AN ORDINANCE AMENDING CHAPTER 5, ARTICLE 4, SECTION 5-4-7 AND
CHAPTER 5, ARTICLE 5, SECTIONS 5-5-4 AND 5-5-5 OF THE HAWAI`I COUNTY
CODE 1983 (2016 EDITION, AS AMENDED), RELATING TO CANCELLATION OF
CONSTRUCTION CODE PERMIT APPLICATIONS, PERMIT EXPIRATIONS, AND
PERMIT EXTENSIONS.
BE IT ORDAINED BY THE COUNCIL OF THE COUNTY OF HAWAI`I:
SECTION 1. Purpose. The function of the County construction code is to protect life and
safety by ensuring that construction projects are completed in alignment with the most current
construction codes adopted by the County. The purpose of this ordinance is to simplify,
standardize, and bring the timing elements for applications, extensions, and expirations of
construction code permits into alignment with the adoption of new construction code standards,
as required by State law.
SECTION 2. Chapter 5, article 4, section 5-4-7, of the Hawai`i County Code 1983 (2016
Edition, as amended), is amended to read as follows:
"Section 5-4-7. [Gan-cell-Mien] Withdrawal of application.
Upon notice to applicant that their application is ready for pick up with either a
"recommend for issuance" or"recommend return with correction,"the applicant shall have
thirty working days to pick up their permit or application respectively. If the permit
The4hilty-day-per-iod-will-begin-en-the-working day following the day that notification is
electronically sent to the applicant.
(b) Sixty days to take action on deficient application.
application is picked up.
(c) 1.80 days to obtain permit.
An application for a permit shall b- dee____d+_ 'i__. _ b__ __ _l a l 80 days fter the uc�•date
of filing, unless such applicat____h___ b____p _ea g oa f it it l b
ia
issued. The authority having ju
additional periods not exceeding ninety consecutive days each. Prior to the deadline,
demonstrate that circumstances beyond the applicant's control justify granting the
extension request.]
(a) An applicant shall have one hundred eighty days from the date of submission to obtain a
permit.
(b) The application will be determined to be abandoned and therefore withdrawn by the
applicant if after the one hundred eighty days:
(1) The applicant fails to submit, dispute, or otherwise act on errors or deficiencies noted
on the application; or
(2) The applicant fails to pay the permit fee.
(c) The authority having jurisdiction may grant one or more extensions of time for additional
periods not exceeding ninety consecutive days each, either at the request of the applicant or
at the discretion of the authority having jurisdiction. Requests by the applicant for
extension shall be filed in writing with the authority having jurisdiction prior to one
hundred eighty days after the date of submission.
(d) Restarting penult application.
If a permit application is [canceled,] abandoned and therefore withdrawn,the application
process must be restarted. In order to restart an application after [its cancellation,] it is
abandoned and therefore withdrawn, the applicant shall resubmit plans with alterations to
meet [current codes] provisions of this code in effect at the time of resubmittal and pay a
new plan review fee.
(e) If an application is [canceled,] abandoned and therefore withdrawn, plans and other data
submitted for review may thereafter be returned to the applicant or destroyed by the
authority having jurisdiction."
SECTION 3. Chapter 5, article 5, section 5-5-4, of the Hawai`i County Code 1983 (2016
Edition, as amended), is amended to read as follows:
"Section 5-5-4. Expiration.
(a) [Permits shall expire and become null and void:
;
(2) Permits issued to owner builders five years after the date of issuance of the permit;
(3) 180 consecutive days after the date of issuance, if the work authorized by the permit
is not commenced by such date; or
consecutive
t a . time after the date of issuance.]
All permits issued after August 17, 2020, shall expire, and become null and void six years
after the date of issuance of the permit.
(b) Upon expiration of a permit, all work shall cease and shall not be recommenced until a new
permit is obtained.
(c) If a permit expires prior to work being completed, an application for a new permit shall be
submitted."
2
SECTION 4. Chapter 5, article 5, section 5-5-5, of the Hawai`i County Code 1983 (2016
Edition, as amended), is amended to read as follows:
"Section 5-5-5. Extension.
[( ) T t1, e..t o f., strike e some :tl.er e.ent beyon.1 the ee tro1_of the contractor tL,e
owner that results in the aba de e„t f„ str ction, tho ut erity-having
jurisdiction may extend the d udlines for construction. An extension of time may be
granted for the length of time that work has been halted by strikes or other causes beyond
the control of the owner or contractor but in no case shall the extension exceed 180
consecutive days.
to the deadlines specified in section 5 5 4 and within seven calendar days after the
the delay, the effect en the performance f work, the time durir„which. efk. etually
suspended, and the portion or portions of the project affected.
granting or denying the request for extension.]
(a) An extension of a permit may be granted if the authority having jurisdiction finds that
circumstances beyond the permit holder's control have significantly impeded the progress
of the construction project, that construction is substantially complete, and that an
extension is justified.
(b) Requests for permit deadline extensions shall be submitted in writing to the authority
having jurisdiction at least thirty days prior to the peiliiit expiration date and an
acknowledgement by the authority having jurisdiction will be sent upon receipt. The
written request shall include:
(1) A written statement explaining how unforeseen circumstances have affected the
progress of the construction project.
(2) Supporting documentation demonstrating a legitimate need for the extension; and
(3) The duration of time during which work was suspended, and the proposed timeline to
complete the project.
(c) A decision on the request for a permit deadline extension will be sent within thirty days of
receipt of the request. If the authority having jurisdiction fails to render a decision within
thirty days of the request, the permit shall not expire until such time as a decision is
rendered.
(d) Permit extensions shall not exceed one extension of one hundred eighty days.
(e) A permit holder whose request for a permit extension is denied may appeal the decision to
the board of appeals within thirty days of receiving notice of the denial pursuant to section
5-11-3."
SECTION 5. Material to be repealed is bracketed and stricken. New material is
underscored. In printing this ordinance, the brackets, bracketed and stricken material, and
underscoring need not be included.
3
SECTION 6. Severability. If any provision of this ordinance or the application thereof to
any person or circumstance, is held invalid, the invalidity does not affect other provisions or
applications of the ordinance which can be given effect without the invalid provision or
application, and to this end the provisions of this ordinance are severable.
SECTION 7. This ordinance shall take effect on December 1, 2023.
INTRODUCED BY:
:l --Yee,'
1OUNC MEM ER, COUNTY OF HAWAI`I
INTRODUCED BY:q
,
.„....,
EMBER, HA Y OF AI`I
1
Kona , Hawai`i
Date of Introduction: November 1, 2023
Date of 1st Reading: November 1, 2023
Date of 2nd Reading: November 15, 2023
Effective Date: December 1, 2023
•
REFERENCE Comm. 516.10
4
;t..� #iY1.. 3�
OFFICE OF THE COUNTY CLERK COUNTY OF H aA fi Pw I I
County of Hawaii
Kona, Hawaii 2023 NOV 28 AN KY 02 •
(Draft 2)
Introduced By: Heather L. Kimball and ROLL CALL VOTE
Susan L.K. Lee Loy AYES NOES ABS EX
Date Introduced: November 1, 2023 Evans X
First Reading: November 1, 2023
Galimba X
Published: November 10, 2023 Inaba X
Kagiwada X
REMARKS. Kaneali'i-Kleinfelder X
Kierkiewicz X
Kimball X
Lee Loy X
Villegas X
6 0 3 0
Second Reading: November 15, 2023
(Draft 3)
To Mayor: November 17, 2023 ROLL CALL VOTE
Returned: November 28, 2023
AYES NOES ABS EX
Effective: December 1, 2023
Published: December:29 , 2023 Evans X
Galimba X
REMARKS. Inaba X
Kagiwada X
Kaneali'i-Kleinfelder X
Kierkiewicz X
Kimball X
Lee Loy X
Villegas X
7 0 2 0
I DO HEREBY CERTIFY that the foregoing BILL was adopted by the County Council published as
indicated above.
4
r
COUNCIL CHAI ERSON
pprove Disapproved this day
of N6-v eavl (�-c,e- , 20 Z C LERK
l
Q' t,' 84 (Draft 3)
Bill No.:
MAYOR, COUNTY OF HAWAI`I C-516. 10/PCPLUD-6
Reference:
Ord No.: 23 87