1