HomeMy WebLinkAboutMIN CRCOC 2023/01/04 (2022-2024)Committee on Communications,
Reports, and Council Oversight
l't Session
Hawaii County Building
25 Aupuni Street
Hilo, Hawaii
January 4, 2023
CALL TO
The regular meeting of the Committee on Communications, Reports, and
ORDER:
Council Oversight was called to order at 10:30 a.m., in the Council Chambers,
Hilo, by Ms. Rebecca Villegas, Chair.
ROLL CALL:
Present:
Ms. Rebecca Villegas, Chair
Ms. Jenn Kagiwada, Vice Chair
Ms. Cindy Evans, Member
Ms. Michelle M. Galimba, Member
Mr. Holeka Goro Inaba, Member
Mr. Matt Kaneali`i-Kleinfelder, Member
Ms. Heather L. Kimball, Member
Ms. Susan L. K. Lee Loy, Member
Absent and Excused: Ms. Ashley L. Kierkiewicz, Member
STATEMENTS
FR C)N4 TNF
PUBLIC ON
AGENDA ITEMS:
COMMUNI-
r A TTnNc
The Chair directed the Committee to proceed to the next order of business,
Statements from the Public on Agenda Item.
(There were none.)
The Chair directed the Committee to proceed to the next order of business,
Communications.
Comm. 11: 2022 ANNUAL REPORT: REAL PROPERTY TAX BOARD OF REVIEW
From Real Property Tax Board of Review Chair Nelson Harano, dated
December 1, 2022, transmitting the above report pursuant to Hawaii County
Code Section 19-97(e).
Motion to Close File: Ms. Lee Loy moved to close file on Comm. 11.
Seconded by Mr. Inaba.
CRCOC-1
January 4, 2023
CHR. VILLEGAS: Thank you. At this time, do we have a representative from
the Real Property Tax Board? Okay, coming in from Kona. Aloha Lisa, thank
you.
(Note: At this time Real Property Tax Board of Review prior Chairperson
Nelson Harano came forward to address the members of the Committee.)
MR. HARANO: Good morning, and happy new year to all Council Members.
My name is Nelson Harano, I was the past Chairperson for the Real Property Tax
Board of Appeals for the year 2022.
CHR. VILLEGAS: Thank you, Mr. Harano. Did you want to go ahead and share
with us findings on this communication? Or did you want me to just go ahead an
open up for questions from the Council?
MR. HARANO: Yeah, you could open up for questions.
CHR. VILLEGAS: Okay.
MR. HARANO: Might be easier.
CHR. VILLEGAS: Okay. Any questions from Council Members here?
Mr. Kaneali`i-Kleinfelder.
MR. KANEALI`I-KLEINFELDER: Thank you very much, Chair. Thank you
for being here today Mr. Harano. Looking over the report looks like we had 835
appeals, is that correct?
MR. HARANO: I believe so, yes.
MR. KANEALI`I-KLEINFELDER: Majority being from East Hawaii?
MR. HARANO: I don't know, I think there was a fair mix between east and
west, north and south.
MR. KANEALI`I-KLEINFELDER: Okay. Then I have the disputed amount—or
of the appeals how many were approved from the office?
MR. HARANO: When you say approved, what do mean by approved?
MR. KANEALI`I-KLEINFELDER: Or found to be—how many were actually
appealed?
MR. HARANO: All were appealed 454 from East Hawaii and 381 from West
Hawaii.
Page 2
CRCOC-I
January 4, 2023
MR. KANEALI`I-KLEINFELDER: Okay so all of the appeals that were filed
were approved, is that correct?
MR. HARANO: Not necessarily, no.
MR. KANEALI`I-KLEINFELDER: How many were?
(Note: At this time Real Property Tax Administrator Lisa Miura came
forward to address the members of the Committee.)
MS. MIURA: Hi Lisa Miura, Real Property Tax. Can I clarify if you're asking if
some were settled or if you're asking how many made it to the board for an actual
hearing?
MR. KANEALI`I-KLEINFELDER: Thank you, Lisa. Yeah, how many were
settled?
MS. MIURA: Okay, so Keita has the list as well. So, a total of 527 were settled.
MR. KANEALI`I-KLEINFELDER: Okay. And this was an increase from the
year before, correct?
MS. MIURA: Correct.
MR. KANEALI`I-KLEINFELDER: Okay. I think we all are very aware of how
the property evaluations greatly affected our property taxes. And that's probably
the reason for the appeals, correct?
MS. MIURA: Correct.
MR. HARANO: I second that.
MR. KANEALI`I-KLEINFELDER: Thank you. I had a lot of phone calls
regarding property taxes, and I was trying to understand and work my way to the
process. And I appreciate both of your time and energy and help me answer
those, and the complaints from the community on property taxes. And I do hope
we see some drops this year.
And I saw that you guys attached some of the information from some of the
appeals, and the rise in the taxes due was fairly incredible in my eyes. And I
know this has been a hardship for our community. Any thoughts?
MS. MIURA: Can I clarify that the attachments you're saying to the report are
just the four complaints that were submitted; those complaints were either those
that filed late or did not file an appeal at all.
Page 3
CRCOC-I
January 4, 2023
MR. KANEALI`I-KLEINFELDER: Okay. I know a lot of people had a hard
time this year, and this is one of the hardships that we all faced. And I understand
it, but I wish there was—we have to look for some solutions in the future yeah.
But either way, I appreciate your time. Thank you for being here today,
Ms. Miura and Mr. Harano. I yield, Chair.
MR. HARANO: Yes, can I just add a few words?
MR. KANEALI`I-KLEINFELDER: Yes.
MR. HARANO: Yeah, the valuations was I think the biggest shock to the
appellants, both private citizens as well as commercial enterprises. I think it's a
need, oh yeah on the westside, the biggest need it seems like its housing for
residents. Yeah, you know, more resources of housing, it seems like it's being
turned into short term rentals. And I think there should be more regulations, as
far as short-term rentals are concerned. I know there's other municipalities across
the U.S. that is starting to enforce, simply because of the complaints from the
neighborhoods.
And also I'd like to say in closing, that the Council or County Government needs
to find other sources of revenue. Disturbing when in excess of 70 percent of the
annual budget comes from Real Property Tax. So we need to find better
alternatives, I think.
MR. KANEALI`I-KLEINFELDER: Thank you for that, and I do appreciate that
you're one of our members of our commission. And thank you for your services
as well, sir. Thank you. Chair, I yield for now.
CHR. VILLEGAS: Thank you, Council Member. Council Member Lee Loy.
MS. LEE LOY: Thank you, Chair. Ms. Miura, thank you for being here. In your
report you suggest a couple of legislative matters, and as the policy making body
here has anyone from the department maybe Deanna engaged in some of these
recommendations? One was a recommendation of the appeal fee, and then the
other was the agricultural committee. Is that something, go ahead Lisa.
MS. MIURA: Lisa Miura, Real Property Tax. I just want to clarify, this isn't my
report, this is the Tax Board of Reviews report and they're suggestions. The tax
appeal fee used to be less then when it came before Council years ago. It met a
lot of controversy as to whether it should even be there, if it should be zero, if it
should be more, if it should be refundable or non. So from our aspect we are not
proactively trying to bring it up, and to be fair among a lot of the boards through
the years. There's been quite a bit of good conversation and arguments back and
forth as to whether there should be a fee at all as well, and what that should be.
Page 4
CRCOC-I
January 4, 2023
In regards to the second item, which is the board recommends a review of the
nondedicated and dedicated agricultural use. We did sit on the agricultural
working review group committee for several years, and there were suggestions
that was made to County Council. But, I believe there are different Council
Members through the years that have looked at bringing it up, and some
discussions it had and then it sort of fails away. So none of these are being
actively pursued by Administration at this time. And I don't know if the Finance
Director has a different thought on that? No, okay.
MS. LEE LOY: Thanks Lisa. Deanna, I have a question. You know, part of our
various categories we know that agricultural kind of captures a lot along with
residential. Is there any direction that the Administration is going to take as far as
teasing out some of the various categories within Ag and or residential as
Mr. Harano mentioned? You know, we have short-term vacation rentals that are
captured within the residential category. Is the Administration going to be
looking at teasing out some of those?
(Note: At this time Finance Director Deanna Sako came forward to
address the members of the Committee.)
MS. SAKO: I think one of our challenges is having the appropriate information,
to be able to distinguish. So for an official short-term vacation rental that has a
permit from planning, no problem. For bed and breakfast and other types of
establishments that may not be permitted, then we don't really have a way to
determine that unless we go door to door. So that would be challenging to ensure
that we capture everyone in their appropriate groups. Ag you know, it's highest
in best use it's based on the base classification. So, you know, we're doing the
best we can with the information we have. So as Lisa said, we were part of the
Ag working group, and those recommendations were submitted to Council, and I
don't believe any action was taken.
MS. LEE LOY: Thank you. Thank you, Lisa. Thank you, Deanna. Thank you,
Mr. Harano for your work, I really did reflect. And thank you for providing your
chairpersons reflections. I think for the rest of my colleagues, I think it really
does sum it up on the kind of post of community and what our real property tax is,
how they are impacting us here locally. Chair, I yield.
CHR. VILLEGAS: Thank you, Council Member Lee Loy. Okay, I'm not sure
who was first here, but I'll go ahead and stick to the right. Council Member
Inaba.
MR. INABA: I think I was last, but real quick.
CHR. VILLEGAS: Okay.
Page 5
CRCOC-1
January 4, 2023
MR. INABA: Just for the administrative recommendations, I know it's from the
board, but how do we plan to or have you folks looked at this to see which of
these are the low hanging fruit that we can implement as we move forward
quickly? Sorry, Ms. Miura that was for you.
MS. MIURA: That's okay. We did look at them, and we look at them each year.
So some of them we already have been actively working on. I think some of the
bigger ones that has come up would be item 13, because some of them are just
their comments that we're presenting our cases well, but they recommend values
located on the bottom of the document be there. So we've already worked with
staff on all of those. And item 13 is in enforcing the petitions and the dedications
on agriculture. And then it comes back to the staff saying, you know, we need
more restrictions on it because right now it's very loose. And as I mentioned, I
know there's been some Council Members discussion on how best to go forward
on that.
And 14 the board commends the division for their effort to enforce homeowner
exemption and tax class. We are still pursuing to make sure that if there are
properties rented for less than 180 days, that they do not get the homeowner pit
nine which was quite a few of our appeals this year. And most of those did
withdrawal. We had 237 appellants withdraw their appeals this year, that wasn't
discussed earlier. In addition, number 18 is one that I believe several Council
Members were taking lead on. Because when the STVR (Short -Term Vacation
Rental) Code was written we had commented that it doesn't match what we have
to do, and what is considered a STVR or a vacation rental. So there has been
some action to try and correct that with the Planning Department.
MR. INABA: Okay, thank you. And then I'm looking at just for our legislative
matters they're very simple this time in comparison to what I think I remember in
previous reports. From the division standpoint other recommendations that came
previously, I don't think the Council acted too much on. Perhaps we can review
that together to see which of those recommendations still stand, and update the
code as necessary. But thank you so much, Mr. Harano, for your service and
Ms. Miura, for the explanation. Chair, I yield.
MR. HARANO: Thank you, Holeka.
CHR. VILLEGAS: Thank you, Council Member Inaba. Yes. Council
Member Kagiwada.
MS. KAGIWADA: Thank you, Chair. And thank you, Mr. Harano, for your
service and for being here. Since Council Member Lee Loy did point out your
chairperson reflections, I just had a question about that, because the examples that
we saw in the complaints seem to say that people were more concerned about
kind of the raising of their property values than specifically about the tax rates.
And in your Chairperson reflections you note that the information that you had,
Page 6
CRCOC-I
January 4, 2023
you thought the people were more concerned about the tax rates themselves and
not their property value. So, I'm just wondering since we don't have access to all
of those that you did, if you can just say a little bit more about that.
MR. HARANO: Well in terms of value, I think there's two values. One for
property tax, and one for when they want to sell the home or the property. It's not
the tax rate, but rather the large increase in the valuations that the resultant
product was a higher tax, so.
MS. KAGIWADA: Thank you that really clarifies, that makes a lot of sense to
me. Thank you so much for letting us know that. I yield.
MR. HARANO: Okay, thank you.
CHR. VILLEGAS: Thank you, Council Member Kagiwada. Council Member
Evans.
MS. EVANS: Thank you. Aloha, I was looking at your comments and
recommendations and there was number seven that stood out for me which hasn't
been talked about yet, and that is about how do we inform the community about
various programs that may give them relief on however we're accessing or
exemptions or whatever programs are available. And I wondered if the group
really drilled down on that a little bit more about how that would happen.
Because clearly one of the issues we have as government is letting people know
what programs and what's available to them.
And I know a lot of times people will tell me they sit down at a dinner table and
somehow it comes up what they're paying for taxes, and they maybe in the same
neighborhood and the difference in the taxes are horrendous. They'll go, what is
it, and then they start talking about dedication, and exemptions, and age. And
some people were like, well I didn't know that. So how do we let people know?
When we send them their annual assessment, do we put down on there like note,
note, note, you may qualify for this, this, this, and list all the different
opportunities?
MR. HARANO: I think that would be a good idea. But I think the first step
would be to have the residence or property owners let me clarify that property
owners, feel like they're in a partnership with the County Government. I don't
know if there is the trust factor that prevents individuals from taking that next
step. Whether it's looking at the County website or talking with their council
representatives. You know, whether it's maybe having one town hall once a
month, once a quarter, right. All of you Council Members, go talk to your
constituents. I don't know, but that something that I think would be a step in the
right direction. I think you need to have trust as well as feel like they are in a
partnership with government.
Page 7
CRCOC-1
January 4, 2023
MS. MIURA: If I could add to that. So with every assessment notice that goes
out and that goes to every owner on record with an address, there's always an
insert, we even changed the colors because we noticed people were just not
reading it. But it used to be blue, we changed it to yellow to get a little bit more
attention. We do present to the Board of Realtor Associations, to the Chambers.
And prior to covid there was a lot more meetings, we'd go to Lions Club, Rotary,
I mean just whoever would let us come and speak, we would do presentations
there. And it's also on our website. And I know not everybody goes to the
website, but if there are other suggestions for us we'd be happy to take that into
account.
I think it would be good if the public read what we sent. Because it talks about
agriculture, home exemptions, affordable rental, and the other programs that we
have. And I'm not sure how to reach them, we even post in the newspaper. You
know, we still also hear the same thing I never knew about the home exemption,
even though if they've owned it for 10 or 15 years and they've gotten that
assessment notice every single year.
MS. EVANS: Okay. Well yeah, I just think that especially young people there
first-time homeowners understanding kind of what they're getting into it does
make a difference. So thank you for your comments. And I have one more thing,
is there any impact on the cesspool situation, in terms of valuation?
MS. MIURA: So we go by the market value and we watch how the market reacts
to the values. And so we haven't seen a huge difference yet. But I am sure we
will start to see it more in the values as the years go on and you see more already
converted to septic and those that want to do any changes to their property
requiring it to have to be converted over. We haven't seen enough examples in
the sales yet, to have that impact. Commercial might be a different story, and I
haven't talked to the commercial appraiser this year if she's seen any sales
changes.
MS. EVANS: Okay. One last question is, so your appraisers are they strictly
using the for sales in the last year? You don't have to answer this right now, but I
really hope that your group has looked at how the appraisers evaluate. Because
there's different methods in terms of appraising and evaluating and I hope they
just don't stick to sales because we have this rush of people that were coming into
Waikoloa that I represent and they were offering $100,000 cash over what the
asking price was because there was no inventory. And so it was pushing values
up that were like crazy because of supply and demand. And I'd just be curious
and hopeful that you really look at the appraisal method and reconsider how we
reach that final assessment. But just a comment.
MS. MIURA: Okay, you would need to change the County Code, because the
County Code does have us go to market value. And supply and demand does
affect the sale prices. Yes, we do look at the market. But we're happy for all new
Page 8
CRCOC-1
January 4, 2023
Council Members to do a RPT 101, so we can show where in the code what we
have to follow.
MS. EVANS: Thank you.
CHR. VILLEGAS: Thank you, Chair Member Evans. Yes, Ms. Kimball.
MS. KIMBALL: Thank you, Chair. And thank you for raising that question,
Council Member Evans. Because I think, you know, understanding of the whole
relationship between appraisals and some of the benefits that we do have. And
tax rates is critical especially for new members as we're entering into tax season
here. And one of those things relating to market value and the impacts that it has
on property taxes is that protection, that three percent cap that we have on
homeowners. So even if surrounding values go up due to sales, if they're in the
homeowner's tax class already then there's that three percent cap on how much
their valuation can go up, if they're in the homeowner's class.
So one of the things that I wondered, you know, my district having a significant
number of properties that are in the ag dedicated or non -dedicated ag programs
they have the benefit of the reduced valuation of the land but they don't have that
three percent cap. But your kind of making a choice, so you're either saying I'm
going to have a lower value of my land because I'm going to put it in this ag
program or I'm going to have the protection of the cap. And it hasn't been
significant until this last year particularly. So this is a longwinded question to the
Administration, did you see a significant number of these appellants actually try
to want to switch to that homeowners text class so they had protection in the
future? Was that something you saw at all?
MS. MIURA: I wouldn't say that a lot of the appeals were based on that. Usually
we talk to them and we explain how it works, we did get quite a few complaints if
you will from homeowners that were doing active agriculture on their property.
That felt it wasn't quite fair that they were farming and living there, but
somebody who wasn't farming benefitted from the three percent cap. So I think
there was a lot of frustration about that due to the increase and values. Especially
on the improvement side because building cost so much more in the lastduring
covid that the increases were a little bit hard for various homeowners and farmers
living on their properties with three generations, maybe for the increase in their
taxes because the three percent cap didn't protect them.
MS. KIMBALL: Right. Thank you for bringing that up. And we've discussed
that a little bit in the past, but I think that is something that Council may want to
consider going forward is if they're homeowners and they're on the ag land,
maybe there's some sort of cap related there. I will say that I had been working
with Council Member Richards on some language around the dedicated ag, and
non -dedicated ag programs he's of course moved on. So I'm hoping to work with
Council Member Galimba to bring that ag perspective into what we're trying to
Page 9
CRCOC-1
January 4, 2023
do, and I hope to have something shortly for you folks around that side of things.
But thank you Commissioner for your work, and I'm sure it was very challenging
this year. And appreciate your time and effort in that capacity. So thank you
again. I yield Chair.
MS. VILLEGAS: Thank you, Chair Kimball. Anyone else?
MR. HARANO: Yes, this is Nelson Harano again.
MS. VILLEGAS: Okay.
MR. HARANO: I think this as a follow up to Council Person Evans, and in terms
of the cesspool. I don't know, you know, on the west side I speak just from the
west side and where I live. Honestly, I don't know how effective that cesspool
credit will be. I don't believe anybody that's living outside of the beach area
there's no streams or water ways here on the westside. But it's hard to come up
with what 15, 20,000 for a cesspool and convert over to septic. You know,
without some county help, I know there is a cesspool credit but it's only available
to water waste for beach homes if I'm not mistaken. It's very difficult to get local
people here to put out that kind of money, to convert over in terms of trying to
convert everyone over. I think it's going to be difficult.
CHR. VILLEGAS: Thank you, Mr. Harano. I definitely feel you on that, living
on the west side myself, and on a piece of property that I couldn't put in septic
system if I wanted to. Based on the structure of the property, and the stone, and
the grade. So I feel you on that unfortunately, it's one of the challenges we're
facing. With that I guess I'll just share my final comments here. And I guess
what resonates with me on this report and I just want to thank again, Ms. Miura
for your continued services and representation, and for you, Mr. Harano in
tackling something that we're in an unprecedented time.
The context of what happened in the last few years. And the worth of properties
verses the value they were being assessed at and sold at was unprecedented. We
were inundated with people from all over the country and the world who
recognized not just our State but our Island as one of the safest places to be on the
planet, during the time of a global pandemic which was taking people's lives. It
unfortunately created an environment for the disparity between the one percent,
and the rest of the world to be that much more highlighted. And those with cash
and the ability to work from home, usually in a digital context, had a lot more
flexibility and a lot more opportunity to move to places that they felt safer with
their families which is good, but it displaced our families.
We lost over 25,000 residents during that time. Their homes were sold, or they
decided this was a time to cash out and be able to leave and buy a home
somewhere else. Perhaps to not have a mortgage anymore. But the disparity that
was created not only affected our workforce, which we all know we have
Page 10
CRCOC-1
January 4, 2023
challenges with even here in our county government, but also, in our small
businesses.
I saw a real transition as this inundation of newcomers and exodus of our work
force and the sales of these properties. And as was pointed out, for those of us
who didn't get to—Lisa did a great presentation during the last term that went
over why some of these values went up so significantly. Because it was a
unprecedented time of properties and correct me if I'm wrong, Lisa but
commercial and some resort properties sold, that otherwise don't actually sell
very often. And so there were new values and assessed values that could be
utilized in order to then assess what the values of these other properties are.
I myself see, you know, we have our old school ohana's that have owned land for
upwards of hundreds of years or even decades and live with multiple generations
on their properties. And they're not thinking necessarily about what property
values and market rates and what not are happening. But what's going on in the
real estate industry was astronomical. And a lot of people made a lot of money,
and a lot of people lost places to live. And there's a balance in that somewhere,
but we are still trying to get back to that balance.
I hope, and Mr. Harano I cherish your honest comment of saying, you know,
communities trust in County Government. In government in general we are also
at a unprecedent time of challenges, in trust with government and division. But
you know, I feel for the tax office and the job they have to do based on the
numbers and the objectives; the objective spreadsheets and the things that are
written out there.
One suggestion I would have, and I appreciate all the comments from my
colleagues. And I look forward to moving forward, hopefully, Ms. Miura
working with you on potential code adjustments. But then we look forward to
how we take what we've learned during covid. And each one of us take
responsibility for the properties we hold and the jobs we have, and the long-term
regenerative future of our community and our lands. I'd like to see and
encourage. I really appreciate it in line -item number eight. Encouraging
organizations like the Board of Realtors, and the Chambers of Commerce and
other organizations who are directly working with new home and property buyers,
that part of that responsibility be on their shoulders to educate new homeowners
and property buyers as to what our tax codes are in this county; how those relate.
Ideally not to provide loopholes, but to provide authentic and adequate reflections
of where they fit in based on the property or the home their buying, or the
business, or whatever that's commercial or residential. But where they're
authentic and accountable tax rates should be according to that and what level
that's at for their kuleana to contribute to our community. So, just some
ramblings of my mind as we look at the objective and subjective context of these
Page 11
CRCOC-1 January 4, 2023
conversations. So with that, if no one else has any other comments, I'd like to
make a motion to close file on Communication 11, all those in favor?
Vote on Comm. 11: The motion to close file on Comm. 11 was carried
Filed by the following voice vote:
Ayes: Committee Members Evans, Galimba, Inaba
Kagiwada, Kaneali`i-Kleinfelder Kimball,
Lee Loy, and Chair Villegas — 8.
Noes: None.
Absent: Committee Member Kierkiewicz — 1.
Excused: None.
CHR. VILLEGAS: Thank you.
Comm. 36: REQUESTS A DISCUSSION WITH THE ADMINISTRATION REGARDING
THE CONSULTANT'S REPORT TO ASSESS THE BUILDING PERMIT
PROCESS
From Council Member Susan L. K. Lee Loy, dated December 13, 2022.
Motion to Close File: Ms. Lee Loy moved to close file on Comm. 36.
Seconded by Mr. Inaba.
CHR. VILLEGAS: With that we have Mr. Lee Lord and Mr. Steven Pause
here. I'm going to go ahead and
MS. LEE LOY: Chair if I may?
CHR. VILLEGAS: Yes.
MS. LEE LOY: Thank you. For the rest of my colleagues especially our new
Council Members, I provided to you in your pink folder Communication 36.1. In
an effort to help level set this conversation, contained within that packet is the
contract from the Mayor's Office in which it provided a scope of services for
Mr. Tinner. And what would be outlined as far as a report that would come back,
a copy of Mr. Tinner's report, and then a memo from our Director of Public Works
Mr. Steve Pause on the recommendations that were in the report and what the
department is doing to address them. And so it's my hope actually to start with
Mr. Lee Lord, to help walk us through the contract, and then hand it off to
Mr. Pause, to walk us through the report and the recommendations that were made.
Thank you, Chair. Mr. Lord.
(Note: At this time Managing Director Lee Lord came forward to address
the members of the Committee.)
Page 12
CRCOC-1
January 4, 2023
MR. LORD: Mahalo. Managing Director, Lee Lord. Thank you all, and Happy
New Year. Thank you, Chair Villegas. At the time this past summer, we were
looking at continuing to improve the processes and outcomes for building permits.
And we've made progress, but there was a lot of progress to make and continues to
be a lot of progress to make. And we decided to look at getting somebody from
outside, with a national and regional perspective, someone who had previously
valuated and knew what was needed in different regions for insuring permitting
and processes are correct and as best as they can be. It happened to be at the same
time that our former Director of Public Works was leaving. And so I took off the
task to finish that project, which was started by Mayor Roth also, because we did
want an outside perspective.
Many people have many opinions about what could make permitting process
better, but we wanted somebody with the experience. So we did do a search, we
went several different ways and we kept coming up with the same person,
Mr. Tinner. And so we started investigating him as to his experience and then
went into vetting him and looking at that.
So we did end up going ahead with a contract. Basically the contract was to
identify inefficiencies within the building division of the Public Works
Department, that may lead to delayed intake, processing, and issuance of a
building and or associated construction permits. We asked him to do things like
online research or permitting, and legal information, relative to building and
associated permits, as well as face to face interviews with building division,
permitting staff, and a limited number of permit applicants.
He did interviews with staff, between October Yd and 7h. He did staff interviews
which were representative of permit clerks, inspectors, plans examiners, division
managers, other departments, we also engaged in a survey monkey and asked the
community to document the recommendations that we've been hearing verbally.
There was very few new suggestions or concerns brought up, since they've been
brought up all along. He took all of that into consideration. He came and did his
site visit after lengthy research from the mainland. And we met with him, and of
course as I said, met with all the staff.
I had created a task plan which I shared with the County Council previously, with
all the steps and what we were looking for. And with the timeline that we would
have the report no later than November 15. And due to HIPAA (Health Insurance
Portability and Accountability Act) regulations, I can't explain why Mr. Tinner
delayed but we lost contact with Mr. Tinner because of a personal reason. But as
soon as he was able to, he got us the report. All be it late, but he got us the report.
So other than that, just to let you know since we got the report early December, we
really haven't sat down exactly with our schedule yet.
I will also be on Mr. Pause's task force for looking at the priorities, and the plan,
and actionable items. Looking at what interaction we're going to need with the
Page 13
CRCOC-I
January 4, 2023
Finance Department or possibly County Council, or what funds would come from
within Public Works. As well as working with Human Resources for those things
that Mr. Tinner suggested that we will be taking up. Unless anyone has any
questions for me about how we got to here, I will turn it over to Mr. Pause, because
he's fully embraced the whole process and has moved forward already.
(Note: At this time Director of Public Works Steve Pause came forward to
address the members of the Committee.)
MR. PAUSE: Thanks Lee. Steve Pause, Director DPW (Department of Public
Works). And joining me today is our Building Chief Julann Sonomura, as well as
our Building Deputy Chief Kelly Wilson. From a timing standpoint both of those
individuals have kind of come into their positions concurrent with launching and
performing this assessment by the outside consultant. So they've been engaged
from the beginning. As Lee said, the study or the assessment was initiated by the
Administration. And in broad terms their scope of work was to look at
inefficiencies or actually just look at ways we can get better
And Jim Tinner's methods included at least the survey monkey, but also just his
interviews with our clerks, our plans examiners, and our inspectors. The people
that are the frontline folks that are doing permitting review, as well as construction
inspection for residential and non-residential. I attempted with this
correspondence to kind of break down the information from Mr. Tinner's report.
Just in terms of what actionable recommendations came out of it, and I tried to
supplement it as well with a number of things that maybe some of those ideas
came out of conversations with Mr. Tinner. Some of them might have just been
internal conversations, recommendations; things that we know we needed to be
doing independent of his assessment and his recommendations.
Just to highlight the conclusions, and I guess I'll start before conclusions. We
found Mr. Tinner to be very engaging, very knowledgeable, good experience
working in government positions. Similar as plans examining inspectors, he did a
lot of fire inspections as well. I think at one point he worked for a fire department,
but good knowledge based. He seemed to also have a pretty good idea with epic
and inner-gov and the Tyler products that we use for our electronic permitting
system. And I would just say, you know, walking through his conclusions there
wasn't anything that was a terribly big surprise.
Things that, you know, in the end when the report came out, were a number of
ideas and a number of recommendations and conclusions that we've already
discussed. He did note, just kind of going through things, that we had a lot of open
positions. And that can't be any more true. I think right now our building
department is barely 60 percent staffed, which is a major challenge for us. He did
also note that in general based on his experience, the pay rate seems to be lower
here then what he is used to. And I think a lot of Jim's experience was in the State
of Washington, the northwest. He did have a large thought pattern
Page 14
CRCOC-1
January 4, 2023
recommendation, on supplementing our stuff or recommending that we supplement
our staff with our parry reviewers. And that's something that I'll come back to
here in a bit.
He noted that we could be better at written documentation policies, plans, and
procedures. And that's something that we had acknowledged early on, and I'll talk
a little bit about some of those steps that we're taking to improve that. But the
context was to be consistent, especially in our interactions with the public. And if
nothing else, allow ourselves a pathway to have a predictable application
timeframe. And when I say that and we'll talk a little bit more about this, but right
now if you were to ask the general public how long does it take to get a permit,
you could get any number of answers. And I think, it's beholding on us to get to
the point where we can communicate what a normal permit time should take. So,
that was something that he noted.
He made some comments about increasing review fees. So presently we charge
20 percent of the permit fee upfront with the application to perform the review.
And he said in general his thoughts were that number should be more like 60 to 65
percent. It's not an additional fee, it's just getting more money up front when you
begin the process. What's interesting too, and I don't remember the exact
numbers, but we do have a number of permits in excess of 1,000 permits where
we've approved applications and they've not been picked up. And under the old
program the old permitting system pre -epic you did not have to put money upfront
with your application. So we've done the review and not collected any money for
it and people have not picked up their permits, which I still find a little interesting.
Some other comments he made was around just improving the deployment of our
internal resources, and we had a lot of discussions and it was sort of outside of
concept of what you can and can't do from a union standpoint. He said that we
should be focusing on the more complex applications our structural engineer, and
maybe having the plans examiners do some of the lighter structural engineering
reviews. He made a comment to same thing with inspectors. You know, if you
got a building inspector going out for a framing rough end or where there's been
some plumbing rough end done, why can't the building inspector just look at the
plumbing while their there. Again, it becomes a bit more complicated, I don't
think it's quite that simple but those are some of the comments that are relative to
efficiency.
We've spent some time talking about PV (photovoltaic) permitting, and one of his
comments was why do you do a building permit for a PV insulation for roof
mount. And quite frankly, the building inspector doesn't go out there climb on a
ladder and go look at the roof mounts and supports and things like that. So, that
was something that I think we've taken to heart and we're looking at further.
He talked about something, and I've had conversations with folks, the lean
process. The lean process, I think, comes out of six sigma and maybe Jack Welch.
Page 15
CRCOC-1
January 4, 2023
But it's a process where you sit down in over a course of a structured several days
and you look at how do you do things. What is your process map look like. And
you take a serious look and say why am I doing this, is it adding value. It maybe
gets rid of comments about will we do this because this is the way we've always
done it. But I been involved in that in my previous life, working in the corporate
world. It's a very valuable process and I won't do it justice by trying to explain it.
Anybody can google it, but it's a strict way of really looking at how we do things.
And I don't think it's a bad idea, the reality of how we implement it that is
something that we can talk about further.
Mr. Tinner also had a very good familiarity with Tyler and with EnerGov. I
believe he mentioned maybe like there were 13, or 14 different government
agencies that he worked with that had used it. And he says that they were well
known in the world of electronic permitting, and he made statements that the pain
if you will that we're feeling, is very common for a roll out. I've been involved in
other software types of projects in my life, but typically it's a little bumpy. And he
said that what you're experiencing is pretty much normal, that the bugs eventually
get worked out. And we've had a number of hard conversations more recently
with EnerGov folks, with the Tyler folks. So, I'm confident that we're on a path to
fix some of the things that we've seen.
He said that another challenge with rolling out something this new is acceptance.
And I think I've been in front of most of you before certainly I don't want to call
you old timers, but the folks that have been established here previously in Council.
And we've talked about the change curve and the ability to just get past the push
back and getting to acceptance. And it can be bumpy, especially for something
like this. And he talked about that extensively and not just push back from the
pubic, but also from the users, from our own staff and getting them comfortable.
And, you know, we're a year and half into this, and there is light at the end of the
tunnel. I think things are getting better in that respect.
He talked about customization and it's pretty much something that he's seen all the
other agencies do. He seemed to think that we might of gone a little bit overboard
on some of our request for customization. So it's something he just kind of
highlighted, that's something we should take a look at. But in the next breath he
also mentioned that there were portions of this application that we just were not
using the technology, specifically on intake. And I think you heard me talk about
intake before that if we could make intake a bit more user software. In other words
instead of relying on people and go from okay, here's the first part of intake, you
can't go to B, until A is completely filled out properly. Whether it's your
forgetting colons, and TMK (Tax Map Key) numbers and things like that.
But he did stress that he really felt one of our solutions to improve the intake
process was just utilize technology. It's already built in which isn't presently
being used and then another one of his comments was he was a big fan of having
our Building Chief and our Deputy Chief more involved with the National
Page 16
CRCOC-I
January 4, 2023
Building Codes, The National Code Development, the IBC (The International
Building Code) and the ICC (International Code Council). And he said that was
pretty much the norm that he's seen in other locals where these folks really need to
be more involved in setting new standards.
So that in a nutshell kind of captures what most of the takeaways from his report,
as well from the conversations that we've had. I've highlighted in your package,
unless you want me to, I won't go through the details. But the short of it is that
we've picked up on a number of the recommendations that he's made, we're
working on them. I think it also kind of leads to, I tried to supplement Mr. Tinners
recommendations by a number of things that our building department is presently
working on. I'll highlight those for the group. Communication is a big one, and
again that wasn't maybe a direct recommendation, but we all know that we can get
better communicating, we all know we can do a better job of reaching out to
stakeholders.
Developing that predict ability that I've mentioned earlier. Meeting with the
design community which we've initiated, publishing checklists that will help
permit applicants in a designed community. So that when they submit
applications, we can get a more complete application. And really try to cut back
on the review schedule where, you know, we reject and we send back and it's got
to go through this cycle. Anything that we can do to kind of improve that and take
some of the time off of it.
We talked about some redesign to the EPIC (Electronic Processing and
Information Center) website. And one of them is to be able to put all the
information that we're generating for guidance, and checklist and things like that.
How do you get the information out? We'll schedule meetings with the
community, but we also just have to improve our website. And make it easier for
people to navigate to get some of these tools.
Staffing you know, we talk about that in great detailed, but it's still on of our
biggest challenges. We have initiated conversations with HR (Human Resources)
to try to get some support. Just in terms of recruiting in terms of incentivizing
candidates to come work here, I did reach out directly to the union and had a
meeting with them. And it did not necessarily go favorably well on the first
conversation, the concept of potentially bringing in third party reviewers to help
us. It's something that, there are other ways to look at it. But it's something that
we're going to have to go back and get a bit more creative, I think.
We talked about just coming up with ways to improve and cut back down on the
timing. Again, I get back to the review cycle. One of the simple things is just
consistently give guidance to plans examiners, as well as the filers of the plans that
design professionals when you submit changes. You know, simple things like use
a cloud for what you've changed and put a delta in the title block to make it easier
for our folks to be able to turn your plan reviews around quicker. So those are the
Page 17
CRCOC-I
January 4, 2023
main things I guess that I'd cover, and then I'd be happy to answer questions
because I'm sure there will be more. And if I can't answer questions, I'll be happy
to have one of my colleagues behind me with far more knowledge than me to come
up and answer them. Thank you.
CHR. VILLEGAS: Thank you, Director Pause, and Mr. Lord. Questions from
Council Members? Council Member Evans.
MS. EVANS: Thank you. This is for Lee Lord. When I read this and understand
all these recommendations, this is a huge amount of workload to ask of Steve Pause
and his staff when they're understaffed. Have you gone through that process of
prioritizing the recommendations? Do you have a couple that you're just really
focused on or is still everybody wheeling with the sure magnitude? I'm reading
this, I just don't know how you can do it.
MR. LORD: So we are going to have to come up with a timeline and a priority list
about how we're going to roll it out. Because we can't do everything first. So we
have not sat down yet for our first planning meeting at all. But you're absolutely
right, there's finances that are going to be needed for some of them that are going to
take some long-term planning. There're some human resources changes that we'd
like to do, which sometimes involves all the other counties and talking to people.
So we haven't had that first meeting yet, but you're right that's what we're going to
have to do and it is a big task.
So, I believe we've prioritized the staffing part first. So as Steven said, "We've
already started talking to Human Resources and it's on going." County wide there's
some initiatives that are going to help. But then there's specific things for Public
Works that we need to do just to get the staffing up, because we can't fix the system
and not have the people thereto help run the system. So, we're just at the
beginning phases. But Steven has and with his staff looked at some priority areas
that they could start on before we got to that point. But within the first next two
weeks since the new year started, we're having our planning meeting to start all of
that stuff. But if Steven wants to add what you have prioritized so far.
MR. PAUSE: Well the other comment I would add is, we are prioritizing as Lee
said staffing. And it's attracting staff and it's retaining staff. And it's providing
career paths from starting off as an Inspector I, II, III, IV. It's providing incentives
for people to acquire certifications. We had one of our Electrical Inspectors go
through and become ICC certified. Which is awesome except that, you know, our
current HR (Human Resources) rules and policies and things don't really allow us
to recognize that. So we need to work with HR to do those sorts of things. But
again, it's a long-term investment and I think it starts with the people.
Now some of the other things as I mentioned, it just seemed somewhat simple to
us. But it ties in with one of the recommendations with documentation, and
policies and procedures, and making things repeatable. But another portion of that
Page 18
CRCOC-I
January 4, 2023
is just simple checklist and talking to the design community and say look, you
know, we're not telling you how to do your job, but these are things we're looking
for when you put forth a set of plans. And being able to communicate that. I think
it's pretty simple, but it really hasn't been done. And to make those tools available
easily, without having to search all over the place.
So those are the sorts of things. And the other one I always come back to is intake.
Okay, we have to make the intake simple so that it doesn't tie up so much time for
our clerks, permit technicians, I guess, is what I'd like to call them. And a lot of
that is as Mr. Tinner pointed out is use the tool, use the software to help you do it.
And I think right now that is one of the areas that I know we do have an IT person
that's dedicated our EPIC person, if you will. That is working on some of those
things.
MS. EVANS: The second question is when you developed the contract that went
out for Mr. Tinner, did the Mayor have a working group or advisory group of
contractors and people that really helped in the writing of that?
MR. LORD: No, there was a few contractors that we did discuss it with, who's
been giving us feedback. And then we worked with the staff in Public Works also,
but we've been receiving feedback for a whole year. And so it kind of got
overwhelming and admiring as to what we need to look at. So we needed to have a
general plan as well as talking to Mr. Tinner about what he could provide. So
when we looked at it, we looked at the priorities of where we wanted to go. And
then we also asked Mr. Tinner to let us know, what he would suggest. So really it
was an assessment of where we are and how we could speed up the process, to
make it better for both the staff and for the people coming to get their permits.
MS. EVANS: So, is today the day that it's going public and the contractors and
everybody are seeing? I mean clearly people are really interested in how, I mean a
lot of people is interested in what changes are coming.
MR. LORD: Right.
MS. EVANS: So has this gone public today, or is it out there?
MR. LORD: It's out there, there's electronic copies going around. I know that
there are several community events, I think it was either Waimea. But there are
contractors that also have copies of it. So we're trying to put it online at this point
and time, so that anyone could come and look at it to see what the
recommendations are. Because we want to be as transparent as possible. So yes,
we've been giving anyone that's wanted a copy, a copy and we got good feedback
about it. So, the more we can share—
MR. PAUSE: To add to that, the contents of the report and even the memo that I
wrote with it isn't really, really, new. I mean we've been out. I've been before
Page 19
CRCOC-I
January 4, 2023
Council I think at least twice to talk about progress on permitting. We have
spoken to the West Hawaii Realtors, we spoke to back in late October the Hawaii
Chamber of Commerce. I've got another one I think with the Kona folks next
week, Kona Chamber of Commerce
So the communication, you know, at a high level we've been including, because
don't forget we first started talking to Mr. Tinner back in August, and we had a lot
of conversations. And even we had a debriefing I think, he was here the first week
of October? So I'm a copious note taker. So a lot of the information that he
shared with us then, has been in our calculus as we're moving forward. Some of
that is highlighted in my memo, but at the same time it's also the same message
that we've been putting forth. Wherever we can.
MS. EVANS: Thank you. Chair Villegas I have one more question, is that okay?
Other question is with staffing and working with the Human Resources. So this
would be for you, Lee. Do we as a County go to California, Washington State and
where the engineering schools and some of these schools are and are we out there
actively seeking new graduates that are coming out of school with engineering and
planning degrees etcetera. How do we get out there to track these people that
would come in at a lower salary, because they don't have the years of experience?
So maybe our qualifications might be a barrier, that's the other kind of a side note.
MR. LORD: So prior to you coming on board, the Council, our Human Resources
Director, did initiate relationships with the University of Hawaii (UH) and went to
several of their career days and those types of things and had some agreements
over there. Looking for engineers in specific because there's several departments
we have engineers, a need in all of those departments for engineers. But I think
Steven has had more extensive conversations in what areas we're looking at.
MR. PAUSE: It's just been a challenge. I'll give you an example. In the last year
and half since I've been with DPW, we've had four entry level engineers come and
go. From the mainland they come here the salary is what it is, the cost of living is
what it is, and then they just turnaround and leave. I think our best success has
been, I'm talking about on the engineering side, has been people that are from
here, through UH, who want to be here, who has family here that has been
probably the best success.
But the other challenge, you know, it's not just engineers, right. It's architects, it's
building inspectors. Maybe a building inspector starts off as a contractor learns a
trade and works their career, and then as they get a little older the legs hurt and
shoulders hurt and it's like oh gosh it's time to maybe step back from swinging
your hammer and becoming an inspector, an electrician, or plumber, the same sorts
of things. Those sorts of things aren't happening.
And I don't have that knowledge or wisdom as to why in conversations with
Page 20
CRCOC-I
January 4, 2023
Mr. Tinner, he points to the great recession in 2008, 2009, where it kind of broke
the chain. I can't wax poetic on that, but none the less I mean there's rational
reasons why that path is just not where it is. And again, it's not just money, and
it's not just cost of living it's just people have changed and people do things
differently.
MR. LORD: And I'd like to add for a fair salary of course, and our community.
One of our biggest challenges is that salaries are negotiable items and cannot be
changed unless we're in open negotiations. So we negotiate with the unions as a
County, with the other counties. So when we're proposing to raise the salary no
matter what position we're talking about in our County, we have to get consensus
and majority with the other counties to do that. So, I know there's been offers
from you all to help with that process when we're going through it. But that's one
of our challenges, because we're not technically in control of our own salaries and
that we have to do it as a group, and it's across the State. So not all counties feel
the same urgency we have at the same level that we have. So we have to work that
and work with our other counties to get through that. So that's one of the big
challenges around the money part.
MS. EVANS: Good to know. Thank you.
MR. PAUSE: If I could make one more statement, I should of brought this up
earlier. You know we have great staff. The people we have work hard and we've
challenged them. Yeah, we have a massive staffing shortage, but I've got
inspectors, plans examiners, and building clerks working overtime. It's not
sustainable, and I'm happy that they're willing to do that. But at some point, we
do need to go through that process and back fill. We're going to do the best we
can. And people are all kind of rallying, but it's been going on for a little bit and
as I said, I don't think it's sustainable. We need to find some solutions.
MS. EVANS: Okay. Thank you.
CHR. VILLEGAS: Thank you, Council Member Evans. Council Member
Kagiwada.
MS. KAGIWADA: Thank you. As you're looking at these staffing issues, it just
comes to mind from my personal experience that when I had my children and I'm
first going back to work one of the main things I looked at is the possibility of
working part-time. Fifty percent and then going to 80 percent, things like that.
I'm thinking with the way the pandemic has rolled out and the way people talk
about reprioritizing their work life balance, that some of these things might be
more enticing to people.
As we work to hopefully get some of the salaries more in line with what people
expect. Could there be some possibility working with Human Resources to offer
some more flexibility in schedules, based on say an 80 percent job where
Page 21
CRCOC-I
January 4, 2023
somebody can still take their kids to school every day and pick them up every day.
And be home in the late afternoon with their kid. Is that a possibility, have you
talked about that at all?
MR. LORD: I have not, I don't think Steven has either.
MR. PAUSE: Yes, I have.
MR. LORD: Okay, we're willing to put anything on the table with Human
Resources.
MR. PAUSE: We did meet with HR yesterday, and we've been having ongoing
conversations with them. I mean you bring up an excellent point, working
conditions, flexibility. I mean we do have flexibility for an eight-hour day, when
people come to work when they leave for work that's something that's been built
into the system. HR had drafted a work from home type of policy that is again
drafted, but it's in line with what you've brought up. And it's a particular
challenge for us, because building inspectors can't work from home, right, they got
to go on site. And we're front facing entity, so our clerks, we need to have a
minimum amount of staffing. But as you bring up, I don't think there's anything
that's off the table right now. We've got to get creative.
You know one of the great benefits of going to an electronic permitting system is
that it's electronic, right? All of our blubbing sessions you can work from home.
You know, I tell our plans examiners they can work from home anytime they want.
You know, if we can work through that, you know, process through HR. But
because they have jobs where they can work remotely, but again, that all has to
kind of get put into policy and HR has to do that. But part of the concept of
working with third party reviewers, same thing they don't have to be here in the
State of Hawaii if we could progress and get down that road. But, I think we still
have a ways to go.
MS. KAGIWADA: Thank you. I yield.
CHR. VILLEGAS: Thank you, Ms. Kagiwada. Yes, Chair Kimball.
MS. KIMBALL: Thank you, Chair. I have two questions and a comment. The
first question, you know, talks a lot about staffing, and it definitely comes out as
one of the key issues in both the report and your response. And I want to start by
acknowledging all the staff of DPW. It is a difficult job, you're front facing to
usually a lot of pissed of people. So, I appreciate it that there's a lot of hard work
there.
MR. PAUSE: I've not noticed that at all.
Page 22
CRCOC-I
January 4, 2023
MS. KIMBALL: I appreciate your optimist Steve, always have. I'd love to have
you kind of give an assessment. I'm hearing three different things with respect to
staffing. There's the actual number of people, there is the conditions of the work
environment, and then there's third maybe this—how well is the work that needs to
be done balanced with the positions as they are described and set up at this point.
And as Council Member Evans said, there's a lot to do here. And if there are other
things, but those are the top three, I kind of heard from what you guys have been
saying. If you were to prioritize those, is it bringing the bodies in the door, is it
working with HR, or do you think you can address them simultaneously?
MR. PAUSE: It's difficult to prioritize. I mean on the outset you say to yourself, I
have empty seats, I need bodies and seats. Some of our processes from an HR
standpoint are a bit antiquated. So we need to do some adjustments, and again, we
just begun that process working with HR to help us. I mentioned earlier gosh this
gentleman went out and got ICC certification, all on his own. We should be able
to encourage people to do that, we should be able to somehow work those things
into their PD's. So they get a bump, or they get some acknowledgement for that.
So it's difficult to really prioritize. I mean we need live bodies; we are front facing
so we have to have people to be able to respond to the public needs. We need to
maybe get more efficient with our processes which you've heard me talk about,
especially with respect to intake. The working conditions again it becomes a
matter of making sure that we have the right job descriptions and the right
positions. And that we provide opportunities to improve, to advance, you know, in
a career path.
And then we'd have to also, we can't just focus on getting new people we have to
take care of the existing people. So retainage is important. We actually lose as
many people to other departments, as we do anything else here. There's a
competition between a number of the departments especially when it comes to
technical people, whether it's architects, engineers, that's another challenge that we
have as well.
MS. KIMBALL: I'm just thinking about my own professional experience with
you've got a system that needs to keep chugging, chugging, chugging and to pull
time back to spend. Determining whether it's chugging, chugging, chugging in the
right way or could chug, chug, a little bit more efficiently, and you wouldn't have
to tweak the system as much. That effort spent on planning and evaluating process
so that you're not just throwing more people or more money or whatever to a
process that is maybe inefficient. As much as it can kind of be painful to do that,
that's kind of my vote. I support you as the director taking some time to evaluate
the process, evaluate those positions, and determine if they are appropriately
described and supported to get the work done that the department is supposed to
get done. So, I just wanted to let my support to spending that time on that part.
Page 23
CRCOC-I
January 4, 2023
MR. PAUSE: And I do appreciate the support and the patience that everybody has
here. It's challenging and it's not a quick fix. And part of what we're doing is
painful because we're changing the way things have always been, and then part of
it is we're also trying to make an investment. So that we, you know, in concert
with electronic permitting system and improved processes and things that we can
develop something that's going to be around and not fall apart.
MS. KIMBALL: Yeah. Managing Director, you know, certainly this is something
that actually has come true on some of the other departments. The other one I
think about is Planning, where there's not a career ladder per se for certain people
that had have a lot of time in there, but they can't elevate to the next step. So as
much as we can help, I think there's a lot of us that have interest as mentioned to
you. We spoke over the weekend, yesterday, we're here to help on that. The other
question I had still relating to staffing director, is part of the contractor assessment.
Did he speak with the employees about working conditions, and get
recommendations about that detailed aspect of it?
MR. PAUSE: He did speak with many, many, many employees. I think the report
documents he spent time with clerks, he spent time with inspectors, and he spent
times with plans examiners. I don't recall specific things that came out from the
comments about working conditions. I think it was just a lot of discussion about
how things are done and how things have been done, and I think he solicited their
input in their thoughts about how to make things better, and I think that was part of
what he was trying to reflect in his conclusions and recommendations.
MS. KIMBALL: The last thing, I just had a comment about having your Chief and
Deputy Chief perhaps being more involved in the International Building Code
process, also want to support that. Council Member Lee Loy knows this well, but
for the other new members, you know, that comes to us, we have to take it. We
can make it stronger, but we can't make it weaker. And there's a lot of code that is
written in there for municipalities that are not at all like ours. And so the common
example that gets brought up is the single wall construction and the fact that we
have to just build everything to death through a certain extent.
I will tell you it's my house, my husband is an architect, we went through the
whole building process it's never falling down. That thing is so over built, but we
make up. So if any of you are in a hurricane, you know, come to my house it's a
safe place to be. But this is one way of saying I really think that representation
from our community, understanding our environment; the things that we're doing,
because we got it addressed it at that very early step before it comes to the Council
for decision making. Hundred percent support that effort, so I'm hoping you guys
are willing to do that. But I do want to lend my support for that. Thanks Chair, I
yield.
CHR. VILLEGAS: Thank you, Chair Kimball. Yes, Council Member Galimba.
Page 24
CRCOC-I
January 4, 2023
MS. GALIMBA: I just wanted to ask you about, well I support your effort to like
streamline and make your organization lean and sort of build in better processes as
Chair Kimball was saying, you know, it's having to get away from the daily
routine. It's hard to then, you know, to make that time, but probably time well
spent if we can support you in doing that. So that's sort of that aspect of it. But I
wanted to sort of talk about almost like streamlining outside of the department, and
specifically in my district there's very, very, many unpermitted structures. There
always has been, probably always will be. But I wondered about your thoughts on
how we can help people to get their buildings permitted, which probably is not a
priority based on this? But it is a priority, I think, for our community.
MR. PAUSE: So, thanks for that question. We've made a lot of attempts to get
out there. Despite my comments earlier, we do get a few complaints and a lot of
those complaints are about our permitted structures. And with our staffing
shortage, I'm not making excuses, but we have to prioritize based on life safety.
So maybe the person living in a burned down house might get an inspection faster
than somebody complaining about their neighbor's lights being too bright.
But those are the sorts of things that we're confronted with and we are as best as
we can being active with respect to trying to run down issues of compliance.
Trying to talk to the people there and trying to come up with a path to compliance.
And then every once in a while, you get the ones that are just a bit more reticent to
really cooperate. And you know, we have a process with issuing notices of
violations and following up on that.
I would tell you that at least since I've been around, we've tried to make it a little
easier to follow-up with paperwork and work with people. Whereas the past, I
think there was a bit more hesitancy to issue notices of violation. Again, it comes
down to people again. You know, you may not want to share my challenges, but
you know, we only have two inspectors on the Kona side now and two permit
clerks. But we're working to resolve that, and we've got folks from Hilo that
maybe come around the island a little further. But there's still priorities, but again
it's a workflow, we'll do the best we can.
MS. GALIMBA: From the other angle of you know, people who build
unpermitted structures to have a place to live and like that aspect of it. And it's a
difficult thing. How do we help people? Like you've kind of mentioned how do
we help get to permitting their structures, which is a whole ball of wax. I think it
has a lot to do with the building codes and making them perhaps less over -built
and more affordable. Because I think there's a certain segment of the population
that just says, it's impossible for me to afford to build a permitted structure so I'm
just going to build something to live in. How do we bridge that gap? It's a
difficult one. I just wanted to ask you about it.
MR. PAUSE: Yeah, unfortunately I don't think I have an answer for you. We
have people who I believe fund their nose at the rules on purpose, and then we
Page 25
CRCOC-I
January 4, 2023
have other people that just don't know what the rules are, and we have other
people that just need a place to live. So I'm not sure how to best address everyone
of those, I guess in some respects the rules are the rules. But on the other hand, we
need to be sensitive and address each of those as they come along. But I don't
really know that I necessarily have a blanket answer that would help.
MS. GALIMBA: I certainly don't expect you, I just really wanted to bring that up.
Thanks for all your doing, it's a lot but it's good direction. So, thank you.
MR. PAUSE: Thank you.
CHR. VILLEGAS: Thank you, Council Member Galimba. Council Member
Goro Inaba.
MR. INABA: Hi, Director Pause, thank you. Just looking back on this process
with this outside consultant we paid $16,000 for. As we move forward, when do
think we might be able to see kind of that timeline that we talked about, as to how
we're going to attack these and priorities? Because it's not really broken down
necessarily by priority. Managing Director Lord?
MR. LORD: Thank you for the question, Council Member Inaba. Great question.
I'm hoping within two months there's going to be a lot of discussion, we have to
look at what resources we do have. But as long as people have the time and the
Administration there at Public Works, and from the Mayor's Office to meet there's
no reason we shouldn't have initial plan within two months. Because Mr. Tinner
kind of laid out what we should be doing to make it the best as possible. As well
as the staff have already seen all the recommendations. Mr. Pause and his staff are
well versed in what's there. You know, the low hanging fruit, and what's going to
take some coordination. But to come up with the plan, I would say you should
expect it within two months.
MR. INABA: Okay. Council Member Lee Loy, thank you.
MR. LORD: And I have to point out, that plan will have actionable items. We
need to say what our expected timeline is for the different recommendations, and
also who's going to take the lead on it and when it's going to get done. This isn't
something that's going to sit on the shelf, it hasn't sat on the shelf since they
received it at Public Works. But everything happens with an actionable plan, and
we help people stay accountable with those.
MR. INABA: Thank you. When did we get this report back from the consultant?
MR. LORD: When did we get it?
MR. INABA: Yes.
Page 26
CRCOC-I
January 4, 2023
MR. LORD: I think it was the first week of December, or the last week of
November.
MR. INABA: Okay.
MR. LORD: I don't think on this copy there's a date.
MR. PAUSE: Yeah, I don't recall, but that sounds about right.
MR. INABA: Okay. And maybe just a last statement regarding Council Member
Kagiwada's recommendation, perhaps we can look into that not just within DPW
but across the board. Because there's a lot of people who don't want to work nine
to five, but who might be looking. I know very capable and skilled folks that could
help fill those pukas across our County. So, perhaps Director Leopoldino can
check into that. Thank you so much Chair, I yield.
CHR. VILLEGAS: Thank you so much, Council Member. Yes, Council
Member Kaneali`i-Kleinfelder.
MR. KANEALI`I-KLEINFELDER: Thank you, Chair Villegas. Thank you,
gentlemen for the kind of overview of what we have in front of us. First question
scope of the contract, what is scope of the contract for him? I mean it's seems very
clear, but I want to make sure that I got it right.
MR. LORD: To identify the inefficiencies within the building division of the
Public Works Department that may lead to delayed intake processing, issuancing
of building and or associated construction permits. So we've asked them to look at
whatever it is in the department or with the adjoining departments that are involved
also to improve it for the public, and to help our staff do the best job they can with
the resources they need.
MR. KANEALI`I-KLEINFELDER: Okay. And did the contract go out to bid?
MR. LORD: No. We found a gentleman who, we had no other opportunities for
somebody with a national or regional experience that he's had in reviewing. So we
went with the sole source.
MR. KANEALI`I-KLEINFELDER: Okay. Was there any feedback from the staff
on these findings? Because I heard feedback from, and I'm not saying you're not
staff. I'm just saying a lot of these folks in the department that he interviewed and
he talked to, he had his interview processed and he came to you folks with his
report. But did the staff get a chance to look at his report and come back with
yeah, that makes sense, no it doesn't make sense this makes sense more sense in
this area?
Page 27
CRCOC-I
January 4, 2023
MR. PAUSE: So his findings were shared with staff, but there wasn't a draft
cycle. I think that's what you're saying. So we didn't give the staff a copy of the
report, and ask them to comment or make statements or review it and then give it
back to Mr. Tinner. We just pretty much got one summary report from him.
MR. KANEALI`I-KLEINFELDER: I think that would be helpful. I mean a lot of
his comments were how the process could be streamlined, how staff interactions
could be better, how our review process of the entire permitting system could be
better. And who better to ask, than the folks who do it every single day. That's a
thought I'm having from reading this.
MR. PAUSE: I agree with you. Thank you.
MR. KANEALI`I-KLEINFELDER: Okay. And then on the backside of all of
that, I'm looking this over I mean this has been a problem for decades, yeah. And
you inherited it, we all inherited it. We get a lot, I mean a good maybe 20 percent
of the phone calls I get are regarding building permit processes, inspections,
whatever it might be. We know it's a problem. And some of the findings in here
are things that I've heard Council Members on this Council say. I've heard people
in the design professional groups that I've interacted with say, I mean these are not
new things that I'm hearing.
So I'm glad that we have a plan, I'm glad we're looking at how we're going to
implement what has been found. But a lot of these we know already. In a very
nice way, I'm saying we know some of this, it's just time to get it done. And I
know we have a two month—we'll get an action plan together. I'd rather see you
guys just do it. If it's not something that requires a code change, and you could
internally just crack em and get it done. And then we can move on and make this
better.
MR. PAUSE: I agree with you. I think the simple stuff is as I talked about the
process changes and maybe some tweaks to the software on the intake side.
Things that we can do within our own control. It's a bit more difficult when we
start going into the realm of HR and changing position descriptions and maybe
creating those career paths and renumerating people for advancing their
certifications and things like that, that becomes a bit more challenging but non the
less I mean we just have to lay it out in front of us and get going. I agree with you.
MR. KANEALI`I-KLEINFELDER: Okay. One thing that worried me is, this is in
his report I believe this is from Tinner himself. In part of his report, I'm just going
to quote it, "I've worked with several jurisdictions that have implemented
EnerGov, and there's some ensuing issues." Yeah, just a lot of complaints across
multiple jurisdictions regarding Tyler and EnerGov as being efficient, cost
effective. And I know we're moving, it's done. But I'm worried that we may have
implemented a system that other jurisdictions find difficult to use or causes more
Page 28
CRCOC-1
January 4, 2023
problems than it fixes. That may not be helpful at all, but that's what I'm getting
from his report.
Sorry, here it is right here, I was looking too low in the document. Tyler's
EnerGov is known in the building permit industry as being particularly
problematic. That was, quote -unquote his words. And from what I've seen so far,
it seems like it has been for us. I know it supposed to streamline things, but it
sounds like this is problematic in other areas as well.
MR. PAUSE: Well, there's two things that came out of this. One of it and I'm not
sure if he made this statement in his report, or if it's in my notes from our debrief
which they have a tendency to over promise and under deliver over sell and under
deliver, okay. And that was very clear his opinion based on the number of systems
that he's familiar with. In our case, I'm not quite sure that applies as much as the
fact that we had our fair share of hiccups and stumbles with them.
We had one recently where we had a difficulty getting them to respond to us. And
Lee's absence yesterday we did have a, if you will a come to Jesus meeting with an
executive at Tyler, and he hears us loud and clear. He will be our account rep now
until April, May, when we get some of the little things that we want fixed. So
yeah, I don't want to make excuses for them. but yeah, it's never—we're a year
and half in, right, the bumps.
There's a whole lot less, like when you talk about our tickets, right. When we
have a problem with the software we submit a ticket, and the number of tickets has
gone down. I mean exponentially from the beginning of the year there was 140 the
first quarter, and I think the last quarter was like 30. So they're getting better,
we're getting more accustomed to it. But yeah, rolling out new software is never
painless.
MR. KANEALI`I-KLEINFELDER: Not at all. One thing that stands out to me in
this report, is his break down of our PV permitting system. And one note that I
saw was really, and I'm from the industry yeah. So I'm looking at his note and it
says that the building permit for a PV system, seems like it's more of a push to
take in permit fees then a matter of usefulness given the license professionals, who
are in the background of these documents. I thought that was very interesting.
Because I remember when it was just an electrical permit to get a PV system
approved. Then it moved to a building permit required, as well, and then a whole
ensuing process began, which has been difficult. And I understand there's reasons
why, but I'm wondering is that one of the recommendations that you're taking on
as being fruitful from this report?
MR. PAUSE: Yes. I mentioned that earlier in my opening statement, that we're
taking a hard look at PV permitting. I know especially in the beginning it was a
really big hold-up, so we really got better at like cranking out permits and getting
done faster. But I think this is another level of something to contemplate, you
Page 29
CRCOC-I
January 4, 2023
know, moving forward. As I mentioned, why are we issuing a building permit for
roof top mounted system, when the inspector doesn't come out and get up on the
roof. I mean yeah, we're definitely looking at that.
MR. KANEALI`I-KLEINFELDER: Thank you. Latitude Chair, if I could?
CHR. VILLEGAS: Yes.
MR. KANEALI`I-KLEINFELDER: There's a follow-up on that question. The
reasoning for it in his report was the weight per square foot was so small for most
systems that are coming into the County. About 95 percent of the PV systems, it's
all according to this report, that it almost doesn't make sense to have the building
permit for those systems. So not so much is the building inspector getting on the
roof, because we leave a ladder and rope for them at every single job. I'm hoping
they get on the roof. But are we burdening the industry with excessive permits,
just as a matter of collecting a fee. That was what I got from this report.
MR. PAUSE: Yeah, I don't know the answer to that. It doesn't seem like, I'm
following up the real property tax people. But it doesn't seem like we're that
desperate for money for an additional fee. I don't think that there would be any
calculated attempt to get more money out of it. I think it's just a matter of like us
maybe not being as efficient as we should be, when it comes to interrupting the
rules and going forward with permitting.
MR. KANEALI'I-KLEINFELDER: Okay. That comment really stood out to me,
maybe because of my background. But I would like to see some movement on that
end. We push for sustainability, green energy, renewable, as a state, this is one of
the big steps. This is an area of particular concern to me, and if we can make that
better and easier, let's do it. Thank you, Chair. I yield.
CHR. VILLEGAS: Fantastic. Thank you, Mr. Kaneali`i-Kleinfelder. Yes,
Council Member Lee Loy.
MS. LEE LOY: Thank you, Chair. I got stink looks already, it's close to lunch.
So I'll make this quick. Mr. Lord, go ahead.
MR. LORD: And before we finish it, I just want to make one comment. What you
don't see in the report and which I think is very important, is when working with
the staff through all this, the Administration and the direct staff of Public Works is
their belief and knowledge, and the fact that everything we're doing in permit
affects people's lives. There is people who are building houses out there who are
renting homes at high cost while they're looking at the mortgage coming down for
their new home, and want to get this done as soon as possible.
There are also contractors out there with 20 and 40 workers, who need the permit
to keep their 20 and 40 workers getting paychecks for their families at home. So
Page 30
CRCOC-1
January 4, 2023
seeing that when I'm working the staff is very heartwarming but it also points out
how much they care about what's in the community. And how important it is we
get this right, and we move forward with what we're doing. That's not in the
report, but that's one of the things I've learned much more through this process.
Thanks for letting me share that.
MS. LEE LOY: Thanks. I think Mr. Pause touched upon it too. We have a stack
of probably 1,000 permits waiting to get picked up. So if there's any contractors
out there looking to keep their 20 to 40 employees employed, they should contact
the building division and see what permits are available. I promise I'll make this
short. And I really just mahalo my colleagues, for really asking the question about
how to make this actionable. You know, I wrote on my notes here how do we eat
the elephant.
And so I also want to mahalo, Mr. Inaba, for really pushing on when we can get
kind of a prioritized list. And you said two months, which I calculated right into
our budget timeline. And then we also heard a lot of conversation about pay, pay
scales, ladders, and steps. And just as a thought for Mr. Pause, and you Mr. Lord.
If you could dovetail that prioritized list to be reflective in the department's budget
to show the actionable resources going into making this report work. I think would
go real efficient, because we have one Council Member going just do em, just do
em. I think that's where the rubber will meet the road is in the budget.
And I'm generally concerned about the latter and getting our respective plumbers,
and electricians certified. We just went through an entire code overhaul. And we
know that cycle is three years. And so the sooner we can get them certified, the
longer they'll have to utilize the code. Because in 2020, we just passed 2021,
we're going to go through a code update. And so all of our plan checkers, our
inspectors, our plumbers, our electricians are going to have to learn another code
and then enforce it.
And so I just wanted to put that all out there, on how we dovetail and electrify.
Not only this plan, but the resources and the process get it efficient. Because the
communication prior to this was how do we create more tax revenue, and for me
it's new construction. It's going to be new construction if we want to create more
tax space. So thank you, gentlemen, for being here. Julan, Kelly, thank you so
much for being here. I look forward to March and that budget cycle coming up.
Thank you, Chair. I yield.
CHR. VILLEGAS: Thank you. And with that just in closing real fast. I want to
thank both of you gentlemen for being here. I wanted to start off Mr. Pause by
thanking you for recognizing, you know, with the comments from Council
Member Galimba. And honoring the sensitive differences and circumstances when
it comes to permitted and unpermitted structures. In my district you know, I've
have had lots of conversations about some landowners who build what they want,
Page 31
CRCOC-I
January 4, 2023
do what they want, make as much money as they want off of it and just defy
permitting. And that's for profit, personal gain. And I think directly
And then you have those who are just looking to build a shelter, probably
something like what I grew up in, in South Kona. Which is just that a shelter, for
yourself or your family to be able to stay dry and safe and out of the elements.
And as we continue to navigate those differences and those discrepancies. I think
more highlighted now, because of the disparity between our one percent and the
rest of us. It's a really interesting time for how we utilize sensitivity in doing so.
I also want to recognize the synchronicity and the opportunity here, while this list
is so long and some of these challenges are so severe. I really like what Council
Member Lee Loy said about the potential with our salary commission coming
online, and the recognition of how far behind we may be. Inadequate pay for these
roles and positions, that synchronicity for how we can find those permit
technicians. And I really appreciate it, also, Council Member Kagiwada's
comments about getting creative with what these jobs entail. As we continue to
move further and further into a digital age and the flexibilities.
And one of the things we highlighted in our last Council meeting we had a
luncheon for the Commission on the Status of Women. And how that affects our
workforce so tremendously and what a instrumental part. And yet being a mother
and having been a single mom, and now being a grandmother. And helping my
daughter who works full-time, just how we balance those things. So I am really
hopeful that HR can help with some of that, and we can solve some of our
problems as a County by being forward thinking, and inclusive and flexible. I also
wanted to quickly say, is Robin, okay? Aloha to Robin.
MR. PAUSE: Yeah, she's doing better.
CHR. VILLEGAS: Oh, fantastic.
MR. PAUSE: Hope to see her in another couple of weeks.
CHR. VILLEGAS: Fantastic. Well just sending all of our aloha out to you,
Robin, and hope you continue to feel better. You know, in the prior terms of my
service, I had attended some of the meetings with the Kona Kohala Chamber of
Commerce permitting task force, and one of things then continually brought up
was, this third -party plan review services. I think there's some synchronicity there
too with this opportunity for digital and doing.
I understand as with a number of the other cutting-edge technologies or
opportunities, we'd like to utilize within our County for wastewater and what not.
We're having issues with the unions and their parameters, which I understand
protecting their staff and employees. So I just am thinking, it just popped into my
mind something for a timeframe of some kind of emergency proclamation
Page 32
CRCOC-I
January 4, 2023
potentially from the Mayor's Office, which allows for some catch up and clean up.
To provide some support for your staff as we get new staffed trained and online
and what not. So just a brainstorming idea. Not sure if it's possible or legal, or
what not. Perhaps there is, within very defined parameters.
If you know me, you know, I'm not one to say rubber stamp any and all buildings,
or developments or what not. Because we are already inundated. And my district
is at capacity, without further infrastructure improvements or projects that are
authentically workforce housing related. I look forward in the next two months
seeing the prioritization. I am very grateful as I look through the comments to see
the things you've already taken into consideration that you've already
implemented.
I see after having endured myself in the last term, the code updates and the ICC,
and the IRC, and the CC, and the make me crazy. That have sending some of your
staff members to those trainings, I think is a worthwhile investment, in order for us
to not be behind the eight ball, as we continue to move forward. So thank you for
this report. Thank you for moving forward. I look forward to hearing and learning
more. I also want to personally say that I appreciate your inspectors. They work
very hard, and very diligently and they are very passionate. I've had great working
relationships with them.
My one last question is, it's one of the dances we get to do between DPW and
Planning. But where is Planning in this process, and where is Planning and do we
get to have a consultation for improving on their participation side of things with
the EPIC system? Or is it the case as what's been stated that their kuleana is
completely covered as far as EPIC and the balls are dropping elsewhere?
MR. LORD: We have been currently meeting for quite a while, since we started
EPIC. I forget what's it's called, the coordinator or the leading meeting.
MR. PAUSE: So we have something called the steer committee, and we meet
every two weeks. And we have Planning, DPW, IT, and then there's a gentleman
from west side Tom Leonard participates in that as well. But as we kick off the
new year, we've put a little bit more structure into those meetings. But I can say
that, you know, Planning has their set of issues, we have our set of issues. We
share the same software, right?
I would say that like when you're looking at a global upgrade to the software, you
know, they got an IT person, we've got an IT person, and everybody kind of
coordinates. But in terms of like the nitty gritty of like some of our issues with
process and intake and things like that, I would suggest that they're separate from
Planning. And I wouldn't tell you that I have the knowledge of what some of
issues that you may have with them or some of their hiccups as well. So that
would probably be best discussed directly with them.
Page 33
CRCOC-1 January 4, 2023
MR. LORD: My guess is everything we're looking at on that committee will be
passed by Planning anyway so they'd know everything we're going through. And
if there is something, we work very well together with Planning and Public Works.
Works excellent so I'm not too worried but I understand the concern.
CHR. VILLEGAS: Thank you, I appreciate that and recognize that need for
synchronicity. Because having had some issues in past where they just kind of get
bounced back, I got bounced back and forth between departments under a different
Administration. It was a little bit challenging to understand where the buck
stopped. So I appreciate all of your comments. I also want to recognize in any
industry, sales job is to sell their product. And sometimes people who are really
good in sales, are really good at stretching the capacity. But then unfortunately
when it lands to those who have to execute, it becomes unfair and overly
burdensome. So I get that, and how that may have happened with this new system.
But thank you for your endurance, and your continued commitment to getting us
up to speed. And hopefully 2023 will be the year of some lava flows, and global
pandemics, and massive storms, and we'll have some opportunity to flow
smoothly, literally. Alright, thank you.
MR. LORD: Thank you.
CHR. VILLEGAS: And with that all those in favor?
Vote on Comm. 36: The motion to close file on Comm. 36 was carried
Filed by the following voice vote:
Ayes: Committee Members Evans, Galimba, Inaba
Kagiwada, Kaneali`i-Kleinfelder Kimball,
Lee Loy, and Chair Villegas — 8.
Noes: None.
Absent: Committee Member Kierkiewicz — 1.
Excused: None.
CHR. VILLEGAS: May I have a motion to adjourn?
ADJOURN- There being no further business, at 12:23 p.m., Ms. Lee Loy moved to adjourn the
MENT: meeting. Seconded by Mr. Inaba and carried by the following voice vote:
Ayes: Committee Members Evans, Galimba, Inaba
Kagiwada, Kaneali`i-Kleinfelder Kimball,
Lee Loy, and Chair Villegas — 8.
Noes: None.
Absent: Committee Member Kierkiewicz — 1.
Excused: None.
Page 34
CRCOC—i
CHR. VILLEGAS : We are adjourned.
Approved:
Ms. Rebecca Villegas, Chair
Communications, Reports,
and Council Oversight Committee
RV/rk
January 4, 2023
�' Itgt / � -3,
ate
Page 35