E.RESUMES OF KEY PERSONNEL PROPOSED FOR THIS CONTRACT
<br /> (Complete one Section E for each key person.)
<br /> 12.NAME 13.ROLE IN THIS CONTRACT 14.YEARS EXPERIENCE
<br /> Matthew Tolley Senior Environmental Scientist a.TOTAL b.WITH CURRENT FIRM
<br /> 16 1
<br /> 15.FIRM NAME AND LOCATION(City and State)
<br /> EnviroServices&Training Center,LLC(ETC),Honolulu,Hawai`i
<br /> 16.EDUCATION(Degree and Specialization) 17.CURRENT PROFESSIONAL REGISTRATION(State and Discipline)
<br /> BS,2002,Cal Poly Humboldt,Environmental Science,Hydrology
<br /> 18.OTHER PROFESSIONAL QUALIFICATIONS(Publications,Organizations,Training,Awards,etc.)
<br /> • 40-Hour Initial/Current HAZWOPER(29 CFR 1910.120)Certificate • California Site Surveillance Technician(17-6073)
<br /> • 8-Hour Refresher HAZWOPER(29 CFT 1910.120)Certificate • AHERA MP,PD,CSS and BSI
<br /> • PG&E Certified Energy Auditor • CDPH Lead Assessor/Inspector Certified
<br /> 19.RELEVANT PROJECTS
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Environmental Consulting Services,Maui District MS4 Program PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> (Island of Maui) 2028
<br /> (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE ® Check if project performed with current firm
<br /> a. Acting project manager on three design projects under Project No.HW-ME-01-19,Contract No.DOT-2020-010.ETC prepared prefinal-level plans,
<br /> specifications,and estimate(PS&E)for the designed replacement of an existing grated drain inlet and associated curb,gutter and pavement,located at the
<br /> southeast corner of Main Street and High Street in Wailuku.Scope included 750/0 design,1000/0 design,and services during bidding and construction.ETC
<br /> prepared specifications,estimates,and an accompanying detail for the designed repair of incomplete drain pipe connections project inside existing storm
<br /> drain manholes located alongside Route 3800.ETC prepared specifications,estimates,and an accompanying detail for the designed repair sunken storm
<br /> drain manholes(SDMH)project located along Mayor Elmer F.Cravalho Way,Hahului.Project Manager.$37,500 budget.
<br /> 1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Lead and Copper Rule Revisions(LCRR)Compliance Assistance,County of Hawaii, PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Department of Water Supply(Island of Hawaii) On-going
<br /> (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE ® Check if project performed with current firm
<br /> b.
<br /> Primary roles and responsibilities included project management,project tracking,financial analysis and technical lead and/or support on primary tasks
<br /> including;Regulatory Roadmap and Gap Analysis with Work Process Evaluation,Service Line Material Inventory Initial Assistance,Lead Service Line
<br /> Replacement Plan,Customer Tap Sampling Plan,Schools and Childcare Facilities Plan,and Public Outreach.LCRR Compliance assistance performed island-
<br /> wide on the Island of Hawaii.Project Manager,$1,557,067 budget.
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Port of Richmond Terminal Four Wharf Removal Project, PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> City of Richmond(Contra Costa County,CA) 2023
<br /> c. (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE n Check if project performed with current firm
<br /> Day-to-day project manager responsible for the planning,design,environmental compliance,soil hazards and biological studies to remove the
<br /> largest derelict creosote wharf in San Francisco Bay.Work included biological studies and monitoring,construction monitoring,assess environmental
<br /> considerations,and completing technical studies.Contract amount$350,000.
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Decommissioning for Units at Humboldt Bay Nuclear Power Plant, PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Pacific Gas&Electric(Eureka,CA) 2021
<br /> d. (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE n Check if project performed with current firm
<br /> Worked closely with Pacific Gas&Electric(PG&E)at the Humboldt Bay Nuclear Power Plant,providing industrial hygiene services related to asbestos
<br /> regulatory compliance and project document administration.Mr.Tolley was a consistent and resourceful onsite presence in association with the dismantling
<br /> of the fossil-fueled power plants(Unit One and Unit Two)and the decommissioning of the nuclear plant(Unit Three).Contract amount$450,000
<br /> (1)TITLE AND LOCATION(City and State) (2)YEAR COMPLETED
<br /> Nordic Aquafarms Facility Development Project, PROFESSIONAL SERVICES CONSTRUCTION(If applicable)
<br /> Nordic Aquafarms Inc.(Samoa,CA) 2021
<br /> e. (3)BRIEF DESCRIPTION(Brief scope,size,cost,etc.)AND SPECIFIC ROLE n Check if project performed with current firm
<br /> Served as an Environmental Scientist and certified site surveillance technician during the project,including Phase I ESA's,pre-demolition hazardous and
<br /> asbestos surveys and CEQA/NEPA environmental documents in association with project-related construction impacts at the former Louisiana Pulp Mill
<br /> Complex.Contract amount$750,000.
<br /> STANDARD FORM 330(REV.7/2021)