My WebLink
|
Help
|
About
|
Sign Out
Home
2008-01-AU Limited Scope Performance Audit Report Department of Public Works CIP Contract Change Orders and Supplements for FY 2006-2007
PublicDocuments
>
Legislative Auditor
>
Audit Reports
>
County Auditor Reports
>
2008-01-AU Limited Scope Performance Audit Report Department of Public Works CIP Contract Change Orders and Supplements for FY 2006-2007
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
7/19/2011 3:17:12 PM
Creation date
7/19/2011 3:10:56 PM
Metadata
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
62
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
o Of the 28 professional services and construction contracts in our audit sample, 18 <br />contracts or 64% remain open and exceed their original contractual completion dates, and <br />14 contracts or 50% remain open and exceed their current contractual completion dates. <br />Please see Appendix for: <br />Table 5.3, Audit Sample — Construction and Professional Services Contracts — <br />Time Analysis. <br />o With regard to escalation fees: <br />Change Order C.000056.1 for $136,238 was issued for escalation fees relating to the <br />County's delay in executing a $375,000 construction contract for planning, design <br />and construction of a new warehouse addition for Ka`u baseyard improvements. <br />Change Order C.000056.2 in the amount of $17,068 for additional escalation fees has <br />been approved by the County and is pending approval by funding source U.S.D.A. If <br />approved, the combined escalation change orders will reflect a 41% increase in <br />contract price. <br />Change Order C.000641.1 (which totaled $1,131,225) included $147,848 directly <br />related to escalation fees due to delayed execution of a $6,409,034 construction <br />contract for the East Hawaii Regional Sort Station. The change order reflects a 2% <br />increase in contract price. However, delay in contract execution was attributable to <br />lack of available funding and not within the direct control of the Department of Public <br />Works. <br />Audit Obiective No. 3: Determine the extent to which contract supplements and change <br />orders could have been avoided. <br />• Contract supplements and change orders could have been avoided, or significantly <br />reduced in number and dollar value, with additional project scoping. <br />Based on project documentation provided by the Department of Public Works, the auditors <br />determined that a significant number of contract supplements and change orders issued for <br />the audit period related to work that could have been foreseen during the initial scoping of a <br />professional services contract or the initial scoping and design phases of a construction <br />project, and should have been included in the original procurement. Among them were: <br />o Contract Supplement No. C.000045.2 for $178,248 for structural engineering services to <br />develop multiple sites considered for a West Hawaii Traffic Building. <br />o Change Order Nos. 000644.1 to 000644.4 totaling $99,758 for additional work related to <br />site assessment and plan deficiencies in large capacity cesspool conversion projects in <br />Ka`u and North and South Kona. <br />17 <br />