HomeMy WebLinkAboutCOM 0756.027 2022-2024 - Part 2 - CIP BudgetCOUNTY OF HAWAH
PART II
THE PROPOSED
CAPITAL BUDGET AND SIX -YEAR
CAPITAL IMPROVEMENTS PROGRAM
FY 2024 - 2025
BILL NO. 137, DRAFT 3
TABLE OF CONTENTS
Part II
THE PROPOSED CAPITAL BUDGET
AND SIX -YEAR CAPITAL IMPROVEMENTS PROGRAM
FY 2024 - 2025
CAPITAL BUDGET ORDINANCE
CAPITAL IMPROVEMENTS PROGRAM BY DEPARTMENTS
Animal Control and Protection Agency .........................7
Civil Defense.................................................................17
Department of Environmental Management................29
Department of Parks and Recreation ............................49
Department of Public Works.........................................73
Finance Department.....................................................115
FireDepartment...........................................................121
Hawaii Police Department...........................................127
Mass Transit Agency.....................................................145
Office of Housing and Community Development .......... 169
(This Page Intentionally Left Blank.)
Matt Kanetrli`i-Veihfelrter
Ha►,ai'i County Council
District 5
Phone No.: (808) 961-8263
irran.karrealii-kleiiifel (lei,@hmr,aiicottitiy.goi,
Finance Committee
Chair
Policy Conin ftlee Health, Safety, FVell-Being
Vice Chair
Hawai `i County Council
County of Hmvai `i
Haivai`i County Building
«
C-)
25 Aupunt Sheet, Suile 2405 • Hilo, Havvai'i 96720
r�
Cam-
W�r-_.
DATE: May 20, 2024;
<Y
TO: Heather L. Kimball, Council Chair
and Members of the Hawaii County CouncilFROM:
�rattKancali`i-Kleinfelder, Council Member
SUBJECT: Transmitting Bill No. 137, Draft 3; Proposed Capital Budget for Fiscal
Year 2024-2025
Attached is Bill No. 137, Draft 3. Bill No. 137 was amended to Draft 2 with the Mayor's
amended budget, transmitted via Communication No. 756.1, and then ftuther amended to Draft 3
with the contents of Communication Nos. 756.2, 756.3, 756.4, 756.5, 756.7, 756.8, and 756.9 to
add the following projects:
PROJECTS
APPROPRIATION
(in thousands)
AC - South Hawaii Animal Control Facility
2,500
DPR - James "Jimmy" Correa BallPield Upgrades
2,000
DPR - Hilo Skate Park (replacement FIS form to include State CIP)
1,000
DPR - Hawaiian Paradise Park District Park (Reapp.)
15,000
FIRE - Hawaiian Paradise Park Station (Reapp.)
10,000
DPW - Pahoa Village Sidewalk Improvement
2,000
DPR - New Waik6loa Gymnasium & Shelter
3,000
Net Increase
35,500
The above amendments increased the FY 2024-2025 Capital Budget by $35,500,000 and six
projects for a total of $531,335,000 and 67 projects. Bill No, 137, as amended to Draft 3, passed
first reading at the Special Meeting of the Council on May 16, 2024.
MKK/sc
Att.
Cornni. ko. T !
Ref. Ta: �/I I
at
Oate A 2 0 2024
llawai'i Counly is air Equal Opportunity Provider and Employer
CpJ+L� Oi h�
COUNTY OF HAWAPI STATE OF HAWAI`I
qTi GF.NI.i
BILL NO. 137
ORDINANCE NO. (DRAFT 3)
AN ORDINANCE RELATING TO PUBLIC IMPROVEMENTS AND FINANCING THEREOF FOR THE FISCAL
YEAR J U LY 1, 2024 TO J U N E 30, 2025.
BE IT ORDAINED BY THE COUNCIL OF THE COUNTY OF HAWAI'I:
SECTION 1. The following amounts to be received from the sale of general obligation
bonds, and other sources are hereby appropriated to the projects and for the purposes
designated in Section 2.
CAPITAL PROJECTS FUND
Funding Source
Federal Grants Receivable
State Revolving Loan Fund
State Capital Improvements Program
General Obligation Bonds, Capital Projects
Fund Balance
Private (Grants)
CBA / Other
Total
Amount
$44,910,000
$41,462,000
$7,000,000
$434,513,000
$2,S00,000
$950,000
$531,335,000
SECTION 2. The monies to be provided from the sources specified in Section 1 shall be
appropriated for the purposes and in the amounts as follows:
[The remainder of this page is intentionally left blank]
FY NO.
PROJECTS
APPROPRIATIONS
(in thousands)
FEDERAL GRANTS RECEIVABLE
202423
DPW - Mamalahoa Highway Rehabilitation, Part 1 & 3 - North Kona
9,600
202424
DPW - Kahakai Blvd Safe Routes to School - Keonepoko
2,000
202427
DPW - Kaiwiki #1 (26-5) &'Ope'a Stream (31-2) Bridges
5,000
202429
DPW - Waianuenue Avenue Bridge Modernization - HMGP
10,650
202432
DPW - Klauea Avenue Safe Routes to School - Waiakea
9,600
202448
MTA - Bus Stop ADA Compliance
1,000
202450
MTA - Pahoa Hub Planning and Construction
2,360
202452
MTA - Zero Emissions Infrastructure (Hilo Base)
2,200
202464
DPR - Hawaiian Paradise Park District Park (Reapp.)
2,500
Subtotal
44,910
STATE REVOLVING LOAN FUND
202428
DPW - 4 Mile Creek Bridge Reconstruction
2,667
202440
FIN - Kilauea Lava Recovery - State Loan FEMA Match
37,895
202450
MTA - Pahoa Hub Planning and Construction
900
Subtotal
41,462
STATE CAPITAL IMPROVEMENTS PROGRAM
202417
DPR - Hilo Skate Park
1,000
202463
DPR -James "Jimmy" Correa Ballfield Upgrades
1,000
202464
DPR - Hawaiian Paradise Park District Park (Reapp.)
5,000
Subtotal
7,000
GENERAL OBLIGATION BONDS, CAPITAL PROJECTS
FUND BALANCE
202401
AC - East Hawaii Animal Control Facility
20,000
202402
AC - North Hawaii Animal Control Facility
5,000
202403
CD - Land Mobile Radio Upgrade
2,000
202404
CD - South Point Building Replacement
100
202405
CD - Kulani Cone Building Replacement
200
202406
CD - New Emergency Operations Center
500
202407
DEM - Pahala Wastewater System
42,000
202408
DEM - Na'alehu Wastewater System (reappr.)
11,500
202409
DEM - Hilo WWTP Rehabilitation and Replacement
110,000
202410
DEM - Kealakehe WWTP Rehabilitation and Replacement
52,500
202411
DEM - Repair/Replacement of Wastewater Facilities
10,000
202412
DEM - Rural Transfer Station Repairs and Enhancements
2,000
202413
DEM - Landfill Gas Collection and Control System, WHSL
2,000
202414
DEM - Wai'ohinu Transfer Station Canopy Over Tipping Floor and Waste Trailer
250
202415
DPR - Repairs/Improvements to Facilities
10,000
202416
DPR - ADA Compliance
L 5,000
202417
DPR - Hilo Skate Park
5,000
202418
DPR - Afook-Chinen Civic Auditorium Upgrades
6,000
202419
DPR - Kea'au Community Center Replacement
1,000
202420
DPR - W.H. Shipman Park Master Plan
750
202421
DPR - Isaac Kepo'okalani Hale Beach Park
3,000
202422
DPW - Facilities Improvements
14,000
202423
DPW - Mamalahoa Highway Rehabilitation, Part 1 & 3 - North Kona
2,400
202424
DPW - Kahakai Blvd Safe Routes to School - Keonepoko
500
202425
DPW - Pauahi Street Bridge Reconstruction
800
202426
DPW - Bridge Repair
1,500
202428
DPW - 4 Mile Creek Bridge Reconstruction
1,333
202429
DPW - Waianuenue Avenue Bridge Modernization - HMGP
3,550
202430
DPW - Hurricane Lane Damage Projects
11,000
202431
DPW - Ka'ahakini Stream Bridge Reconstruction
700
202432
DPW - IGlauea Avenue Safe Routes to School - Waiakea
2,400
202433
DPW - Wailoa Stream Flood Control Channel Maintenance Dredging
3,000
202434
DPW - Land Acquisition
1,000
202435
DPW - Puhala Street Extension (Pikake PI. to S. Kopua Road)
550
202436
DPW - Ane Keohokalole Highway Phase III - Hinalani Drive to Ka'iminani Drive
4,000
202437
DPW - Post Office Road Widening
500
202438
DPW - Oneo Lane (Ali'i Drive to Kuakini Highway)
1,250
202439
DPW - Drainage/Flooding Improvement Projects, Islandwide
4,000
202441
HPD - Kea'au Police Station
1,500
202442
HPD - Public Safety Complex Facility Improvements
1,250
202443
HPD - Evidence Storage Warehouse
150
202444
HPD - West Hawai'i Evidence Warehouse
185
202445
HPD - East Hawai'i Firing Range & Training Complex
600
202446
HPD - Hawaiian Ocean View Estates Police Substation
150
202447
HPD - Holding Cell Improvements
600
202450
MTA - Pahoa Hub Planning and Construction
4,000
202452
MTA - Zero Emissions Infrastructure (Hilo Base)
6,000
202453
MTA - Zero Emissions Infrastructure (Kona Base/Maintenance Facility)
350
202454
MTA - Waimea Hub Planning and Construction
525
202455
MTA - Kailua/Kona Hub Planning and Construction
525
202456
MTA - Park and Ride Lots
1,070
202457
MTA - Hilo Base Yard Expansion (Maintenance -Office -Training)
325
202458
OHCD - Facilities Repairs/Maintenance and Renovation
1,500
202459
OHCD - Haihai Affordable Housing Project
15,000
202460
OHCD - Ainako Afforable Housing Project
16,000.
202461
OHCD - Ainaloa Affordable Housing Project
20,000
202462
AC - South Hawaii Animal Control Facility
2,500
202463
DPR -James "Jimmy" Correa Ballfield Upgrades
1,000
202464
DPR - Hawaiian Paradise Park District Park (Reapp.)
5,000
202465
FIRE - Hawaiian Paradise Park Station (Reapp.)
000
10t2,
202466
DPW - Pahoa Village Sidewalk Improvement
00
202467
DPR - New Waikoloa Gymnasium & Shelter
3,000
Subtotal
434,513
PRIVATE (GRANTS)
202464
DPR - Hawaiian Paradise Park District Park (Reapp.)
2,500
Subtotal
2,500
CBA / OTHER
202444
HPD - West Hawai'i Evidence Warehouse
415
202448
MTA - Bus Stop ADA Compliance
220
202449
MTA - Islandwide Bus Shelter
300
202451
MTA - Bus Stop Signage
15
Subtotal
950
Grand Total
531,335
SECTION 3. The Director of Finance shall open appropriate accounts for each project,
make monies available, and expend funds for the projects listed herein.
SECTION 4. The appropriation and authorization in Section 2 includes land purchase, plans,
site preparation, equipment purchase, improvements to land, and construction.
SECTION 5. The Mayor shall initiate authorized projects taking into consideration the
factors of public need, general financial condition of the general fund, highway fund, sewer fund,
parking meter fund, bikeway fund, beautification fund, vehicle disposal fund, solid waste fund,
golf course fund, geothermal relocation revolving fund, housing fund, and fair share
contributions as well as the County's general economic conditions.
SECTION 6. Severability. If any provision of this ordinance or the application thereof is held
invalid, such invalidity shall not affect other provisions or applications of the ordinance which can
be given effect without the invalid provision or application, and to this end, the provisions of this
ordinance are declared to be severable.
SECTION 7. As required by Section 10-6(a) of the Hawai'i County Charter, the estimated cost
of each capital improvement pending or proposed to be undertaken, the estimated operating cost,
and the pending or proposed method of financing are set forth in the attached Project Data and/or
Financial Impact Statement sheets.
SECTION S. This ordinance shall take effect on July 1, 2024.
INTRODUCED BY:
COUNCIL MEMBER, COUNTY OF HAWAII
, Hawai'i
Date of Introduction:
Date of 1st Reading:
Date of 2nd Reading:
Effective Date:
REFERENCE Comm. 756.27
(This Page Intentionally Left Blank.)
ANIMAL CONTROL
AND PROTECTION
AGENCY
MATTHEW RUNNELLS,
A D M I N I ST RATO R
(This Page Intentionally Left Blank)
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
Department: Animal Control and Protection Agency
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
in thousands)
FUNDING FORECAST BY FISCAL YEAR
in thousands
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private'
CBA,
Other"
Prior
Funds
Allotted
T s
Request
2024-25
2025-26
2026-27 i
2027-28
2028-29
2029-30
Beyond 6
years
1
East Hawal'i Animal Control Facility
20,000
1
20,000
a 20,000
2
North Hawal'I Animal Control Facility
5,000
5,000
5,000
3
South Hawaii Animal Control Facility
2,500
2,500
2,500
4
5
6
7
8
9
10
TOTAL
27,500
-
-
-
-
27,500
-
-
-
-
-
-
27,500
Created By: Matthew Runnells ' Private: Foundation Grants
Date: 1/2/2023 `" Community Benefit Assessments: Fair Share, Park Dedication, Etc. Other:.GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank.)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Animal Control and Protection Agency
2. SUBMITTER: Matthew Runnells DATE: 12/22/2023
3. PROJECT NAME: East Hawai'i Animal Control Facility
4. LOCATION (COUNCIL DISTRICT): 5
S. COUNCIL BENEFIT DISTRICT(S): Districts 1 through 6 (Long Range), Districts 6 through 9 (Interim)
6. TMK/CDP PLANNING AREA: 1-6-009:056
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 20,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
E] New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
21 Nonrecurring rehabilitation I
❑ Planning, feasibility, eng., or design study I
R1 Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
The animal boardingfacility is being used as a temporary facilityfor animal control which has different needs. This project will provide the infrastructure and facility for the Animal Control and
y g p y p l p y
Protection Agency (ACPA), including administration services.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: 2
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 2 Quality of . [Z Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
Yes: 0
N/A
Additional info: Inter -departmental collaboration occurs with all Building Projects because County agencies are the end -users.
12. LONG RANGE PLANS/
❑ Dept. Priority
I Details:
Comm. Value
Details: Maintenance and rehabilitation is required to maintain commercial values.
COMMUNITY VALUES, check
❑ General Plan
Details:
Admin Priority
Details: ACPA was created in 2023 but lacked the physical facilities to supports its mission.
at least one and all that apply,
provide details:
❑ CDp
Details:
❑ Multi Hazard
Details: Temporary facility does not meet Building Code and employee safety requirements.
Details:
❑Other Plans
Details: Provides central location in east Hawai'iforACPAservicesforthe community.
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? -ifYes: 0
DESCRIBE: County Chapter 4 covers the activities of Animal Control but specifically Section 4-3-1 covers Impoundment of Animals and providing care.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
Q Promotes energy and resource conservation
JE Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
L11Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
❑ project currently underway
Q Previ ously Appropriated
ElStaff available to manage project
ElExternal funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
ng
cquisition
/Survey
uction
20.000
$20,000
TOTAL:
$20,000
$20,000
& M COSTS (x $1000):
NDING SOURCE(x$1000):
O. Bond
rM(Grants)
20,000
$20,000
Revolving Fund
CIP
al
e (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
1
11 $20,000
$20,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Animal Control and Protection Agency
2. SUBMITTER: Matthew Runnelis DATE: 1/26/2024
3. PROJECT NAME: North Hawai'i Animal Control Facility
4. LOCATION (COUNCIL DISTRICT): 9
5. COUNCIL BENEFIT DISTRICT(S): Districts 1,2,3,8,9
6. TMK/CDP PLANNING AREA: Waimea
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 5,000,000
8. PROJECT ELIGIBILITY, ✓ all
0 Land acquisition
❑ Infrastructure improvement
El New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ,one:
that apply: 10
Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
El High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
The animal boardingfacility current) owned b Parker Ranch has been used for animal control services in the past b contract services but we are movingto purchase this property for the
Y Y Y p y p p p Y
agency for use and future facility buildings.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., /if Yes:
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: 0
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of El Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: FYI✓if
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
Yes: 0
N/A
Additional info: Inter -departmental collaboration occurs with all Building Projects because County agencies are the end -users.
12. LONG RANGE PLANS/
❑ Dept. Priority
Details:
Comm. value
Details: Maintenance and rehabilitation is required to maintain commercial values.
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details: ACPA was created in 2023 but lacked the physical facilities to supports its mission.
at least one and all that apply,
provide details:
❑ CDP
Details:
Multi Hazard
I
Details: Temporary facility does not meet Building Code and employee safety requirements.
Details:
El Other Plans
Details: Provides central location in north Hawo� i for ACPA services for the communiti
El mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: E
DESCRIBE: County Chapter 4 covers the activities of Animal Control but specifically Section 4-3-1 covers Impoundment of Animals and providing care.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
v Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
R] Project currently underway
❑Previously Appropriated
❑Staff available to manage project
❑External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
5,000
$5,000
Design/Survey
Construction
TOTAL:
$5,000
$5,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
5,0001
$5,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$5,000
$5,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Animal Control and Protection Agency
2. SUBMITTER: Matthew Runnells DATE: 5/6/2024
3. PROJECT NAME: AC -South Hawai'i Animal Control Facility
4. LOCATION (COUNCIL DISTRICT): 6
5. COUNCIL BENEFIT DISTRICT(S): 6
6. TMK/CDP PLANNING AREA: TBD
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 2,500,000
8. PROJECT ELIGIBILITY, ✓ all
Land acquisition
0 Infrastructure improvement
New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
[21 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
The southern region of the island does not currently have a facility for animal control and protection. This is one of the heavier trafficked areas for animal related calls and would greatly benefit
from this facility. This funding is for land purchase, planning costs, infrastructure development and a temporary facility while the permanent one is being built.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: [21
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: 21
Reduces risk of a documented hazard,
B. Service improvements, ✓all that apply:
n Access to n Quality of n Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
Yes: 7
N/A
Additional info: Inter -departmental collaboration occurs with all Building Projects because County agencies are the end -users.
12. LONG RANGE PLANS/
❑ Dept. Priority
Details:
M Comm. Value
Details: This is for initial purchase of property and infrastructure work and temporary structure
COMMUNITY VALUES, check
❑ General Plan
Details:
[JAdmin Priority
Details: ACPA was created in 2023 but lacked the physical facilities to supports its mission.
at least one and all that apply,
provide details:
❑ CDP
Details:
F1 Multi Hazard
Details:
Details:
❑ Other Plans
Details: Provides new location in Hawaii for ACPA services for the community.
❑Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE: County Chapter 4 covers the activities of Animal Control but specifically Section 4-3-1 covers Impoundment of Animals and providing care.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
[21 Reduces hazard risk
[2] Preserves/protects our natural/cultural env.
10 Cost benefit analysis
❑ Promotes economic vitality
121 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
JEJ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑ Can realistically encumber funds
List phases already completed: None to date
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond6
Years
TOTAL:
Planning
Land Acquisition
1,000
$1,000
Design/Survey
500
$500
Construction
1,000
$1,000
TOTAL:
$2,500
$2,500
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
2,500
$2,500
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$2,500
1
1
$2,500
(This Page Intentionally Left Blank.)
CIVIL DEFENSE
TALMADG E MAG NO,
ADMINISTRATOR
17
(This Page Intentionally Left Blank)
18
Department: Civil Defense Agency
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
(in thousands)
FUNDING FORECAST BY FISCAL YEAR
(in thousands)
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private*
CBA,
Other**
Prior
Funds
Allotted
This
Request
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond 6
years
1
CD - Land Mobile Radio Upgrade
2,000
1
2,000
2,000
2
CD - South Point Building Replacement
100
200
100
300
3
CD - Milani I Cone Building Replacement
200
200
100
300
4
CD - New Emergency Operations Center
SOD
Soo
500
31,000
32,000
5
CD-ATR025 Radio Channel Expansion
-
2,000
2,000
6
CD - LMR Core to West Hawaii
300
1,700
2,000
8
9
10
TOTAL
1 2,8001
1-
-
200
2,800
2,600
300
32,700
-
38,600
Created By: Bliss Kato * Private: Foundation Grants
Date: 1/18/2024 ** Community Benefit Assessments: Fair Shore, Park Dedication, Etc. Other: GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Civil Defense Agency
2. SUBMITTER: Talmadge Magna DATE: 12/29/2023
3. PROJECT NAME: CD - Land Mobile Radio (LMR) Upgrade
4. LOCATION (COUNCIL DISTRICT): 3,6
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 2,000,000
8. PROJECT ELIGIBILITY, ✓ all 10
Land acquisition
Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, -"one:
that apply:
21 Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
0 Information/communications tech.
[21 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Rehabilitate three existing land mobile radio (LMR) towers (Kulani Cone, New Ka'u Police Station, and Na'alehu Pasture). These towers have not received routine maintenance and as a result
have prematurely aged. This project will renovate the existing towers to extend their useful life to prevent catastrophic failure of the LMR system.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes:
Needed to continue current level of services.
A. Addresses public health/safety, ✓if Yes: ❑'
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
El Access to ❑ Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
Project will restore full operations to asset.
F. Fosters inter -departmental collaboration
Yes: 0
DPW
Additional info: Ensures first responder
communication which enables Police and Fire response in the affected districts.
12. LONG RANGE PLANS/
E Dept. Priority
Details: Maintaining the LMR System is an essential task.
❑ Comm. Value
Details:
COMMUNITY VALUES, check
El General Plan
Details: Coordinates the County's disaster preparedness and response program.
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details: Statewide Communications Intern erabilit Plan (SCIP . p y )
E] Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes:
DESCRIBE: Chapter 7 of Hawaii County Code requires Civil Defense to maintain the Land Mobile Radio system to provide first responder communications.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
10 Cost benefit analysis
I ❑ Promotes economic vitality
L] Strengthens and sustains our community
Additional info: Maintenance of the LMR system is an essential task identified in Chapter 7, Disaster and Emergency Management, of the County Code.
16. PROJECT READINESS, ✓all
10 Project currently underway
❑� Previously Appropriated
❑� Staff available to manage project ❑ External funds/resources ready to proceed
that apply:
0 Identified operating budget needs
21 Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
2,000
$2,000
TOTAL:
$2,000
$2,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
2,000
$2,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
,OD0 $2
22,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Civil Defense Agency
2. SUBMITTER: Talmadge Magno DATE: 12/29/2023
3. PROJECT NAME: CD - South Point Building Replacement
4. LOCATION (COUNCIL DISTRICT): 6
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: (3) 9-3-001-006
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 100,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
El Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
El Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
LI Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Purchase and install a replacement building at South Point that houses current radio system equipment. Recommend a composite building that is better suited to withstand the hard
environmental conditions in this location. Estimates shown here is the cost to install the structure at the Land Mobile Radio Site.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ,if Yes: Z
Needed to continue current level of services.
A. Addresses public health/safety, ✓if Yes: ❑
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to ❑ Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and maintains services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, /if Yes: ❑
Necessary repaidmaintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: El
DPW
Additional info: The Land Mobile Radio (LMR) components require a climate controlled environment that is protected from the elements. The current structure does not adequately provide this environment.
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Maintaining the LMR System is an essential task.
❑ Comm. value
Details:
COMMUNITY VALUES, check
Q General Plan
Details: Coordinates the County's disaster preparedness and response program.
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑Multi Hazard
Details:
Details:
0 Other Plans
Details: Statewide Communication Interoperability Plan (SCIP).
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REIXD? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: 0
DESCRIBE: Chapter 7 of Hawaii County Code requires Civil Defense to maintain the Land Mobile Radio system to provide first responder communications.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I ❑ Promotes energy and resource conservation
2 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
I ❑ Promotes economic vitality
JLd Strengthens andsustains our community
Additional info: Maintenance of the LMR system is an essential task identified in Chapter 7, Disaster and Emergency Management, of the County Code.
16. PROJECT READINESS, Val I
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budge[ needs
❑Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000): IF
Prior Funds Allotted
(not lapsed) IL
This Request
FY 24-25 I
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
200
$200
Construction
100
$100
TOTAL:
$200
$100
1$300
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
200
100
$300
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$200
$100
1
$300
10
(This Page Intentionally Left Blank)
County of Hawairi
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT.AND DIVISION: Civil Defense Agency
2. SUBMITTER: Talmadge Magno DATE: 12/29/2023
3. PROJECT NAME: CD - Kulani Cone Building Replacement
4. LOCATION (COUNCIL DISTRICT): 3
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: (3) 9-9-001-034
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 200,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
0 Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
0 Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Purchase and install a replacement building at Qlani Cone LMR site that houses current radio system equipment. Recommend a composite building that is better suited to withstand the harsh
environmental conditions in this location. Estimate shown is the cost to install the structure at the Land Mobile Radio Site.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bidg., ✓if Yes: 21
Needed to continue current level ofservices.
A. Addresses public health/safety, ✓if Yes: U
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and maintains services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
Yes: [21
DPW
Additional info: The Land Mobile Radio (LMR) components require a climate controlled environment that is protected from the elements. The current structure does not adequately provide this environment.
12. LONG RANGE PLANS/
4 Dept. Priority
Details: Maintaining the LMR System is an essential task.
[]Comm. value
Details:
COMMUNITY VALUES, Check
❑ General Plan
Details: Coordinates the County's disaster preparedness and response program.
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑� Other Plans
Details: Statewide Communications lnteroperability Plan . (SCIPJ
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: �
DESCRIBE: Chapter 7 of Hawaii County Code requires Civil Defense to maintain the Land Mobile Radio system to provide first responder communications.
15. SUSTAINABILITY FOCUS, ✓al I that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
121 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
10 Promotes economic vitality
Ll Strengthens and sustains our community
Additional info: Maintenance of the LMR system is an essential task identified in Chapter 7, Disaster and Emergency Management, of the County Code.
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
7 Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑Can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
200
$200
Construction
100
$100
TOTAL:
$200
$100
1$300
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
200
100
$300
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$200
1 $100
1
$300
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Civil Defense Agency
2. SUBMITTER: Talmadge Magna DATE: 1/18/2024
3. PROJECT NAME: CD - New Emergency Operations Center
4. LOCATION (COUNCIL DISTRICT): 2
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Pending
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 500,000
8. PROJECT ELIGIBILITY, ✓ all
❑Land acquisition
� Infrastructure improvement
El New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation I
CI Planning, feasibility, eng., or design study
0 Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
The Civil Defense Agency program have maximized capacity of the current EOC which was built circa 1992 and operations exceeds capacity during activations. New Emergency Management
programs and strategies requires a facility that can support a greater number of personnel engaged in training, community engagement, planning, information dissemination and operations
coordination without impacting each other. A facility designed with purpose to provides ace for these services will enable the County to meet FEMA Mission Goals for Emergency
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., -'If Yes: [21
Addresses anticipated future need.
A. Addresses public health/safety, ✓if Yes: LJ
Eliminates a documented hazard.
B. Service improvements, /all that apply:
❑ Access to 9 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, /if Yes:
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: 0
DPW
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: This facility enhances Civil Defense's ability to provide emergency monageme
❑ Comm. Value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
El Other Plans
Details: County Charter requires the County to have an EOC.
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REgD? /if Yes: ❑
DESCRIBE:
24. LEGAL MANDATE? ✓if Yes: E
DESCRIBE: Chapter 7 of the Hawaii County Code and HRS 127A-5 requires us to establish, operate, and manage/maintain the emergency operations center
25. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
Preserves/protects our natural/cultural env.
10 Cost benefit analysis
❑ Promotes economic vitality
JU Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
ElExternal funds/resources ready to proceed
that apply:
0 Identified operating budget needs
❑ Can realistically encumber funds
List phases already completed:
Additional info: Civil Defense will be applying for the FEMA Emergency Operations Center Grant Program during this fiscal year.
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
11
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
500
$500
Land Acquisition
Design/Survey
500
$500
Construction
31,000
$31,000
TOTAL:
$500
$500
$31,000
$32,000
18. O & M COSTS (x $3000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
500
500
$1,000
State Revolving Fund
State CIP
Federal
31,000
$31,000
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$500
$500
$31,000
$32,000
(This Page Intentionally Left Blank)
DEPARTMENT OF
ENVIRONMENTAL
MANAGEMENT
RAIVIZI MANSOUR,
DIRECTOR
29
(This Page Intentionally Left Blank)
30
Department: Environmental Management
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
(in thousands)
FUNDING FORECAST BY FISCAL YEAR
(in thousands)
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private"
CBA,
Other""
Prior
Funds
Allotted
Is
Request
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond 6
years
1
DEM- Pahala Wastewater System
42,000
9,785
42,000
51,785
2
DEM- Na alehu Wastewater System (reappr.)
11,500
2,034
11,500
94,500
108,034
3
DEM - Hilo WWTP Rehabilitation and Replacement
110,000
1
27,066
110,000
1
137,066
4
DEM - Kealakehe WWTP Rehabilitation and Replacement
52,500
52,500 1
52,500
5
DEM- Repair/Replacement of Wastewater Facilities
10,000
7,736
10,000
10,000
10,000
10,000
10,000
30,00o
67,736
6
DEM- Rural Transfer Station Repairs and Enhancements
2,000
10,160
2,000
2,000
2,000
2,000
2,000
2,000
22,160
7
DEM - Landfill Gas Collection and Control System, WHSL
2,000
4,000
2,000
2,000
8,000
8
DEM- Waiohinu Transfer Station Canopy Over Tipping Floor and Waste Trailer
250
250
3,000
3,250
9
DEM - Kealakehe Scrap Metal Site Remediation Phase 2
250
Soo
500
1,250
10
DEM - Replacement of Kona Baseyard Building
600 -
2,000
2,600
11
DEM - Replacement of Waimea Baseyard Building
1
200
400
2,000
2,600
12
DEM- Leachate Mitigation System, Hilo TS
2,000
2,000
13
DEM- Pua Sewer Pump Station Force Main Replacement
3,930
40,000
43,930
14
DEM- Kula'imano & Papa'ikou Dewatering and Barminuter Replacement
3OD
8,000
8,000
16,300
15
DEM-Improvements to East Hawaii Sort Station
270
4,500
4,770
16
DEM- Leachate Mitigation System, EHRSS
250
2,000
2,250
17
DEM- Leachate Mitigation System, East Hawai'I Stations
10,000
1
10,000
18
DEM- Wailoa SPS Renovation & Dual Force Mains
2,000
20,000
1 22,000
19
DEM- Kaumana Gardens Collector Sewer
6DO
6,000
6,600
20
DEM- Hilo Scrap Metal Site Remediation
16,000
1
16,000
21
DEM - Replacement of Kailua Disposal Area
600
1,000
1 2,000
3,600
22
DEM- Replacement of Hilo Disposal Area
600
1,D00
3,ODO
4,600
23
DEM- Leachate Mitigation System West Hawaii
5,00D
5,000
24
DEM- Pua SPS Renovation
2,873
32,000
34,873
25
DEM- Ainako Aina Nani Collector Sewer
1
1
250
10,000
10,250
26
DEM- Alnako Interceptor Sewer Phase 2
200
10,000
10,200
27
DEM - Pauka'a SPS New Force Main
800
8,000
8,800
28
DEM - North Kona SPS, FM, Hina Lani Gravity Sewer, West Hawaii Business Park Gravity Sewer
2,701
1,000
20,000
23,701
29
DEM - Onekahakaha SPS Renovation and Dual Force Mains
12,000
12,00D
30
DEM- Mlea SPS Renovation and Dual Force Mains
10,000
10,000
31
DEM- Kealakehe Wastewater Treatment Plant R-1 Upgrade
13,689
40,000
53,689
32
DEM - Kalanlana'ole Collector Sewer Phase II
12,000
12,000
33
DEM - Kula'imano WWTP Upgrade
37,000
37,000
34
DEM- Papa'ikou WWTP Upgrade
120,000
20,000
35
DEM - Wailuku Force Main and Gravity Sewer Replacement
16,000
16,000
36
DEM - KeopO FM Replacement/SPS Renovation and Relocation
2,000
2,000
37
DEM - Kealakehe SPS Renovation and Force Main Replacement
15,000
15,000
38
DEM - Pu'u'eo Gravity Sewer Replacement
8,800
8,800
39
DEM - Lanihau SPS Upgrade
3,000
3,000
1
TOTAL
230,250
1
84,544
230,250
1 112,550
77,650
47,300
50,250
95,000
173,800
871,344
Created By: Robin Bauman " Private: Foundation Grants
Date: 3/27/2024 "" Community Benefit Assessments; Fair Share, Park Dedication, Etc. Other: GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Department of Environmental Management - Wastewater Division
2. SUBMITTER: Chris Sparber, P.E. DATE: 3/25/2024
3. PROJECT NAME: DEM - Pahala Wastewater System
4. LOCATION (COUNCIL DISTRICT): 6
S. COUNCIL BENEFIT DISTRICT(S): 6
6. TMK/CDP PLANNING AREA: 9-5/Ka'u
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $42,000,000
S. PROJECT ELIGIBILITY, ✓ all
0 Land acquisition
0 Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
El Info rmation/co m muni cations tech.
0 High ElMed. I--]Low
10.. PROJECT/PROGRAM
DESCRIPTION:
New treatment and disposal facilities to replace C. Brewer plantation LCC sewer system. Includes planning, design, and construction for the closure of two (2) Large Capacity Cesspools (LCCs).
The LCCs are currently owned and operated by the County of Hawai'i. Project will meet the legal requirements of executed Administrative Order on Consent (AOC).
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., 'if Yes: 0
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: 0
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to 0 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: 0
Necessary repair/maintenance/replacement per
maintenance plan/schedule.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Expand sewer service to underserved and underepresented community.
[]Comm. Value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? /if Yes: 0
DESCRIBE: Federal EPA grant requires 45% match
14. LEGAL MANDATE? ✓if Yes: 0
DESCRIBE: Compliance with Administrative Order on Consent (EPA Docket No. SDWA-UIC-AOC-2017-0002).
15. SUSTAINABILITY FOCUS, ✓al I that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
0 Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
Promotes economic vitality
10 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
0 Project currently underway
0 Previously Appropriated
0 Staff available to manage project
❑External funds/resources ready to proceed
that apply:
❑ identified o eratin budget needs
f operating 9
Can realistically encumberfunds
❑ Y f
List hoses already completed: Plannin Des? n in ro ress
P Y P g/ 9 progress
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
285
$285
Design/Survey
7,658
$7,658
Construction
1.842
42,000
$43,842
TOTAL:
$9,785
$42,000
$51,785
18. O & M COSTS (x $3000):
19. FUNDING SOURCE (x $3000):
Cty G.O. Bond
3,754
42,000
$45,754
State Revolving Fund
4,189
$4,189
State CIP
Federal
1,842
$1,842
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$9,78511
$42,000
1$51,785
Other Roads
Major Roads
Naatehu-Pahala Sewer Lines
6" 0 Naatehu-Pahala Sewer Manholes
4" Naatehu-Pahala LCCs
3" Naatehu-Pahala Cleanouts
Pahala Wastewater System
FY 24-25 CIP Project
1:9,028
0 0.1 02 0.4 rw
0 0.15 03 08km
0 Open9treelMap Im"I cartcuWm, CC GY SA. Dmig Goehmq
lwa l County
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENTAND DIVISION: Department of Environmental Management - Wastewater Division
2. SUBMITTER: Chris Laude, P.E DATE: 3/25/2024
3. PROJECT NAME: DEM - N5'51ehu Wastewater System (reappr.)
4. LOCATION (COUNCIL DISTRICT): 6
5. COUNCIL BENEFIT DISTRICT(S): 6
6. TMK/CDP PLANNING AREA: 9-5/Ka'G
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $11,500,000
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
OInfrastructure improvement
FZ] New bldg., structure, or addition
9. PROJECT URGENCY/NEED, /one:
hat apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
30. PROJECT/PROGRAM
DESCRIPTION:
New treatment and disposal system to replace C. Brewer plantation sewer system including closure of two (2) existing Large Capacity Cesspools which are all currently owned by the County of
Hawai'i. Required by ACC.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current servicesforunderservedarea/demographic.
A. Addresses public health/safety, ✓if Yes: 0
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of 21 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: 0
Necessary repair/maintenance/replacement per
maintenance plan/schedule.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Expand sewer service to underserved and underepresented community.
❑Comm. Value
Details:
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Admin Priority
Details:
least one and all that apply,
provide details:
❑CDP
Details:
[]Multi Hazard
Details:
Details:
El other Plans
Details:
❑ Miti anon Plan
g
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: 0
DESCRIBE: Compliance with Administrative Order on Consent (EPA Docket No. SDWA-UIC-AOC-2017-0002).
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
0 Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
0 strengthens and sustains our community
Additional info:
16.. PROJECT READINESS, ✓all
0 Project currently underway
❑ Previously Appropriated
0 Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
2 Identified operating budget needs
El can realistically encumber funds
list phases already completed:
Additional info:
27. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
1,500
$1,500
Land Acquisition
1,000
$1,000
Design/Survey
2,034
9,000
$11,034
Construction
94,500
$94,500
TOTAL:
$2,034
$11,5001
$94,500
1
$108,034
18. 0 & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
1,284
11,500
94,500
$107,284
State Revolving Fund
750
$750
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$2,034
$11,5001
$94,500
1
$108,034
Na`alehu Wastewater
System FY24-25 CIP Project
Ilk
:. -�'S'�f+:*} • - �'G ^,{tip_, _ �; Aar ;�.,.� 4� SF�,; e.
Replace and upgrade existing {
g wastewater collection and disposal
system with a system that meets current
DOH and EPA legal requirements.
��' . 1 •.R � � � 'ems ` '-A • s t�-�
Tf
aet ,
:
y
1. ` �.���r — ��•.. . , _ :1� t z� ' �' .� � �f'
—
a
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Department of Environmental Management - Wastewater Division
2. SUBMITTER: Chris Laude, P.E DATE: 12/18/2023
3. PROJECT NAME: DEM - Hilo WWTP Rehabilitation and Replacement
4. LOCATION (COUNCIL DISTRICT): 3
S. COUNCIL BENEFIT DISTRICT(S): 1, 2, 3
6. TMK/CDP PLANNING AREA: (3) 2 / South Hilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $110,000,000
S. PROJECT ELIGIBILITY, ✓ all
D Land acquisition
9 Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
Z Nonrecurring rehabilitation I
R] Planning, feasibility, eng., or design study
❑ Information/communications tech.
2 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Upgrades on the Hilo WWTP will include replacing screens, grit removal, and odor control equipment. Replacement of septage receiving station, renovation of primary clarifiers,
upgrades/replacement of secondary process, replacing solids treatment process and sludge dewatering facility. Electrical and instrumentation/control upgrades. Repairs needed due to
corrosion damage. HWWTP was built in 1990 and after 30 years of operation facility is nearing the end of it's useful life. Upgrades will restore HWWTP's 5.0 mgd capacity.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: El
Needed to continue current level of services.
A. Addresses public health/safety, 'if Yes: ❑�
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to El Quality of El Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of 0
facility/infrastructure/building, ✓if Yes:
Project will restore full operations to asset.
F. Fosters inter -departmental collaboration
if Yes: ❑
N/A
Additional info:
12 _LONG RANGE PLANS/
❑ Dept. Priority
Detoils: Only WWTP for the Hilo area
❑ Comm. value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Detain:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: 0
DESCRIBE: Compliance with Administrative Order on Consent (EPA Docket No. CWA-309(a)-23-003).
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
El Promotes energy and resource conservation
Reduces hazard risk
0 Preserves/protects our natural/cultural env.
0 Cost benefit analysis
Promotes economic vitality
Ld strengthens and sustains our community
Additional info:
16. PROJECT READINESS, 'all
R] Project currently underway
0 Previously Appropriated
Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed)
This Request
11 FY 24-25
1 FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
27,066
$27,066
Construction
110,000
$110,000
TOTAL1
$27,06611
$110,000
1
$137,066
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
13,766
110,000
$123,766
State Revolving Fund
13,300
$13,300
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$27,0661
$110,000
1
$137,066
MI;PI
Kekuanaoa PI Kekuanaoa PI;,:
.1
Replacement of headworks and anaerobic
sludge digestion facilies in their entirety.
Rehabilitation of existing primary
sedimentation tanks, rehabilitation of existing
secondary treatment facilities, and
construction of new solids handling facility.
Improvements to instrumentation and
electrical systems plant -wide to improve
operational efficiency.
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal year 2024 - 2025
1. DEPARTMENT AND DIVISION: Department of Environmental Management - Wastewater Division
2. SUBMITTER: Chris Sparber, P.E. DATE: 3/25/2024
4. LOCATION (COUNCIL DISTRICT): 8
3. PROJECT NAME: Kealakehe WWTP Rehabilitation and Replacement
S. COUNCIL BENEFIT DISTRICT(S): 7,8
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $52,500,000
6. TMK/CDP PLANNING AREA: (3)7-4-008:058/North Kona
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
0 Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Repair existing headworks screens, grit washers, replace septage receiving facility, replace existing influent gravity sewer main, address corrective actions in corrective action plan from DOH for
facility, and install additional equipment to upgrade the facility tertiary treatment process to produce increased quality effluent.
12. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer ail that apply:
D. New facility/infr./bldg., ✓ if Yes: 0
Needed to continue current level of services.
A. Addresses public health/safety, ✓if Yes:'
Eliminates o documented hazard.
B. Service improvements, Vail that apply:
17 Access to 21 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
�
aci lity/i nfrastructure/bu ildi ng, ✓if Yes: ❑
Project will restore full operations to asset.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/ Dept. Priority
Details: Repair Kealakehe WWTP to operate as initially designed
[]Comm. value
Details:
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Adman Priority
Details:
least one and all that apply,
provide details:
El
Details:
❑Mutt! Hazard
Details:
Details:
[]Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ., if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? , if Yes: ❑
DESCRIBE: Compliance with Administrative Order on Consent (EPA Docket No. CWA-309(a)-23-003).
15. SUSTAINABILITY FOCUS, all that apply:
Provide additional information as appropriate:
❑� Promotes energy and resource conservation
10 Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
ILI Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓ all
0 Project currently underway
❑ Previously Appropriated
❑' Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑ Can realistically encumber funds
List phases already completed:
Additional info
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
52,500
$52,500
TOTAL:
$52,500
$52,500
8. O & M COSTS (x $1000):
9. FUNDING SOURCE (x $1000):
ty G.O. Bond
Itate
52,500tate
Revolving Fund
CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$52,500
$52,500
Kealakehe WWTP Rehabilitation and Replacement
FY 24-25 CIP Project
— nw Rrgis*
� OL". County d HwAk (WAVI
—Fore, fmole
—h6Wry
•
Cminly at Hnwwi f.M WWD)
vinin-OVA" Roads
......... Siphon, County of Haa•ii iW WD)
—Farce. C-MMtV of Hrwar (not W WDl—PrWWe
•
WKery
MAE&
TreetmenL County of Mears "D)— Ferrm Stahr,
—Stave
•
Pnvete
—Artw04d Sernv SvOrrn. Cotm d HllMSI fWWDL Q84y, Pnvala
loterift
UrAroran
•
Statr
—Ora tty. Deffilat m PxndW4
—GraNty. CcunV Of Hawal I" iVWD)
Fi.+d>tannn Poroamq
CMmnoy
•
UNUrawn
— Gra Ity, Cwty of Mason IWWDI
Crnrt'I State
�-C,,r tv of Hawas "rYALI;
• Dodraben Po-JR%,a
Manholes
—Faroe. Csronly of H*"i (WWDh
<:s,rily :+I Hawar Aryl W WD,
• County of f- wai CWMI
0
Crn•rty of HewM I'NNOi, f},,r
1:4,514
0 0.05 0 1 0.2 mi
0 0.07 0 15 0. 3 km
Sarco: Elm, Ulpltalfitob• GooE'ya CVYg1•r CasOgfap► 5, Cf&&
Airbus DS, USDA USGS ArroGRID. IGN, sM the UIS User
Commurty, Dew Goet.mo Haerut Cw*.Y
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Department of Environmental Management - Wastewater Division
3. PROJECT NAME: DEM - Repair/Replacement of Wastewater Facilities
2. SUBMITTER: Chris Laude, P.E DATE: 12/18/2023
4. LOCATION (COUNCIL DISTRICT): 1, 2, 3, 6, 7, 8
6. TMK/CDP PLANNING AREA- 3 - Various
S. COUNCIL BENEFIT DISTRICT(S): 1, 2, 3, 6, 7, 8
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $10,000,000
8. PROJECT ELIGIBILITY, ✓ all
that apply:
and acquisition ❑ Infrastructure improvement
Nonrecurring rehabilitation Planning, feasibility, eng., or design study
New bldg., structure, or addition
❑ Information/communications tech.
9. PROJECT URGENCY/NEED, ✓one:
F1 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Major repairs and/or replacement of wastewater facilities at various locations to ensure compliance with regulations under HAR 11-62, Wastewater Systems; HAR 11-54, State Water Quality
Standards; HAR 11-55, State Water Pollution Control; and the US Environmental Protection Agency.
12. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., -'If Yes: El
N/A
A. Addresses public health/safety, ✓if Yes:
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to R1 Quality of El Quantity of
E. Operational efficiency and leveraging
Opportunities:
Results in net decrease in operating cost and improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility /infrastructure/buildin , ✓if Yes: ❑
Project will restore full operations to asset.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Aging WW facilities repair or replacement to ensure continued operations.
❑Comm. Value
Details:
COMMUNITY VALUES, Check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ Cop
Details:
❑ Multi Hazard
Details:
Details:
❑ other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓ if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓ if Yes: ❑
DESCRIBE:
15. SUSTAINABILTTY FOCUS, ✓all that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
El Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
10 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓ al I
ject currently underway
[APreviously Appropriated
Staffavailable to manage project
❑ Externalfunds/resources ready to proceed
that apply:
r[:Ildentifiedoperating budget needs
❑Can realistically encumber funds List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not la sect)
This Request
FY 24-25 1
FY 25-26
1 FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
1,729
1,000
1,000
1,000
1,000
1,000
1,000
$7,729
Construction
6,007
9,000
9,000
9,000
9,000
9,000
9,000
$60,007
17 TOTAL:
$7,73611
$10,000
1 $10,000
1 $10,000
1 $10,000
1 $10,000
1 $10,000
1
$67,736
18. 0 & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):-�
Cty G.O. Bond
7,736
10,000
10,000
10,000
10,000
10,000
10,000
$[ 1, 736
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL]
$7,736
$10,000
$10,000
$10,000
$10,000
$10,000
$10,000
$67,736
County of Hawai'i - DEM - Wastewater Division
Repair/Replacement of Wastewater Facilities
n
:,,�,enww29. n2o
Map Ro36S
Towts
,ss.Sit
0 126 25 60m
0 20 .O 006-
1-t +tMG D.... xY. van, 0w V� - •+� cew
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1, DEPARTMENT AND DIVISION: Department of Environmental Management - Solid Waste Division
2. SUBMITTER: Gene Quiamas DATE: 12/15/2023
4. LOCATION (COUNCIL DISTRICT): All
6. TMK/CDP PLANNING AREA: Various
3. PROJECT NAME: DEM - Rural Transfer Station Repairs and Enhancements
S. COUNCIL BENEFIT DISTRICT(S): All
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $2,000,000
8. PROJECT ELIGIBILITY, ✓ all
that apply:
❑Land acquisition
❑ Nonrecurringrehabilitation
❑ Infrastructure improvement
❑New bldg., structure, or addition
❑ Information/communications tech.
�9. PROJECT URGENCY/NEED, ✓one:
❑ High Med. ❑Low
❑ Planning, feasibility, eng., or design study
10. PROJECT/PROGRAM
DESCRIPTION:
This project is for necessary infrastructure repairs and improvements to the rural transfer sites such as construction of recycling and green waste collection facilities and modifications to refuse
collection facilities.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bidg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes: FA
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
ED Access to El Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
�
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
-if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Improves overall services to the public
OComm. Value
Details: Improves access to disposal and recycling
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ cop
Details:
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓ if Yes: ❑ I DESCRIBE:
14.LEGAL MANDATE? ✓if Yes: ❑ DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply: ❑ Promotes energy and resource conservation Reduces hazard risk
Provide additional information as appropriate: ❑ Cost benefit analysis 0 Promotes economic vitality
Preserves/protects our natural/cultural env.
JEJ Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
[] Previously Appropriated ❑ Staff available to manage project
ElExternal funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
Can realistically encumber funds List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
nning
d Acquisition
ign/Survey
L
1,104
$1,104
struction
9.056
2,000
2,000
2,000
2,000
2,000
2,000
$21,056
TOTAL:
$10,160
$2,000
$2,000
$2,000
$2,000
$2,000
$2,000
$22,160
18. O & M COSTS x $1000):
19. FUNDING SOURCE (x $1000):
CtyG.O.Bond
10,160
2,000
2,000
2,000
2,000
2,000
2,UOn
$22,160
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$10,16011
$2,000
1 $2,000
$2,000
1 $2,000
$2,000
1 $2,000
$22,160
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Department of Environmental Management - Solid Waste Division
2. SUBMITTER: Gene Quiamas DATE: 12/15/2023
3. PROJECT NAME: DEM - Landfill Gas Collection and Control System, WHSL
4. LOCATION (COUNCIL DISTRICT): 8
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: 7-1-003:017
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $2,000,000
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
The GCCS is required to be updated/expanded once the landfilled waste is 5 years old to meet EPA regulations. The last expansion was completed in 2020.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
NIA
A. Addresses public health/safety, ✓if Yes: R1
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to El Quality of [2] Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
Necessaryrepoir/maintenance/replacement.
F. Fosters inter -departmental collaboration
Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Maintains compliance with State and Federal regulations
❑ comm. Value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY, MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: El
DESCRIBE: The EPA requires landfill to mitigate landfill gas emissions.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
ID Reduces hazard risk
Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
❑ strengthens and sustains our community
Additional info:
16. PROJECT READINESS, /all
❑ project currently underway
FZ] Previously Appropriated
Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
0 Identified operating budget needs
❑ Can realistically encumber funds
list phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
125
125
$250
Construction
4,000
1,875
1,875
$7,750
TOTAL:
$4,00011
$2,000
1
$2,000
$8,000
18, 0 & M COSTS (x $1000).
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
4,000
2,000
2,000
$8,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$4,00011
$2,000
1
$2,000
1
$8,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Department of Environmental Management - Solid Waste Division
2. SUBMITTER: Gene Quiamas DATE: 12/15/2023
3. PROJECT NAME: DEM - Wai'6hinu Transfer Station Canopy Over Tipping Floor and Waste Trailer
4. LOCATION (COUNCIL DISTRICT): 6
S. COUNCIL BENEFIT DISTRICT(S): 6
6. TMK/CDP PLANNING AREA: 9-5-005:001
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $250,000
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
El Infrastructure improvement
F±] New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project is continuation of the improvements to the facility which will add a preengineered metal building to serve as a canopy over the tipping floor and waste trailer. The canopy over the
waste trailer will prevent rain water from getting in the waste trailer which will prevent leachate generation. The canopy over the tipping floor will allow faster and more efficient movement of
disposers by elimianting the need to reverse their vehicle to the disposal chute.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: 0
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
El Access to 21 Quality of [21 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Improves overall services to the public
Comm. Value
Details: Improves access to disposal and recycling
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Admin Priority
Details:
least one and al I that apply,
provide details:
❑CDP
Details:
[I Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CIY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? "if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I ❑ Promotes energy and resource conservation
❑ Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
❑ Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
Staff available to manage project
❑External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
250
$250
Construction
3,000
$3,000
TOTAL:
$250
$3,000
$3,250
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
250
3,000
$3,250
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:1
11$250
$3,000
$3,250
(This Page Intentionally Left Blank)
DEPARTMENT OF PARKS
AND RECREATION
MAURICE MESSINA,
DIRECTOR
49
(This Page Intentionally Left Blank)
all
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
Department: Parks and Recreation
FISCAL YEAR 2024-2025
PRIORITY
PROTECT
2024-25 FY FUNDING
in thousands
FUNDING FORECAST BY FISCAL YEAR
in thousands
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private'
CBA,
Other-
Prior
Funds
Allotted
This
Request
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond 6
years
1
IDPR Repairs/Improvements to Facilities
10,000
20,000
10,000
10,000
10,000
30,000
10,000
60,00D
2
DPR ADA Compliance
5,000
5,000
5,000
3
DPR Hilo Skate Park
5,000
l,000
5,000
6,000
11,000
4
DPR Afook-Chinen Civic Auditorium Upgrades
6,000
7,500
6,000
13,500
5
DPR Kea'au Community Center Replacement
1,000
1,000
7,500
8,500
6
DPR W.H. Shipman Park Master Plan -
750
750
1,500
10,000
12,250
7
Isaac Kepo'okalani Hale Beach Park
3,000
3,000
3,000
8
DPR James "Jimmy" Correa Ballfield Upgrades
1,000
1,000
2,000
2,000
9
IDPR- Hawaiian Paradise Park District Park
5,0o0
5,000
2,500
2,500
15,000
15,000
10
jDPR- New Waikoloa Gymnasium & Shelter
3,000
3,000
35,000
38,00D
TOTAL
1
39,750
7,000
2,500
2,500
12,500
1 51,750
19,000
20,OOD
45,000
10,000
10,000
16%250
Created By: James Komata Private: Foundation Grants
Date: 04/22/2024 " Community Benefit Assessments: Fair Shore, Park Dedication, Etc. Other: GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank.)
County of Hawairi
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Parks and Recreation
2. SUBMITTER: James Komata DATE: 1/5/2024
3. PROJECT NAME: DPR Repairs/Improvements to Facilities
4. LOCATION (COUNCIL DISTRICT): Island -wide
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 10,000,000
8. PROJECT ELIGIBILITY, ✓ all
El. Land acquisition
0 Infrastructure improvement New bldg., structure, or addition 19.
PROJECT URGENCY/NEED, ✓one:
that apply:
0 Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study ❑ Information/communications tech. 121
High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
The repair, renovation, upgrade, addition, modification, alteration, improvement, demolition, landscaping, development, etc. of park sites, facilities, amenities, infrastructure, utilities,
components, etc. necessary to facilitate and support safe use thereof and to address the needs of department staff, programs, activities, communities, recreational groups, etc. to fully or best
utilize the department's inventory of land and recreational developments to support the needs of the public.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: 0
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
Access to 0 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Reduces cost by 20% or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes:
Necessary repair/maintenance/replacement per
maintenanceplon/schedule.
F. Fosters inter -departmental collaboration
'if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑' Dept. Priority
Details: Dept.'s highest priorityfollowing ADA compliance projects
Comm. Value
Details: Park users and community groups have advocated for repairs to facilities
COMMUNITY VALUES, check
❑� General Plan
Details: Reference 12.2(a) and 12.3(b), amongst others
QAdmin Priority
Details: Mayor recognizes need to address deteriorating conditions at facilities island -wide
at least one and all that apply,
provide details:
0 CDP
Details: all approved/draft CDPs recognize deteriorating facilities' conditions
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? /if Yes: ❑
1 DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
[2] Promotes energy and resource conservation
2 Reduces hazard risk
R1 Preserves/protects our natural/cultural env.
M Cost benefit analysis
Promotes economic vitality
LJ Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
0 Project currently underway
E Previously Appropriated
Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
21 Identified operating budget needs
0 Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
1,000
1,000
1,000
1,000
1,000
1,000
ongoing
$6,000
Construction
9,000
9,000
9.000
9.000
9,000
9,000
ongoing
$54,000
TOTAL:
$10,000
$10,000
$10,000
$10,000
$10,000
$10,000
$60,000
18. O & M COSTS (x $3000):
19. FUNDING SOURCE (x $3000):
Cty G.O. Bond
10,000
10,000
10,000
10,000
10,000
10,000
$60,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$10,000
$10,000
1 $10,000
1 $10,02LL
$10.000
$10,000
$60,000
(This Page Intentionally Left Blank)
County of Hawairi
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENTAND DIVISION: Parks and Recreation
2. SUBMITTER: James Komata, Park Planner DATE: 1/5/2024
3. PROJECT NAME: DPR ADA Compliance
4. LOCATION (COUNCIL DISTRICT): Island -wide
S. COUNCIL BENEFIT DISTRICT(S): Island -wide
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 5,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition � Infrastructure improvement
p New bldg., structure, or addition
9. PROJECT URGENCY/NEED, "one:
that apply:
0 Nonrecurring rehabilitation 10 Planning, feasibility, eng., or design study
❑ Information/communications tech.
El High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Elimination of architectural barriers and the provision of accessibility improvements at various recreational sites, faclities, amenities, etc. as set for the in the County of HawaiTs Self Evalutaion
and Transition Plan, as determined in conjunction with on -going priorities and needs identified with the federal court and as required to ensure compliance with the Americans with Disabilities
Act and simlar accessibility regulations and obligations of the County. Includes associated work required to ensure longevity and safety of the assets.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: El
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: U
Eliminates o documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to ❑ Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Reduces cost by 20% or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes:
Necessary repair/maintenance/replacement per
maintenance plan/schedule.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Compliance w/federal laws and court orders
Comm. value
Details: Park users and community groups have advocated for repairs to facilities
COMMUNITY VALUES, check
0 General Plan
Details: Reference 12.2(o), 12.3 (b), and 12.3(h), amongst others
Admin Priority
Details: Mayor recognizes need to address deteriorating conditions at facilities island -wide
at least one and all that apply,
provide details:
CDP
Details: all approved/draft CDPs recognize ADA compliance as a priority
Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: El
DESCRIBE: ADA Act (1990), Title 28 CFR35.150; COH's Consent Decree U.S.D.C. Civil No. 97-01102SPK - June 4, 1998 inluding ongoing court proceedings
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
R Promotes energy and resource conservation
2 Reduces hazard risk
12 Preserves/protects our natural/cultural env.
19 Cost benefit analysis
0 Promotes economic vitality
JU, Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
[ Project currently underway
❑ Previously Appropriated
❑' Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
0 Identified operating budget needs
R1 can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
1FTfh7ih Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
1,000
$1,000
Construction
4,000
$4,000
TOTAL:
$5,000
$5,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
5,000
$5,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$5,000
$5,000
(This Page Intentionally Left Blank)
County of HawaN
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Parks and Recreation
2. SUBMITTER: James Komata, Park Planner DATE: 5/6/2024
3. PROJECT NAME: DPR - Hilo Skate Park
4. LOCATION (COUNCIL DISTRICT): 2
5. COUNCIL BENEFIT DISTRICT(S): 1,2,3,4,5
6. TMK/CDP PLANNING AREA: (3)2-2-033:013
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 5,000,000
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Development of a new public skate park in Hilo.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes:
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes:
Community concerns exists around conditions.
B. Service improvements, ✓all that apply:
0 Access to [A Quality of F�l Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Reduces cost by less than 20% by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
N/A
F. Fosters inter -departmental collaboration
✓if Yes:
N/A
Additional info:
12. LONG RANGE PLANS/
n Dept. Priority
Details: Dept. Acknowledges need far safe skating facility in Hilo
n Comm. Value
Details: Skating community and volunteers in support, council member in support
COMMUNITY VALUES, check
❑� General Plan
Details: Provides additional recreation diversity and optimizes use of County lands
Da Admin Priority
Details: Mayoral directive to pursue
at least one and all that apply,
provide details:
❑ CDP
Details:
7 Multi Hazard
Details:
Details:
F1 Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: P 1 DESCRIBE: State funds ($1M) are available provided that matching funds be provided by the County of Hawai'i.
14. LEGAL MANDATE? ✓if Yes: ❑ DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply: ❑ Promotes energy and resource conservation 0 Reduces hazard risk
Provide additional information as appropriate: ❑ Cost benefit analysis 121 Promotes economic vitality
0 Preserves/protects our natural/cultural env.
10 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, Val[
0 Project currently underway
0 Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified o eratin budget needs
f operating 9
❑Can realistically encumber ands
Y f
List hoses already completed. Planning and Design in ro ress
P Y P 9 9 progress
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
500
500
$1,000
Construction
4,500
5,500
$10,000
TOTAL:
$5,000
$6,000
$11,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE N $1000):
Cty G.O. Bond
5,000
5,000
$10,000
State Revolving Fund
State CIP
1,000
$1,000
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:11
$6,000
$11,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENTAND DIVISION: Parks and Recreation
2. SUBMITTER: James Komata, Park Planner DATE: 1/5/2024
3. PROJECT NAME: DPR Afook-Chinen Civic Auditorium Upgrades
4. LOCATION (COUNCIL DISTRICT): 3
5. COUNCIL BENEFIT DISTRICT(S): 1, 2, 3, 4, 5
6. TMK/CDP PLANNING AREA: (3)2-2-033:001/1-Iilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 6,000,000
S. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
E] Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
0 Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10, PROJECT/PROGRAM
DESCRIPTION:
Upgrades to existing multi -use facility necessary to address failing state of building components and to ensure intergrity, safety and usability of the facility for large variety of uses into the
future. Includes replacement of main floor's ceiling and lighting system
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., /if Yes: ❑
N/A
A. Addresses public health/safety, /If Yes: Cl
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
El Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and maintains services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, 'if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Consistent with depYs vision, mission and goals
Comm. Value
Details: Desired and valued by the community
COMMUNITY VALUES, check
General Plan
Details: Provide a variety of recreational opportunities for the residents and visitors
❑Admin Priority
Details: Facility is necessary to support large recreational and communityfunctions
at least one and all that apply,
provide details:
❑✓ CDP
Details: Maintenance of existing facility
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REIXD? 'if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ElDESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
0 Reduces hazard risk
9 Preserves/protects our natural/cultural env.
Cost benefit analysis
0 Promotes economic vitality
21 strengthens andsustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
0 Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
P Identified operating budget needs
� Can realistically encumberfunds
List phases already completed: Design in progress
Additional info:
17. EXPENDITURE PHASING (X $1000):
IF Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
750
$750
Construction
6,750
6,000
$12,750
TOTAL:11
$7,50011
$6,000
$13,500
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
7,500
6,000
$13,500
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$7,50011
$6,000
1
$13,500
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1, DEPARTMENT AND DIVISION: Parks and Recreation
2. SUBMITTER: James Komata, Park Planner DATE: 1/5/2024
3. PROJECT NAME: DPR Kea'au Community Center Replacement
4. LOCATION (COUNCIL DISTRICT): 3
5. COUNCIL BENEFIT DISTRICT(S): 3, 4, 5
6. TMK/CDP PLANNING AREA: 1-6-143:041/Kea'au
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,000,000
B. PROJECT ELIGIBILITY, ✓all
❑ Land acquisition
Infrastructure improvement El New bldg., structure, or addition
9. PROJECT URGENCY/NEED, "one:
that apply: I
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study ❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10, PROJECT/PROGRAM
DESCRIPTION:
Design and construction of a new community center for Kea'au town to house Department of Parks and Recreation programs, government functions, and for community gathering purposes to
replace the existing Kea'au Community Center. Includes demolition of the existing structure and related site improvements.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Needed to continue current level of services.
A. Addresses public health/safety, ✓if Yes: ❑
NIA
B. Service improvements, ✓all that apply:
0 Access to El Quality of [21 Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessaryrepoir/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Consistent with dept's vision, mission and goals
❑ comm. value
Details: Desired and valued by the community
COMMUNITY VALUES, check
0 General Plan
Details: Reference 12.2(a)&(c) and 12.3(b)(d)(g)(h)
EAdmin Priority
Details: Mayor in support
at least one and all that apply,
provide details:
❑✓ CDP
Details: Maintenance of existing facility
❑ Multi Hazard
Details:
Details:
El Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, Vail that apply:
Provide additional information as appropriate:
21 Promotes energy and resource conservation
10 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
El Promotes economic vitality
❑ Strengthens andsustains ourcommunity
Additional info:
16. PROJECT READINESS, ✓all
10 Project currently underway
❑ PreviouslyApproprioted
❑' Staff available to manage project ❑ External funds/resources ready to proceed
that apply:
El Identified operating budget needs
Can realistically encumberfunds
List phases already completed: None
Additional info:
17. EXPENDITURE PHASING (X $100D): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 2425
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
250
$250
Land Acquisition
Design/Survey
750
$750
Construction
7,500
87,500
TOTAL:
$1,000
$7,500
$8,500
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
1,000
7,500
$8,500
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
1
$1,000
1 $7,500
$8,500
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 202S
1, DEPARTMENT AND DIVISION: Parks and Recreation 112.
SUBMITTER: James Komata, Park Planner DATE: 1/5/2024
3. PROJECT NAME: DPR W.H. Shipman Park Master Plan
4. LOCATION (COUNCIL DISTRICT): 5
5. COUNCIL BENEFIT DISTRICT(S): 3, 4, 5
6. TMK/CDP PLANNING AREA: 1-6-003:007 (por.), 058 & 086
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 750,000
8. PROJECT ELIGIBILITY, ✓ all
0 Land acquisition 0 Infrastructure improvement
New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation U Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Planning for the consolidation of park parcels and expansion of the park's area, new circulation route and parking improvements, and potential development of new recreational amenities and
supporting improvements on exisitng leased lands and additional adjacent land.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Needed to continue current level ofservices.
A. Addresses public health/safety, /if Yes: ❑
NIA
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of J
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: El
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Consistent with dept's vision, mission and goals
0 Comm. value
Details: Desired and valued by the community
COMMUNITY VALUES, check
❑� General Plan
Details: Reference 12.2(a)&(c) and 12.3(b)(d)(g)(h)
Admin Priority
Details: Mayor in support
at least one and all that apply,
provide details:
0 CDP
Details: Maintenance of existing facility
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? /if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
❑ Reduces hazard risk
JE1 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
El Promotes economic vitality
L,1 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
❑ Project currently underway
❑ Previously Appropriated
Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
E Identified operating budget needs
0 Can realistically encumber funds
List phases already completed: None
Additional info:
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
I TOTAL:
Planning
600
$600
Land Acquisition
Design/Survey
150
1,500
$1,650
Construction
10,000
$101000
TOTAL:
$750
$1,500
$10,000
$12,250
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
750
1,500
10,000
$12,250
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$750
$1,500
$10,000
$12,250
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Parks and Recreation
2. SUBMITTER: James Komata, Park Planner DATE: 1/30/2024
3. PROJECT NAME: DPR Isaac Kepo'okalani Hale Beach Park Improvements
4. LOCATION (COUNCIL DISTRICT): 4
S. COUNCIL BENEFIT DISTRICT(S): 4,5
6. TMK/CDP PLANNING AREA: 1-3-008:014, 016, 021 & 1-4-093:048
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 3,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition El Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED,,/one:
that apply:
❑ Nonrecurring rehabilitation ❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
El High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Construction of a new Pavilion, Hale Wa'a, multiple Hale Wai, Native Planting Area, water and electrical infrastructure system and other improvements to existing facilities
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: ❑
NIA
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: 0
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑' Dept. Priority
Details: Consistent with dept's vision, mission and goals
0 Comm. value
Details: Desire and valued by the community
COMMUNITY VALUES, check
0 General Plan
Details: Restoration supports basis of the General Plan
FZ] Admin Priority
Details: Mayor in support
at least one and all that apply,
provide details:
CDP
Details:
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: R]
I DESCRIBE: Required as matching funds for FEMA project
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I 0 Promotes energy and resource conservation
❑ Reduces hazard risk
JE Preserves/protects our natural/cultural env.
Fff7Eojbmefit analysis
0 Promotes economic vitality
JU4 strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
R Project currently underway
❑ Previously Appropriated
❑' Staff available to manage project
❑' External funds/resources ready to proceed
that apply:
R Identified operating budget needs
R1 Can realistically encumber funds
List phases already completed: planning and design in progress
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
3,000
$3,000
TOTAL:
$3,000
$3,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
3,000
$3,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$3,000
$3,000
(This Page Intentionally Left Blank.)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Parks and Recreation
2. SUBMITTER: James Komata, Park Planner DATE: 5/6/2024
3. PROJECT NAME: DPR -James "Jimmy" Correa Ballfield Upgrades
4. LOCATION (COUNCIL DISTRICT): 3
5. COUNCIL BENEFIT DISTRICT(S): 1, 2, 3, 4, 5
6. TMK/CDP PLANNING AREA: (3)2-2-033:001/Hilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
I ❑ Information/communications tech.
D High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Upgrades to existing ballfield within Dr. Francis F.C. Wong Stadium to include the installation of artificial turf.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bidg., /if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes: ❑
No health, safety or environmental conditions
exist.
B. Service improvements, ✓all that apply:
L I Access to W Quality of I-1 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
N/A
C. Repair/maintenance/replacementof J
facility/infrastructure/building, ✓if Yes: P]
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: F1
N/A
Additional info:
12. LONG RANGE PLANS/
n Dept. Priority
Details: Consistent with dept's vision, mission and goals
n Comm. Value
Details: Desired and valued by the community
COMMUNITY VALUES, check
D General Plan
Details: Provide a variety of recreational opportunities for the residents and visitors
n Admin Priority
Details: Upgrades will support higher levels of athletic play and more consistent use conditions.
at least one and all that apply,
provide details:
0 CDP
Details: Maintenance of existing facility
n Multi Hazard
Details:
Details:
DtherPlons
Details:
Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: I l
DESCRIBE: State funds ($1M) are available provided that matching funds (1:1) be provided by the County of Hawaii
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, Vail that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
❑ Reduces hazard risk
ElPreserves/protects our natural/cultural env.
❑ Cost benefit analysis
El Promotes economic vitality
0 strengthens and sustains our community
Additional info:
16. PROJECT READINESS, Vail
❑ Project currently underway
❑ Previously Appropriated
❑� staff available to manage project
ElExternal funds/resources ready to proceed
that apply:
0 identified operating budget needs
0 Can realistically encumber funds
List phases already completed: N/A
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
LFY 24-25
1 FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
500
$500
Construction
1,500
$1,500
TOTAL:
$2,000
1$2,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
1,000
$1,000
State Revolving Fund
State CIP
1,000
$1,000
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:1
11 $2,000
1
$2,000
(This Page Intentionally Left Blank.)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Parks and Recreation
2. SUBMITTER: Ashley Kierkiewicz DATE: 5/8/2024
3. PROJECT NAME: DPR - Hawaiian Paradise Park District Park
4. LOCATION (COUNCIL.DISTRICT): 4
S. COUNCIL BENEFIT DISTRICT(S): 4,5
6. TMK/CDP PLANNING AREA: 1-5-039:267
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 5,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
PI Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation 12
Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Construction of the HPP District Park to include recreational facilities and recreational/sports fields that serve the needs of the growing Hawaiian Paradise Park community. The park would aid
in 'ohana, keiki, and kupuna time together, encourage physical activity and time in nature, and provide additional shelter space during a disaster.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., -if Yes: 0
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: ❑
NIA
B. Service improvements, Val[ that apply:
❑ Access to ❑ Quality of n Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
NIA
F. Fosters inter -departmental collaboration
Yes:
N/A
Additional info:
12. LONG RANGE PLANS/
n Dept. Priority
Details: desire to support growing population
D� Comm. value
Details: Community input demonstrates need and desire for park
COMMUNITY VALUES, check
U General Plan
Details: identified as necessary to supporting whole communities
❑Admin Priority
Details:
at least one and all that apply,
U CDP
Details: Identified in the Puna Community Development Plan
❑Multi Hazard
Details:
provide details:
❑ Other Plans
Details: HPP Park Master Plan, and park EA completed
n Mitigation Plan
Details:
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, -'all that apply:
Provide additional information as appropriate:
ElPromotes energy and resource conservation
❑ Reduces hazard risk
ElPreserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
0 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
Ei Previously Appropriated
Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ identified o eratin budget needs
f operating 9
❑Can realistically encumberfunds
Y f
List bases already completed: Master Plan completed 4 2018
P Y P P /
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
15,000
$15,000
TOTAL:
$15,000
$15,000
18. O & M COSTS (x $3000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
5,000
$5,000
State Revolving Fund
State CIP
5,000
$5,000
Federal
2,500
$2,500
Private (Grants)
2,500
$2,500
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$15,000
$15,000
(This Page Intentionally Left Blank.)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Department of Parks and Recreation 112.
SUBMITTER: Council Member Cindy Evans DATE: 5/16/2024
3. PROJECT NAME: DPR - New Waikoloa Gymnasium & Shelter
4. LOCATION (COUNCIL DISTRICT): Waikoloa Village (Kohala)
S. COUNCIL BENEFIT DISTRICT(S): 9
6. TMK/CDP PLANNING AREA: Tentatively (3)6-8-041:012 (por.)
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 3,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
El Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
El Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High 0 Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Development of a new gymasnium to support the indoor sports and recreational needs for the growing community of Waikoloa Village and the district of South Kohala. The new gymanisium
would also be designed as a hurricane/emergency shelter and provide varied community meeting spaces in support of community gatherings, public meetings, community events, and the
provision of more recreational services and programs.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: FA
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes:
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
L Access to LI Quality of n Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
N/A
F. Fosters inter -departmental collaboration
✓if Yes: n
Civil Defense
Additional info:
12. LONG RANGE PLANS/
n Dept. Priority
Details: DPR supports this much needed recreational amenity
D] comm. value
Details: District 9Councilmembersupports this project
COMMUNITY VALUES, check
General Plan
Details: Addresses Course of Action 12.5.6.2N.
nAdmin Priority
Details: Mayor suppoirts this project.
at least one and all that apply,
CDP
Details: Addresses Waikoloa Policy 1 for on indoor gymansium
n Multi Hazard
Details: Hurricane shelter and community center
provide details:
Other Plans
Details:
❑ Mitigation Plan
Details:
Additional info:
13. cTY. MATCHING FUNDS REIXD? ✓if Yes: 1 l
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, Vail that apply:
Provide additional information as appropriate:
LqPromotes energy and resource conservation
0 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis
0 Promotes economic vitality
C) strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
❑ Project currently underway
❑ Previously Appropriated
T Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
C) Can realistically encumberfunds
list phases already completed: N/A
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
3,000
$3,000
Construction
35.000
$35,000
TOTAQ1
$3,000
$35,000
$38,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
3,000
35,000
$38,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$3,000
$35,000
$38,000
(This Page Intentionally Left Blank)
DEPARTMENT OF PUBLIC
WORKS
STEVE PAUSE,
DIRECTOR
73
(This Page Intentionally Left Blank)
74
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
Department: Public Works
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
in thousands)
FUNDING FORECAST BY FISCAL YEAR
in thousands
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private*
CBA,
Other**
Prior
Funds
Allotted
This
Request
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond 6
years
1
DPW - Facilities Improvement
14,000
1 6,362
14,000
24,000
14,000
14,000
14,000
14,000
1 90,362
2
DPW - Mamalahoa Highway Rehabilitation, Part 1 & 3
2,400
9,600
12,000
12,000
3
DPW - Kahakai Blvd Safe Routes to School - Keonepoko
500
2,000
2,500
2,500
4
DPW - Pa ua hi Street Bridge Reconstruction
800
4,000
800
4,80D
5
DPW - Bridge Repair
2,500
1
400
1,500
10,000
11,90D
6
DPW - Kaiwiki #1 (26-5) &'Ope'a Stream (31-2) Bridges
5,000
5,000
5,000
7
DPW - 4 Mile Creek Bridge Reconstruction
1,333
2,667
4,000
14,000
18,000
B
DPW- Waianuenue Avenue Bridge Modernization -HMGP
3,550
10,650
1,906
14,200
16,106
9
DPW - Hurricane Lane Damage Projects
11,000
5,243
11,000
16,243
10
DPW - Ka'ahakini Stream Bridge Reconstruction
700
700
6,000
6,700
11
DPW- Kilauea Avenue Safe Routes to School - Walakea
2,400
9,600
12,000
12,000
12
DPW - Wailoa Stream Flood Control Channel Maintenance Dredging
3,000
3,000
3,000
13
DPW- Land Acquisition
1,000
213
1,000
1,213
14
DPW - POhala Street Extension (Pikake PI. to S. Kopua Road)
550
550
4,000
4,550
15
DPW -Ane Keohokalole Highway Phase III - Hinalani Drive to Ka'iminani Drive
4,000
4,000
45,000
49,000
16
DPW - Post Office Road Widening
Soo
Soo
2,000
2,500
17
DPW - Oneo Lane (AIN Drive to Kuakini Highway)
1,250
1,250
6,000
7,250
18
DPW - Drainage/Flooding Improvement Projects, Islandwide
4,000
4,000
4,000
1g
DPW - Manono Street Shoulder Improvements
-
20
-
3,500
3,520
20
DPW - Pahoa Village Sidewalk Improvement
2,000
2,000
2,000
TOTAL
54,483
2,667
1 36,850
-
-
18,144
1 94.000
41,500
77,000
14,000
1 14,000
14,000
272,644
Created By: Stephen M. Pause, P.E Private: Foundation Grants
Date: 1/22/2024 '" Community Benefit Assessments: Fair Share, Park Dedication, Etc. Other: GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: DPW Building Division 112.
SUBMITTER: Julann Sonomura DATE: 12/22/2023
3. PROJECT NAME: DPW - Facilities Improvements
4. LOCATION (COUNCIL DISTRICT): All
S. COUNCIL BENEFIT DISTRICT(S): All
16. TMK/CDP PLANNING AREA: All
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 14,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
21 Infrastructure improvement
Mew bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
0 Nonrecurring rehabilitation I
D Planning, feasibility, eng., or design study I
❑ Information/communications tech.
❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project represents various facilities improvements including additions, energy efficiency, ADA compliance, hazard mitigation, hardening, maintenance, renovation, repairs, etc.; and new
facilities to replace existing that are beyond service life.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., /if Yes:
Needed to continue current level of services.
A. Addresses public health/safety, ✓if Yes: U
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to 0 Quality of [�] Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, /if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: 0
DPW
Additional info: Inter -departmental collaboration occurs with all Building Projects because County agencies are the end -users.
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Department Priority (Asset Management)
❑� Comm. value
Details: Maintenance and rehabilitation is required to maintain commercial values.
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑ other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
Promotes energy and resource conservation
Reduces hazard risk
❑Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
ILJ strengthens andsustains ourcommunity
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑J Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
11
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
1 FY 25-26
FY 26-27
1 FY 27-28
1 FY 28-29
1 FY 29-30
Beyond 6
1 Years
TOTAL:
Planning
Land Acquisition
Design/Survey
25
1,330
1,400
1,400
1,400
1,400
1,400
$8,355
Construction
6,337
12,670
12,600
12,600
12,600
12,600
12,600
$82,007
TOTAL:
$6,362
$14,000
$14,000
$14,000
$14,000
$14,000
$14,000
$90,362
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
6,362
14,000
14,000
14,000
14,000
$90,362
State Revolving Fund
State CIP
[77
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$6,362
$14,000
1 $14,000
1 $14,0001
$14,000
1 $14,000
1 $14,000
$90,362
(This Page Intentionally Left Blank)
County of Hawai'i
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works; Engineering
2. SUBMITTER: Keone Thompson DATE: 12/22/2023
3. PROJECT NAME: DPW - Mamalahoa Highway Rehabilitation, Part 1 & 3 - North Kona
4. LOCATION (COUNCIL DISTRICT): 7 & 8
S. COUNCIL BENEFIT DISTRICT(S): 7 & 8
6. TMK/CDP PLANNING AREA: 7-5/Kona
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 2,400,000
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
0 Nonrecurring. rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project will pave/rehabilitate the existing roadway.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., 'if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes: 0
Community concerns exists around conditions.
B. Service improvements, ✓all that apply:
❑ Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessaryrepoir/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
NIA
Additional info:
12. LONG RANGE PLANS/
0 Dept. Priority
Details: Improve roadway safety.
❑� Comm. value
Details: Enhances quality of life for residents.
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: 0
DESCRIBE: 80% Federal 20% County
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
10 Reduces hazard risk
10 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
JE Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
Project currently underway
❑ Previously Appropriated
0 Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
Identified operating budget needs
r
0 Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
12,000
$12,000
TOTAL:
$12,000
$12,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
2,400
$2,400
State Revolving Fund
State CIP
Federal
9,600
$9,600
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:11
$12,000
$12,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works; Engineering
2. SUBMITTER: Keone Thompson DATE: 12/22/2023
3. PROJECT NAME: DPW - Kahakai Blvd Safe Routes to School - Keonepoko
4. LOCATION (COUNCIL DISTRICT): 4
S. COUNCIL BENEFIT DISTRICT(S): 4
6. TMK/CDP PLANNING AREA: 1-5/Puna
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 500,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition Fz] Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation ❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project will construct a paved shoulder and drainage improvements.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes:
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: U
Community concerns exists around conditions.
B. Service improvements, /all that apply:
El Access to ❑ Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, "if Yes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Improve roadway safety.
❑ Comm. Value
Details: Enhances quality of life for residents.
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Pion
Additional info:
13. CTY. MATCHING FUNDS RECVD? ✓if Yes: PI
I DESCRIBE: 80% Federal 20% County
14. LEGAL MANDATE? if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis
0 Promotes economic vitality
Ld Strengthens andsustains our community
Additional info:
16. PROJECT READINESS, ✓all
121 Project currently underway
❑ Previously Appropriated
El Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
12 Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
2,500
$2,500
TOTAL:
$2,500
$2,500
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
500
$500
State Revolving Fund
State CIP
Federal
2,000
$2,000
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$2,500
$2,500
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Pauahi Street Bridge Reconstruction
4. LOCATION (COUNCIL DISTRICT): 2
S. COUNCIL BENEFIT DISTRICT(S): 2
6. TMK/CDP PLANNING AREA: 2-2-04,12/S. Hilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 800,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, -one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
DESCRIPTION: 30. PROJECT/PROGRAM
Project will reconstruct the bridge.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., -if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes: 0-
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
�
facility/infrastructure/building, ✓if Yes: ❑
Necessoryrepoir/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Assessment and repairs required by State and Federal programs.
❑ Comm. Value
Details:
COMMUNITY VALUES, check
0 General Plan
Details: Transportation and economic impact.
❑Admin Priority
Details:
at least one and all that apply,
provide details:
0 CDP
Details: Community safety.
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓al I that apply:
Provide additional information as appropriate:
ElPromotes energy and resource conservation
JE Reduces hazard risk
10 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
I ❑ Promotes economic vitality
❑ Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
0 Project currently underway
0 Previously Appropriated
0 Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El can realistically encumber funds
List phases already completed: Design, Bid
Additional info:
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
4,000
800
$4,800
TOTAL:
$4,000
$800
$4,800
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
4,000
800
$4,800
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$4,000
$800
$4,800
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENTAND DIVISION: Public Works -Engineering Division
2. SUBMITTER: Keane Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Bridge Repair
4. LOCATION (COUNCIL DISTRICT): Various
S. COUNCIL BENEFIT DISTRICT(S): Various
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,500,000
8. PROJECT ELIGIBILITY, ✓ all
I ❑ Land acquisition
Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
10 Nonrecurring rehabilitation
10 Planning, feasibility, eng., or design study
I ❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Bridge repair and maintenance for County in-service bridges and County maintained bridges.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., -if Yes: ❑
N/A
A. Addresses public health/safety, -'If Yes: U
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑' Dept. Priority
Details: Assessment and repairs as necessary and in compliance with State and Feder
❑ Comm. Value
I Details:
COMMUNITY VALUES, check
General Plan
Details: Transportation and economic impact (sections 2 and 13).
❑Admin Priority
Details:
at least one and all that apply,
provide details:
CDP
Details: Community safety.
Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑Mitigation Plan
Additional info:
13. CTY, MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
121 Reduces hazard risk
EZ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
ILI Promotes economic vitality
JU Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
E] Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑ Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
1 FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
1,500
$1,500
Construction
4001
10,000
$10,400
TOTAL:
$40011
$1,500
1$10,000
$11,900
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
400
1,500
10,000
$11,900
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund -(describe)
TOTAL:
$40011
$1,500
1 $10,000
1
$11,900
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works; Engineering
2. SUBMITTER: Keone Thompson DATE: 12/22/2023
3. PROJECT NAME: DPW - Kaiwiki #1 (26-5) &'Ope'a Stream (31-2) Bridges
4. LOCATION (COUNCIL DISTRICT): 1
S. COUNCIL BENEFIT DISTRICT(S): 1
6. TMK/CDP PLANNING AREA: 2-6 & 3-1/Hamakua
7. TOTAL COUNTY FUNDS NEEDED THIS FY: $0 (100% Federal)
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
0 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
21 Nonrecurring rehabilitation
LJ Planning, feasibility, eng., or design study I
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project will construct bridge repairs and improvements.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: L✓]
Community concerns exists around conditions.
B. Service improvements, ✓all that apply:
0 Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, -if Yes: El
N/A
F. Fosters inter -departmental collaboration
Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Improve roadway safety.
0 comm. Value
Details: Enhances quality of life for residents.
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D?
✓if Yes: ❑
DESCRIBE: 100% Federal
14. LEGAL MANDATE? ✓if Yes:
❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
El Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Costbenefitanalysis
P1 Promotes economic vitality
U strengthensandsustainsour community
Additional info:
16. PROJECT READINESS, ✓all
Project currently underway
❑ Previously Appropriated
Staff available to manage project
ElExternal funds/resources ready to proceed
that apply:
rIdentified operating budget needs
El Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000):
IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
5,000
$5,000
TOTAL:
$5,000
$5,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000).
Cty G.O. Bond
State Revolving Fund
State CIP
Federal
5,000
$5,000
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$5,000
$5,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 202S
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - 4 Mile Creek Bridge Reconstruction
4. LOCATION (COUNCIL DISTRICT): 3
S. COUNCIL BENEFIT DISTRICT(S): 3
6. TMK/CDP PLANNING AREA: 2-4-04/S.Hilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,333,333
8. PROJECT ELIGIBILITY, ✓ all
2 Land acquisition
0 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
01 Planning, feasibility, eng., or design study
❑ Information/communications tech.
B High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project will design and construct a new reinforced concrete bridge to replace/reconstruct the existing 4 Mile Creek Bridge. The existing one -lane 100-year old bridge is a historical bridge and its historic features will be retained while modernizing
and implementing the necessary structural and safety improvements. Hydrologic and hydraulic studies will determine its associated upstream and downstream channel improvements to ensure its 100-year storm design conveyance capacity. The
intersection at Haihai Street and Kilauea Avenue will be analyzed to determine what improvements will be needed to be Implemented in order to accommodate the proposed new two lane bridge, all in accordance with AASHTO Design.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Addresses anticipated future need.
A. Addresses public health/safety, ✓if Yes: LI
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
R1 Access to D Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: 21
Necessary repair/maintenance/replacement per
maintenance plan/schedule.
F. Fosters inter -departmental collaboration
✓if Yes: 0
Fire
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Bridge and surrounding area needs improvements for safety and increase incapacity.
❑✓ Comm. Value
Details: Bridge and surrounding area needs improvements for safety and increase incapacity.
COMMUNITY VALUES, check
General Plan
Details: Section 5- Addresses flooding and other natural hazards.
❑� Admin Priority
Details: Project is a focus for both the State and County.
at least one and all that apply,
provide details:
❑ CDp
Details:
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? /if Yes: 0
I DESCRIBE: State Provide $12M (2/3 cost), County provide $6M (1/3 cost).
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
0 Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
JU strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
❑ Project currently underway
Previously Appropriated
0 Staff available to manage project
❑' External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El Can realistically encumber funds
List phases already completed:
Additional info:
Ad
EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
1,000
$1,000
Land Acquisition
500
$500
Design/Survey
2,500
$2,500
Construction
14,000
$14,000
TOTAL:
$4,000
$14,000
$18,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
1,333
4,667
$6,000
State Revolving Fund
State CIP
2,667
9,333
$12,000
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:11
$4,000
$14,000
$18,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keane Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Waianuenue Avenue Bridge Modernization - HMGP
4. LOCATION (COUNCIL DISTRICT): 2
S. COUNCIL BENEFIT DISTRICT(S): 2
6. TMK/CDP PLANNING AREA: . 2-3-25,26,32/S. Hilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 3,550,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
R1 Infrastructure improvement ❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, *'one:
that apply:
❑ Nonrecurring rehabilitation
21 Planning, feasibility, eng., or design study I ❑ Information/communications tech.
❑ High 0 Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project will design and modernize the existing Bridge. The existing bridge is a historical bridge and its historic features will be retained while modernizing and implementing the necessary
structural and safety improvements. Hydrologic and hydraulic studies will determine its associated upstream and downstream channel improvements to ensure its 100-year storm design
conveyance capacity.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
A. Addresses public health/safety, ✓if Yes: Ll
Reduces risk of o documented hazard.
B. Service improvements, Vail that apply:
0 Access to 0 Quality of E21 Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓ifyes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
Additional info:
12. LONG RANGE PLANS/
0 Dept. Priority
Details: Safety improvements to the bridge.
❑ Comm. value
Details:
COMMUNITY VALUES, check
❑� General Plan
Details: Transportation and economic impact (sections 2 and 13).
❑� Admin Priority
Details: Modernize the bridge.
at least one and all that apply,
provide details:
0 CDP
Details: Community safety.
❑ Multi Hazard
Details:
Details:
❑ other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: 0
DESCRIBE: 75% Federal FEMA HMGP funds, 25% County
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
R1 Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
ILI Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Pr oject currently underway
❑� Previously Appropriated
❑' Staff available to manage project
External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
10Can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
250
$250
Land Acquisition
Design/Survey
1,656
$1,656
Construction
14,200
$14,200
TOTAL:11
$1,906
$14,200
$16,106
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
3,550
$3,550
State Revolving Fund
State CIP
Federal
1,656
10,650
$12,306
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - GET
250
$250
TOTAL:11
$1,90611
$14,200
1
$16,106
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Hurricane Lane Damage Projects
4. LOCATION (COUNCIL DISTRICT): Various
S. COUNCIL BENEFIT DISTRICT(S): 1,2,3,4,5,9
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 11,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, -one:
that apply:
❑ Nonrecurring rehabilitation 1
CI Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
County funding share of the FEMA Hurricane Lane projects which will repair damages caused by the heavy winds and rainfall to the Island of Hawaii.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, 'if Yes: LI
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 21 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services. 71
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Assessment and repairs required by Federal programs.
[-]Comm. Value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes:
DESCRIBE: FEMA 75%, County 25%
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I ❑ Promotes energy and resource conservation
121 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
ILvJ Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
R Project currently underway
I ❑ Previously Appropriated
I [A Staff available to manage project ❑' External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El Can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
243
$243
Construction
5,000
11,000
$16,000
TOTAL:
$5,2431
$11,000
$16,243
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
11
11,000
$11,011
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - GET Fund
5,232
$5,232
TOTAL:
$5,24311
$11,000
1
$16,243
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Ka'ahakini Stream Bridge Reconstruction
4. LOCATION (COUNCIL DISTRICT): 1
5. COUNCIL BENEFIT DISTRICT(S): 1
6. TMK/CDP PLANNING AREA: 2-8-04,09
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 700,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, "one:
that apply:
❑ Nonrecurring rehabilitation I
❑ Planning, feasibility, eng., or design study I
❑ Information/communications tech.
0 High ❑ Med. ❑Low
10. PROJECT/PROGRAM
DESCRIPTION:
Project will reconstruct the bridge abutments/foundation. Bridge is currently closed to traffic.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer al I that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes: 0
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of El Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of J
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Assessmentand repairs required by5tate and Federal programs.
❑Comm. Value
Details:
COMMUNITY VALUES, check
0 General Plan
Details: Transportation and economic impact
❑ Admin Priority
Details:
at least one and all that apply,
provide details:
0 CDP
Details: Community safety.
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE: 7771
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
12 Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
JU strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
Project currently underway
0 Previously Appropriated
0 Staff available to manage project
ElExternalfunds/resources ready to proceed
that apply:
rOIdentified operating budget needs
❑Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000j:
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
1 FY 25-26
FY 26-27
1 FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
700
$700
Construction
6,000
$6,000
TOTAL:
$700
$6,000
$6,700
18. O & M COSTS (x $1000):
19. FUNDING SOURCE N $1000):
Cty G.O. Bond
700
6,000
$6,700
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$700
1
$6,000
1
$6,700
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works; Engineering
2. SUBMITTER: Keone Thompson DATE: 12/22/2023
3. PROJECT NAME: DPW - Kilauea Avenue Safe Routes to School - Waiakea
4. LOCATION (COUNCIL DISTRICT): 2
S. COUNCIL BENEFIT DISTRICT(S): 2 & 3
6. TMK/CDP PLANNING AREA: 2-2/1-lilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 2,400,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project will construct concrete sidewalks and drainage improvements.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bidg., ✓if Yes:
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, -'If Yes:
Community concerns exists around conditions.
B. Service improvements, ✓all that apply:
El Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
N/A
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Improve roadwaysafety.
Comm. Value
Details: Enhances quality of life for residents.
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
El Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: 0
I DESCRIBE: 80% Federal 20% County
14. LEGAL MANDATE? -if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis
El Promotes economic vitality
Ld strengthens and sustains our community
Additional info:
16. PROJECT READINESS, Val I
❑� Project currently underway
❑ Previously Appropriated
❑' staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
0 can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
12,000
$12,000
TOTAQ1
$12,000
$12,000
18. 0 & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
2,400
$2,400
State Revolving Fund
State CIP
Federal
9,600
$9,600
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$12,000
$12,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 3/28/2024
3. PROJECT NAME: DPW - Wailoa Stream Flood Control Channel Maintenance Dredging
4. LOCATION (COUNCIL DISTRICT): 2
S. COUNCIL BENEFIT DISTRICT(S): 2
6. TMK/CDP PLANNING AREA: 2-2-20,29/S. Hilo
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 3,000,000
S. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition ❑ Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
R1 Nonrecurring rehabilitation El Planning, feasibility, eng., or design study
❑ Information/communications tech.
Z High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Removal of sediment to bottom of channel within the extents of the Wailoa Stream Flood Control Channel.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes: CI
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
R1 Access to B Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Necessary maintenance to comply w/USACE inspections and restore capacity.
❑ Comm. Value
Details:
COMMUNITY VALUES, check
General Plan
Details: Section 5.2 - Reduce surface water and sediment runoff.
❑ Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ,if Yes: El
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
Reduces hazard risk
0 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
El Promotes economic vitality
0 Strengthens and sustains ourcommunity
Additional info:
16. PROJECT READINESS, Val
El Project currently underway
❑ Previously Appropriated
0 Staff available to manage project
ElExternal funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
2 Can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Des ign/Survey
Construction
3,000
$3,000
TOTAL:
$3,000
$3,000
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $2000).
Cty G.O. Bond
3,000
$3,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$3,000
$3,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Land Acquisition
4. LOCATION (COUNCIL DISTRICT): All
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,000,000
8. PROJECT ELIGIBILITY, ✓ all
Land acquisition
El Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply: I
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study I
❑ Information/communications tech.
❑ High 0 Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Purchase of land to resolve complaints of existing roadway or drainage facility encroachments into private property and other land acquisition related to roadway or drainage improvement
projects. Funds to be used for all related activities such as title search, appraisal, and parcel map preparation.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes:
NIA
B. Service improvements, Vail that apply:
0 Access to U Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
NIA
F. Fosters inter -departmental collaboration
Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details:
❑ Comm. Value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑ CDP
Details:
❑ Multi Hazard
Details:
Details:
El Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I ❑ Promotes energy and resource conservation
10 Reduces hazard risk
10 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
ILI Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, Vail
❑ Project currently underway
❑. Previously Appropriated
❑� Staff available to manage project
❑External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
JEICan realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
213
1,000
$1,213
Design/Survey
Construction
TOTAL:
$21311
$1,000
1
$1,213
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
213
1,000
$1,213
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$213
$1,000
$1,213
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
Iz. SUBMITTER: Keane Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Pfihala Street Extension (PSkake Pl. to S. Kopua Road)
4. LOCATION (COUNCIL DISTRICT): 5
S. COUNCIL BENEFIT DISTRICT(S): 5
16. TMK/CDP PLANNING AREA: 1-1738:207/Puna
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 550,000
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, /one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High 0 Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Extend Puhala Street from Pikake Place to South Kopua Road. Land acquisition required for road extension right-of-way.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes:
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: ❑�
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
PI Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
v�A
F. Fosters inter -departmental collaboration
Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
Dept. Priority
Details: Provide alternate evacuation/access route.
0 Comm. value
Details: 2016Ad Hoc Committee on Puna connectivity report identified connector locations.
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
❑� CDP
Details: 2008 Puna CDP discusses the need of connector roads.
❑ Multi Hazard
Details:
Details:
E) other Plans
Details: 2005 Puna Regional Circulation Plan identifies the lack of connector roads.
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE: 771
14. LEGAL MANDATE? ✓if Yes: ❑ I
DESCRIBE: 77-71
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
10 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
ILI Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
❑ Project currently underway
0 Previously Appropriated
0 Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
50
$50
Design/Survey
500
$500
Construction
4,000
$4,000
TOTAL:
$550
$4,000
$4,550
18. O & M COSTS (x $3000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
550
4,000
$4,550
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$550
$4,000
1
$4,550
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Ane Keohokalole Highway Phase III - Hinalani Drive to Ka'iminani Drive
4. LOCATION (COUNCIL DISTRICT): 8
S. COUNCIL BENEFIT DISTRICT(S): 6,7,8,9
6. TMK/CDP PLANNING AREA: 7-3-9:05,13,25,7-3-10:06,61/N. Kona
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 4,000,000
8. PROJECT ELIGIBILITY, ✓ all
0 Land acquisition
0 Infrastructure improvement
ElNew bldg., structure, or addition
9. PROJECT URGENCY/NEED, "one:
that apply:
❑ Nonrecurring rehabilitation
LJ Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High 0 Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
New connector road will enhance the quality of life by reducing traffic congestion.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: 0
Lack of documented hazard but safety concern
exists.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement per
maintenance plan/schedule.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Infrastructure that improves traffic circulation/congestion.
0 Comm. Value
Details: To improve traffic circulation and to reduce traffic congestion.
COMMUNITY VALUES, check
0 General Plan
Details: 13.2.5.7.2 Course of action for Ane K to connect Palani Road to University Dri
❑Admin Priority
Details:
at least one and all that apply,
provide details:
0 CDP
Details: 4.1.3 Goals, objectives, policies,and actions to connect Kailua Village to the aj
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? -'If Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
0 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
0 Project currently underway
❑Previously Appropriated
0 Staff available to manage project
ElExternal funds/resources ready to proceed
that apply:
❑ Identified operating budge[ needs
El Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
700
$700
Land Acquisition
400
$400
Design/Survey
2,900
$2,900
Construction
45,000
$45,000
TOTAL:
$4,000
$45,000
$49,OOD
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
4,000
9,000
$13,000
State Revolving Fund
State CIP
Federal
36,000
$36,000
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$4,000
$45,000
1
$49,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Post Office Road Widening
4. LOCATION (COUNCIL DISTRICT): 4
S. COUNCIL BENEFIT DISTRICT(S): 4
6. TMK/CDP PLANNING AREA: 1-5-06,11,14/Puna
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 500,000
8. PROJECT ELIGIBILITY, ✓ all I
0 Land acquisition
0 Infrastructure improvement ❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply: 10
Nonrecurring rehabilitation
[] Planning, feasibility, eng., or design study I ❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Post Office Road between Pahoa Village Road and the Pahoa Bypass (Highway 130) provides a useful connection point between the highway and Pahoa Village. It is a narrow road that is heavily
used by people who park at the Pahoa Post Office, as well as those who are entering or leaving Pahoa. Charter School students may access Pahoa Village by crossing the highway and then
walking along this road. Traffic was diverted through this road during the 2014 Puna lava emergency. This project will acquire lane, widen, and repave the road.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: ❑
Community concerns exists around conditions.
B. Service improvements, Val I that apply:
0 Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details:
❑Comm. value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
0 CDP
Details: Puna Community Development Plan 4.3.1
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D?
✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes:
❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
JLJ Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
El Project currently underway
ropriated
❑' Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
E Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
500
$500
Design/Survey
Construction
2,000
$2,000
TOTAL:
$500
$2,000
$2,500
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
G.O. Bond
500
2,000
$2,500
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL.
wo
$2,000
1
$2,500
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keane Thompson DATE: 12/26/2023
3. PROJECT NAME: DPW - Oneo Lane (Ali'i Drive to Kuakini Highway)
4. LOCATION (COUNCIL DISTRICT): 7
S. COUNCIL BENEFIT DISTRICT(S): 7,8
6. TMK/CDP PLANNING AREA: 7-5-09:021,022,023,025/N. Kona
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,250,000
8. PROJECT ELIGIBILITY, ✓ all
Ri Land acquisition
21 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
104 Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
New connector road will enhance the quality of life by reducing traffic congestion.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 2
Fills gap in current services.
A. Addresses public health/safety, "if Yes: U
Lack of documented hazard but safety concern
exists.
B. Service improvements, ✓all that apply:
0 Access to P1 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
0 Dept. Priority
Details: Infrastructure that improves traffic circulation/congestion.
❑ Comm. value
Details:
COMMUNITY VALUES, check
❑ General Plan
Details:
❑Admin Priority
Details:
at least one and all that apply,
provide details:
0 CDP
Details: Improves connectivity.
❑ Multi Hazard
Details:
Details:
El Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
JU, strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
0 Project currently underway
0 Previously Appropriated
staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El Can realistically encumber funds
List phases already completed: N/A
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
250
1,000
6,000
$250
$1,000
$6,000
TOTAL:
$1,250
$6,000
$7,250
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
1,250
6,000
$7,250
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$1,250
$6,000
$7,250
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Public Works - Engineering Division
2. SUBMITTER: Keone Thompson DATE: 3/28/2024
3. PROJECT NAME: DPW - Drainage/Flooding Improvements Projects, Islandwide
4. LOCATION (COUNCIL DISTRICT): Various
S. COUNCIL BENEFIT DISTRICT(S): Various
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 4,000,000
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
P1 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
El Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Inspection, repair, and construction of drainage improvement projects, islandwide.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., 'if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes:
Community concerns exist around conditions
B. Service improvements, ✓all that apply:
Access to E Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Has no reduction of construction costs.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
0 Dept. Priority
Details: Improve flooding safety concerns.
Comm. Value
Details: Community safety driven.
COMMUNITY VALUES, check
❑� General Plan
Details: Sections -Addresses flooding and other natural hazards.
❑AdminPriority
Details:
at least one and all that apply,
provide details:
CDP
Details: Community safety.
❑ Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
Reduces hazard risk
El Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
0 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
Project currently underway
E] Previously Appropriated
0 Staff available to manage project
ElExternal funds/resources ready to proceed
that apply:
FOldentified operating budget needs
M Can realistically encumber funds
List phases already completed:
Additional info:
Ad
EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
1 FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
4,000
$4,000
TOTAL:
$4,000
$4,000
18. O & M COSTS (x $3000):
19. FUNDING SOURCE N $1000):
Cty G.O. Bond
4,000
$4,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:1
$4,000
1
$4,000
(This Page Intentionally Left Blank.)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Office of Housing and Community Development
2. SUBMITTER: Ashley Kierkiewicz DATE: 5/8/2024
3. PROJECT NAME: OHCD - Pahoa Village Sidewalk Improvement
4. LOCATION (COUNCIL DISTRICT): 4,5
5. COUNCIL BENEFIT DISTRICT(S): 4,5
6. TMK/CDP PLANNING AREA: 1-5-003:007/ Puna
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 2,000,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Infrastructure improvement I
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation I
0 Planning, feasibility, eng., or design study I
❑ Information/communications tech.
ED High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Pahoa village residents, including children, use the Pahoa Village Road to access schools, stores, restaraunts, recreation facilities, etc. Most of the narrow road does not have well-defined
sidewalks and pedestrains face hazardous traffic conditions and uneven walking walking surfaces throughout the roadway. A visible sidewalks structure througout the roadway, would provide
pedestrians a safer path to their destination and comply with ADA requirements.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, -'If Yes:
Reduces risk of a documented hazard.
B. Service improvements, Val[ that apply:
❑ Access to I Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes:
Necessary repaidmaintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
NIA
Additional info:
12. LONG RANGE PLANS/
n Dept. Priority
Details:
Comm. Value
Details: promotes walking via shared use paths
COMMUNITY VALUES, check
❑ General Plan
Details:
❑� Admin Priority
Details: Project will provide a safer access for pedetrians.
at least one and all that apply,
U CDP
Details: idenified in Puna CDP
❑ Multi Hazard
Details:
provide details:
[J Other Plans
Details: Pdhoo Village Dev. Plan, Pahoa Public Safety Portership Crime Prevention Acti
❑ Mitigation Plan
Details:
Additional info:
13. CTY. MATCHING FUNDS REIXD? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? /if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
R] Promotes energy and resource conservation LJ Reduces hazard risk JEI Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis El Promotes economic vitality Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
0 Previously Appropriated
0 Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El can realistically encumber funds
List phases already completed:
Additional info: Federal funds are not available due to Pahoa Village sitting in Lava Zone 2 and is a risk factor, according to HUD rules.
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
500
$500
Construction
1,500
$1,500
TOTAL:
$2,000
$2,000
18. 0 & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
2,000
$2,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$2,000
1
1
1
1 $2,000
(This Page Intentionally Left Blank)
DEPARTMENT OF
FINANCE
DIANE NAKAGAWA,
DIRECTOR
115
(This Page Intentionally Left Blank)
116
Department: Finance
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
(in thousands)
FUNDING FORECAST BY FISCAL YEAR
(in thousands)
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private"
CBA,
Other"
Prior
Funds
Allotted
;-.T is=�>-
--Request.
.2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond
years
1
Kilauea Lava Recovery -State Loan FEMA Match
37,895
37,895
37,895
2
3
4
5
-
6
7
8
;
9
10
TOTAL
-
37,895
37,895,
-
-
-
-
37,895
Created By: Douglas Nam Le - ' Private: Foundation Grants
Date: 2/1/2024 " Community Benefit Assessments: Fair Share, Park Dedication, Etc. Other: GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Finance
2. SUBMITTER: Douglas Nam Le DATE: 2/1/2024
3. PROJECT NAME: Kilauea Lava Recovery- State Loan FEMA Match
4. LOCATION (COUNCIL DISTRICT): 4
5. COUNCIL BENEFIT DISTRICT(S): 4
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: None - State Funded
B. PROJECT ELIGIBILITY, ✓ all
R1 Land acquisition
0 Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, "one:
that apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
0 Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
This project represents the matching funds for the various FEMA approved projects related to the 2018 Kilauea volcanic eruption where a County match is required. This project is funded by the
$40 million loan from the State of Hawai'i. This project will encompass all phases for each of the projects, however, exact amounts are not available.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: B
Needed to continue current level ofservices.
A. Addresses public health/safety, ✓if Yes: 0
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
[D Access to 2 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes:
Project will restore full operations to asset.
F. Fosters inter -departmental collaboration
✓if Yes:
Additional info:
12. LONG RANGE PLANS/
❑Dept. Priority
Details:
❑Comm. Value
Details:
COMMUNITY VALUES, check at
[I General Plan
Details:
❑Admin Priority
Details:
least one and all that apply,
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑ DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑ DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply: ❑ Promotes energy and resource conservation
Provide additional information as appropriate: ❑ Cost benefit analysis
❑ Reduces hazard risk
JEI Preserves/protects our natural/cultural env.
❑ Promotes economic vitality
10 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
0 Project currently underway
Ei Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
37,895
$37,895
TOTAL:11
$37,895
$37,895
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
State Revolving Fund
37,895
$37,895
State OF
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL-11
$37,895
1
$37,895
(This Page Intentionally Left Blank)
FIRE DEPARTMENT
KAZUO TODDY
FIRE CHIEF
121
(This Page Intentionally Left Blank.)
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
Department: FIRE
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
in thousands
FUNDING FORECAST BY FISCAL YEAR
in thousands)
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private*
CBA,
Other**
Prior
Funds
Allotted
This
Request
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond 6
years
1
FIRE- Hawaiian Paradise Park Station
10,000
1
10,000
1 10,000
2
'
3
4
5
6
7
8
9
10
TOTAL
10,000
10,000
10,000
Created Bv: LRB
* Private: Foundation Grants
Date: 5/16/2024 ** Community Benefit Assessments: Fair Share, Park Dedication, Etc. Other., GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank.)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Fire Department
2. SUBMITTER: Ashley Kierkiewicz DATE: 5/9/2024
3. PROJECT NAME: FIRE - Hawaiian Paradise Park Station
4. LOCATION (COUNCIL DISTRICT): 4
S. COUNCIL BENEFIT DISTRICT(S): 4
6. TMK/CDP PLANNING AREA: (3) 1-5-040:065/ Puna
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 10,000,000
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
❑ Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
I ❑ Nonrecurring rehabilitation
I ❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Expansion of existing station which currently does not provide sufficient parking for fire apparatus and ambulance, doesn't allow for adequate exhaust ventilation, and doesn't provide adequate
living facilities and currently has one restroom and shower facilities for four personnel (including females).
11. PROJECr JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, ✓if Yes: 0
Eliminates a documented hazard.
B. Service improvements, Val[ that apply:
FYI Access to F7J Quality of F, Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info:
12. LONG RANGE PLANS/
(] Dept. Priority
Details: To achieve Department's mission and goals.
❑ Comm. Value
Details: first responders provide essential services to a growing community
COMMUNITY VALUES, check
U General Plan
Details: would meet the needs of a growing community
❑Admin Priority
Details:
at least one and all that apply,
LJ CDP
Details: identified in Puna CDP as a priority
rl Multi Hazard
Details:
provide details:
❑ Other Plans
Details: identified in the Hawaiian Paradise Park Community Development Plan
❑Mitigation Plan
Details:
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
(] Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
project currently underway
K
121 Previously Appropriated
ElStaff available to manage project
❑ External funds/resources ready to proceed
that apply:
Identified operating budget needs
0 Can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
10,000
$10,000
TOTAL:
$10,000
$10,000
18. 0 & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
10,000
$10,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$10,000
1$30,000
(This Page Intentionally Left Blank.)
HAWAVI POLICE
DEPARTMENT
BENJAMIN MOSZKOWICZ,
POLICE CHIEF
127
(This Page Intentionally Left Blank)
128
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
Department: Police
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
(in thousands)
FUNDING FORECAST BY FISCAL YEAR
(in thousands)
TOTAL
ESTIMATED
PROJECT .
COST
County
G.O. Bond
State
Federal
Private`
CBA,
Other—
Prior
Funds
Allotted
This
Request,
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond
years
1
HPD- Kea'au Police5tation
1,500
1,500
1,500
2
HPD- Public Safety Complex Facility Improvements
1,250
1,250
1,250
3
HPD - East Hawaii Evidence Storage Warehouse
150
150
1,500
1,650
4
HPD - West Hawaii Evidence Storage Warehouse
185
415
600
700
1,300
5
HPD - East Hawaii Firing Range & Training Complex
600
600
6,000
6,600
6
HPD- Hawaiian Ocean View Estates Police Substation
150
150
1,500
1,650
7
HPD- Holding Cell Improvements
600
600
600
B
HPD- South Kona Police Station
1,400
5,600
7,000
9
10
TOTAL
4,435
-
-
415
1,40D
4,8501
9,700
1
5,600
1 21,550
Created By: Benjamin T. Moszkowicz . Private: Foundation Grants
Date: 1/24/24 (revised) " Community Benefit Assessments: Fair Share, Park Dedication, Etc. Other., GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Police Department - Administration 12.
SUBMITTER: Police Chief Benjamin Moszkowicz DATE: 1/24/2024
3. PROJECT NAME: HPD - Kea'au Police Station
4. LOCATION (COUNCIL DISTRICT): Kea'au
S. COUNCIL BENEFIT DISTRICT(S): District 3, Puna
6. TMK/CDP PLANNING AREA: N/A
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,500,000
S. PROJECT ELIGIBILITY, ✓ all
E Land acquisition
❑ Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
❑ Information/communications tech.
El High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Land acquisition, plan, design, construct a new police station in Kea'au
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current servicesforunderservedarea/demographic.
A. Addresses public health/safety, ✓if Yes: 7
Reduces risk of a documented hazard.
B. Service improvements, Vail that apply:
ED Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
N/A
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
itiona in o: ea y, the size o the acl ity must a su icient to house a commandsta , which we project to include seventy sworn personnelan our civilian employees. e a oa Police Station is current y eing
utilized as the main station for the entire Puna District. This facility space is shared between the Police Department and the Fire Department and is overcrowded and not centrally located, which delays police response in the
12. LONG RANGE PLANS/
Dept. Priority
Details: Provide the highest quality of police services
❑Comm. Value
Details: Provide the highest quality of police services
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Admin Priority
Details:
least one and all that apply,
provide details:
❑� CDP
Details: Part of County plan for area
E] Multi Hazard
Details:
Details:
El Other Plans
Details:
❑ Mitigation Plan
Additional info: In line with the Department's Vision and Mission statement of providing the highest quality of police services.
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
JE Strengthens and sustains our community
Additional info: Increased demand for police services in line with population growth.
16. PROJECT READINESS, ✓all
❑ project currently underway
❑ Previously Appropriated
❑Staff available to manage project
❑External funds/resources ready to proceed
that apply:
El Identified operating budget needs
Elcan realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
1,000
$1,000
Land Acquisition
500
$500
Design/Survey
Construction
TOTAL:I
$1,500
$1,500
18. O & M COSTS (x $1000):
19 FUNDING SOURCE (x $1000):
Cty G.O. Bond
1,500
_
J
$1,500
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:11
$1,500
1
$1,500
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Police Department- Administration
2. SUBMITTER: Police Chief Benjamin Moszkowicz DATE: 1/24/2024'
3. PROJECT NAME: HPD - Public Safety Complex Facility Improvements
4. LOCATION (COUNCIL DISTRICT): 2, Hilo
5. COUNCIL BENEFIT DISTRICT(S): 2, Hilo
6. TMK/CDP PLANNING AREA: 2-4-25:28-33
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,250,000
8. PROJECT ELIGIBILITY, ✓ all I
❑ Land acquisition
Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED,,/one:
that apply: I
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
R] High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Replace the two cooling towers, paint complex (Buildings A & B), and perform facility improvements at the Public Safety Complex in Hilo (Police and Civil Defense)
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes:
Reduces risk of a documented hazard.
B. Service improvements, 'all that apply:
❑ Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓ifyes: ❑
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
A ditional in o: T e current condition of the Public Safety Comp ex is very poor. The paint is peeling and mildew moss have grown on some surfaces. The cooling towers that service the air conditioning units for the entire
nml2lpx are old and obsolete and reou'red costly repairs several times the last year, Unprofe ional appearance is seen by the general nubloc when they first arrive at the police station and this area is heavily used.
12. LONG RANGE PLANS/
❑Dept. Priority
Details:
❑Comm. value
Details:
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Admin Priority
Details:
least one and al I that apply,
provide details:
❑ CDP
Details:
Multi Hazard
Details: Mildew/moss causes slippery conditions
Details:
❑Other Plans
Details:
❑ Mitigotion Plan
Additional info:
13. CTY. MATCHING FUNDS RECI'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓al I that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
10 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
JEI strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑Can realistically encumberfunds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
1,250
$1,250
TOTAL:
$1,250
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
1,250
$1,250
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:11
$1,250
1
$1,250
(This Page Intentionally Left Blank)
w
to
County of Hawai'i
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Police Department
2. SUBMITTER: Police Chief Benjamin Moszkowicz DATE: 1/24/2024
3. PROJECT NAME: HPD - East Hawai'i Evidence Storage Warehouse
4. LOCATION (COUNCIL DISTRICT): All
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: 2-2-058:018
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 150,000
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
❑ Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, one:
that apply:
D Nonrecurring rehabilitation
10 Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Evidence warehouse in Hilo is needed to house vehicles seized as evidence that are currently housed outdoors. Approximate size needed is 250' x 50' (12,500 square feet)
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., -if Yes:
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: 0
Eliminates a documented hazard.
B. Service improvements, ✓all that apply:
❑ Access to ❑ Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes: ❑
NIA
Additional info:
12. LONG RANGE PLANS/
❑Dept. Priority
Details:
❑Comm. value
Details:
COMMUNITY VALUES, check at
❑General Plan
Details:
❑AdminPriority
Details:
least one and all that apply,
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
❑ Other Plans
Details:
❑ Mitigation Plan
Additional info:
13. Cry. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ,if Yes: 0
I DESCRIBE: Police Department is obligated by law to seize vehicles connected to criminal cases.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
El Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
❑ Strengthens and sustains our community
Additional info: Increased demand for police services in line with population growth.
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑ Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
1 FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
150
$150
Land Acquisition
Design/Survey
1,500
$1,500
Construction
TOTAL:11
$150
1 $1,500
1
$1,650
18 O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
150
1,500
$1,650
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$150
$1,500
$1,650
(This Page Intentionally Left Blank)
County of HawaN
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Police Department 112.
SUBMITTER: Police Chief Benjamin Moszkowicz DATE: 1/24/2024
3. PROJECT NAME: HPD- West Hawaii Evidence Storage Warehouse 114.
LOCATION (COUNCIL DISTRICT): 8
5. COUNCIL BENEFIT DISTRICT(S): 8 116.
TMK/CDP PLANNING AREA: 7-4-020:021/Kona
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 600,000 11
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
❑ Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
I ❑ Planning, feasibility, eng., or design study
I ❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Construct a 5,000 square feet evidence warehouse at the Kealakehe Police Station site.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., 'If Yes:
Fills gap in current services.
A. Addresses public health/safety, ✓if Yes: ❑�
Reduces risk ofa documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost butimproves services.
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
NIA
F. Fosters inter -departmental collaboration
Yes: ❑
N/A
Additional info: Evidence facility at the Kealakehe Police Station has been over capacity for many years, requiring department to lease commercial storage facilities that creates undue security risks.
12. LONG RANGE PLANS/
❑r Dept. Priority
Details: Comply with national standards set for security and control of evidence
OComm. Value
Details: Ensures the security and control of evidentiary property
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Admin Priority
Details:
least one and all that apply,
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
❑OtherPlons
Details:
❑ Mitigation Plan
Additional info: Facilities being utilized include two shipping (Matson) containers that are located at the Kealakehe Police Station
13. CTY. MATCHING FUNDS REQ'D? 'if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓al I that apply:
Provide additional information as appropriate:
I ❑ Promotes energy and resource conservation
❑ Reduces hazard risk
JEI Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
❑ Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
100
$100
Construction
500
700
$1,200
TOTAL:
$600
$700
$1,300
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
185
700
$885
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
415
$415
Other Cty Fund - (describe)
TOTAL:
$600
1 $700
1
1
$1,300
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Hawai'i Police Department
2. SUBMITTER: Police Chief Benjamin Moszkowicz DATE: 1/24/2024
3. PROJECT NAME: HPD - East Hawai'i Firing Range & Training Complex
4. LOCATION (COUNCIL DISTRICT): All
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: 2-4-25:28
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 600,000
8. PROJECT ELIGIBILITY, ✓ all
E Land acquisition
❑ Infrastructure improvement
El New bldg., structure, or addition 119.
PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Plan, design, and construct a new firing range and training room complex
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 1z
Addresses anticipated future need.
A. Addresses public health/safety, ✓if Yes:
Reduces risk of o documented hazard.
B. Service improvements, ✓all that apply:
❑� Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, -ifYes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info: Firearms training
of personnel is currently conducted on private lands in Kamuela or Pohakuloa Military Area as department indoor range is inadequate and has only three stalls.
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Ensure officers are properly trained in the use of their firearms
0 Comm. value
Details: Ensure officers are properly trained in the use of their firearms
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Admin Priority
Details:
least one and all that apply,
provide details:
Elcop
Details:
M Multi Hazard
Details: Inadequately trained police officers in firearms use may increase litigation
Details:
❑Other Plans
Details:
E]Mitigation Plan
Additional info: Access to private lands will eventually not be allowed and gaining access to the military training area is becoming increasingly difficult.
13. CTY. MATCHING FUNDS RECCD? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
❑ Promotes economic vitality
❑ Strengthens and sustains our community
Additional info: Increased demand for police services in line with population growth
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
600
$600
Construction
6,000
$6,000
TOTAL:
$600
1 $6,000
1
$6,600
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
600
6,000
$6,600
State Revolving Fund
State CIP
Fed era I
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$600
$6,000
$6,600
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Hawaii Police Department
2. SUBMITTER: Police Chief Benjamin Moszkowicz DATE: 1/24/2024
3. PROJECT NAME: HPD - Hawaiian Ocean View Estates Police Substation
4. LOCATION (COUNCIL DISTRICT): 6
S. COUNCIL BENEFIT DISTRICT(S): 6
6. TMK/CDP PLANNING AREA: None at this time
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 150,000
S. PROJECT ELIGIBILITY, V. all
El Land acquisition
❑Infrastructure improvement
El New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
I ❑ Planning, feasibility, eng., or design study
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Land acquisition, plan, design, construct new police substation in Hawaiian Ocean View Estates, Ka'G.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., /if Yes: 0
Needed to continue current level of services.
A. Addresses public health/safety, ✓if Yes: D
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
❑� Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes: ❑
N/A
Additional info: T e Ka u Distnct encompasses 900 square miles and includes the largest subdivision in the LiMted States. The Population in and around Hawaiian Ocean View Estates, which includes Hawaiian Ocean View
Ranchos, Kahuku Country Gardens, Kula Kai View Estates, Kona Gardens, Keoke's Ranchos, and Kona view Estates, has grown by well over 45% from 2000 to 2010. Hawai'i county currently rents an inadequate one -room wooden
'Lampd Ortirturp that ig loratpri in the miridlp of a htjq4nPr,,; roMplpx in Pohnp Pla7;; Center. where spcuritV and functionality of rnnr-prn.
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Provide the highest quality of police services
❑v Comm. Value
Details: Provide the highest quality of police services
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Admin Priority
Details:
least one and all that apply,
provide details:
❑CDP
Details:
Multi Hazard
Details:
Details:
❑ DtherPlons
Details:
❑Mitigation Plan
Additional info: In line with the Department's Vision and Mission statement of providing the highest quality of police services.
13. cry. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I ❑ Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
JEJ Cost benefit analysis
❑ Promotes economic vitality
10 Strengthens and sustains our community
Additional info: Increased demand for police services in line with population growth.
16. PROJECT READINESS, all
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
❑ Can realistically encumber funds
List phases already completed:
Additional in
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
150
$150
Design/Survey
1,500
$1,500
Construction
TOTAL:
$150
$1,500
$1,650
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
150
1,500
$1,650
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$150
$1,500
$1,650
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Hawai'i Police Department
2. SUBMITTER: Police Chief Benjamin Moszkowicz DATE: 1/24/2024
3. PROJECT NAME: HPD - Holding Cell Improvements
4. LOCATION (COUNCIL DISTRICT): All
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Hilo, Puna, N & S Kohala
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 600,000
8. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
❑ Infrastructure improvement
❑ New bldg., structure, or addition
IJEJ
9. PROJECT URGENCY/NEED, ✓one:
that apply: I
El Nonrecurring rehabilitation I
[A Planning, feasibility, eng., or design study
❑ Information/communications tech.
High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Plan, design, and construct to modify existing temporary detention facilities in the Hilo, Kona, Puna, North Kohala, and South Kohala districts to comply with the Commission on Accreditation for
Law Enforcement Agencies (CALEA) standards, Chapters 71 and 72, which requires separating males, females, and/or juveniles that are detained at the same time. The holding cells shall be
separated from each other by sight and sound.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bidg., 'if Yes: ❑
N/A
A. Addresses public health/safety, 'if Yes: P1
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to El Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net increase in operating cost but improves services.
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓ifyes: El✓if
NIA
F. Fosters inter -departmental collaboration
Yes: ❑
N/A
Additional info: Currently, officers are required to transport detainees to another facility to provide constant supervision until the facility is ready to accommodate that detainee.
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: Comply with notional standards set by CALEA
❑� Comm. Value
Details: Promote conditions that contribute to the health/security of the detainees
COMMUNITY VALUES, check at
❑General Plan
Details:
❑Adman Priority
Details:
least one and all that apply,
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info: Holding cell improvements will enhance the ability of the staff to promote conditions that contribute positively to the health and security of the detainees and the safety of others.
13. CTY. MATCHING FUNDS RE(XD? ✓if Yes: ❑
1 DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: 0
DESCRIBE: Separation of juveniles is mandated, and CALEA Standard 72.5.3. includes females.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I ❑ Promotes energy and resource conservation
10 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
ID Cost benefit analysis
❑ Promotes economic vitality
ILI strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑ Project currently underway
❑ Previously Appropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
El Can realistically encumber funds
List phases already completed:
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
600
$600
TOTAL:
$600
$600
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $3000):
Cty G.O. Bond
600
$600
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$600
1
$600
(This Page Intentionally Left Blank)
MASS TRANSIT AGENCY
VICTOR KANDLE,
ADMINISTRATOR
145
(This Page Intentionally Left Blank)
146
Department: Mass Transit
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
(in thousands)
FUNDING FORECAST BY FISCAL YEAR
(in thousands)
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private'
CBA,
Other-
Prior
Funds
Allotted
Is
Request
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond 6
years
1
IMTA - Bus Stop ADA Compliance
1,000
220
2,613
1,220
500
Soo
50
-
-
4,883
2
MTA- Islandwide Bus Shelter
300
840
300
300
300
300
300
300
300
2,940
3
MTA - Pahoa Hub Planning and Construction
4,000
900
2,360
3,450
7,260
1,200
11,910
4
MTA - Bus Stop Signage
15
45
IS
15
15
1
1
1
1
94
5
MTA- Zero Emissions Infrastructure(Hilo Base)
6,000
2,200
1,000
8,200
5,500
650
15,350
6
MTA -Zero Emissions Infrastructure (Kona Base/Maintenance Facility)
350
3,596
350
14,000
2,500
1,200
-
-
-
21,646
7
MTA- Waimea Hub Planning and Construction
525
525
4,250
3,000
6,650
6,650
6,650
-
27,725
8
MTA- Kailua/Kona Hub Planning and Construction
525
525
1,200
3,000
4,725
9
MTA- Park and Ride Lots
1,070
250
1,070
1,070
1,070
1,070
1,070
-
-
5,600
10
MTA - Hilo Base Yard Expansion (Maintenance -Office -Training)
325
125
325
4,236
-
-
-
-
-
4,686
TOTAL
12,795
900
5,560
-
535
11,919
19,790
32,271
11,035
9,271
8,021
6,9511
3011
99,559
Created By: Victor Kandle ' Private: Foundation Grants
Date: 12/27/2023 '* Community Benefit Assessments: Fair Share, Park Dedication, Etc. Other., GET, Fuel Tax and other non -bond sources
(This Page Intentionally Left Blank)
.P
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Bus Stop ADA Compliance
4. LOCATION (COUNCIL DISTRICT): All
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 220,000
S. PROJECT ELIGIBILITY, ✓ all
Land acquisition
Infrastructure improvement
El New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
R] Planning, feasibility, eng., or design study
❑ Information/communications tech.
El High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Desgin and construct ADA pads for passengers to board buses at safe locations along State and County right-of-way.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: R1
Needed to continue current level ofservices.
A. Addresses public health/safety, ✓if Yes: ❑
Community concerns exists around conditions.
B. Service improvements, ✓all that apply:
Access to U1 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
Reduces cost by 20% or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: 0
Project will restorefulloperations toasset.
F. Fosters inter -departmental collaboration
✓if Yes: 0
DPW
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Provides a safe place for passengers to ride Hele-On
Comm. Value
Details: Provides an opportunity for the communities to board buses in safe places
COMMUNITY VALUES, check
❑ General Plan
Details: Included in the transit portion of the General Plan
❑ Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at least one and all that apply,
provide details:
CDP
Details: Included in the seven CDPs
❑ Multi Hazard
Details:
Details:
❑other Plans
Details: Included in the Multi -Modal Transit and Transportation Mosier Plan
❑Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
I DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: 0
DESCRIBE: ongoing DOJ interest
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I [j] Promotes energy and resource conservation
El Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis
El Promotes economic vitality
0 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
0 Project currently underway
Previously Appropriated
0 Staff available to manage project
0 External funds/resources ready to proceed
that apply:
❑� Identified operating budget needs
El can realistically encumber funds
List phases already completed: Planning
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
5
5
5
5
5
$25
Land Acquisition
10
10
10
10
10
$50
Design/Survey
580
250
235
235
5
$1,305
Construction
2,018
955
250
250
30
$3,503
TOTAL-.11
$2,61311
$1,220
1 $500
1 $500
1 $50
1
$4,883
18. O & M COSTS (x$1000):
5
$15
$20
$25
$30
$35
$40
$40
$210
19. FUNDING SOURCE (x$1000):
CtyG.O. Bond
State Revolving Fund
State CIP
Federal
1,613
1,000
$2,613
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe) GET
1,00011
220
1 500
1 500
1 50
1
$2,270
TOTAL:111
$1,220
1 $500
1 $500
1 $50
1
$4,883
(This Page Intentionally Left Blank)
County of Hawai'i
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Islandwide Bus Shelters
4. LOCATION (COUNCIL DISTRICT): All
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 300,000
B. PROJECT ELIGIBILITY, ✓ all
0 Land acquisition
Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
I ❑ Information/communications tech.
0 High ❑ Med. ❑ Low
DESCRIPTION: 10. PROJECT/PROGRAM
Construct bus shelters island -wide, as well as replace damaged shelters or relocate bus shelters from areas that are no longer served by Hele-On
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Needed to continue current level ofservices.
A. Addresses public health/safety, ✓if Yes: ❑
Community concerns exists around conditions.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Reduces cost by 20%or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes:
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
"if Yes: 0
DPW
Additional info:
12. LONG RANGE PLANS/
0 Dept. Priority
Details: Provides a safe place for passengers to ride Hele-On
0 Comm. value
Details: Provides an opportunity for the communities to board buses in safe places
COMMUNITY VALUES, check
0 General Plan
Details: Included in the transit portion of the General Plan
❑Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at least one and all that apply,
provide details:
CDP
Details: Included in the seven CDPs
❑ Multi Hazard
Details:
Details:
❑ Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? /if Yes: ❑
DESCRIBE:
15. SLISTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I 0 Promotes energy and resource conservation
0 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
0 strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
0 Project currently underway
0 Previously Appropriated
❑ Staff available to manage project
External funds/resources ready to proceed
that apply:
E] Identified operating budget needs
0 Can realistically encumber funds
List phases already completed: Planning
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25 I
FY 25-26
1 FY 26-27
1 FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
10
10
10
10
10
10
10
10
$80
Land Acquisition
130
130
130
130
130
130
130
130
$1,040
Design/Survey
10
10
10
10
10
10
10
10
$80
Construction
690
150
150
150
150
150
150
150
$1,740
TOTAL:
$840
$300
1 $300
$300
$300
$300
$300
$300
$2,940
18. O & M COSTS (x $1000):
97811
$1,008
1 $200
1 $225
1 $250
1 $300
1 $325
1 $325
1 $3,611
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
State Revolving Fund
State CIP
Federal
540
$540
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe) GET
300
300
1 300
300
300
300
300
300
$2,400
TOTAL:
$8401
$300
1 $300
1 $300
1 $300
J $300
1 $300
1 $300
$2,940
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA- Pahoa Hub Planning -Construction
4. LOCATION (COUNCIL DISTRICT): 4 & 5
S. COUNCIL BENEFIT DISTRICT(S): Pahoa
6. TMK/CDP PLANNING AREA: Pahoa
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 4,000,000
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
0 Infrastructure improvement
[21 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
El Planning, feasibility, eng., or design study I
❑ Information/communications tech.
0 High ❑ Med. ❑Low
10. PROJECT/PROGRAM
DESCRIPTION:
Construct transit hubs in Pahoa with bus bays, shelters, benches, trash cans, bike racks, parking, building with community room/restroom, electric vehicle charging and secure bus parking.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: [21
Fills gap in current servicesforunderservedoreo/demographic.
A. Addresses public health/safety, ✓if Yes: ❑
NIA
B. Service improvements, Vail that apply:
1Z Access to 21 Quality of P] Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Reduces cost by 20%or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes:
Planning
Additional info:
12. LONG RANGE PLANS/
El Dept. Priority
Details: Provides a safe place for passengers to ride Hele-onComm.
value
Details: Provides an opportunity for the communities to board buses in safe places
COMMUNITY VALUES, check at
least and all that apply,
General Plan
Details: Included in the transit portion of the General Plan
❑� Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
one
provide details:
�CDP
Details: Included in the Pahoa and KonoCDPs
El Multi Hazard
Details:
Details:
Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: [Z
I DESCRIBE: Mass Transit Agency will persue FTA funds and when successful, 20% local match will be required using GET
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
E] Promotes energy and resource conservation
0 Reduces hazard risk
10 Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
0 Promotes economic vitality
10 strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
1 Project currently underway
0 Previously Appropriated
0 Staff available to manage project
External funds/resources ready to proceed
that apply:
1Z Identified operating budget needs
0 Can realistically encumber funds
List phases already completed: None
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
500
1,100
$1,600
Land Acquisition
1,000
1,000
$2,000
Design/Survey
450
750
$1,200
Construction
1,500
4,410
1,200
$7,110
_TOTAQF
$3,45011
$7,260
1 $1,200
1
$11,910
18. O & M COSTS (x $3000):
$5
$6
$8
$10
$10
1
$39
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
3,000
4,000
1,200
$8,200
State Revolving Fund
State CIP
450
900
$1,350
Federal
2,360
$2,360
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:11
$3,450
H $7,260
1 $1,200
1
$11,910
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support 12.
SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Bus Stop Signage
4. LOCATION (COUNCIL DISTRICT): 3
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 15,000
B. PROJECT ELIGIBILITY, ✓ all
❑ Land acquisition
0 Inf struc rature improvement
E] New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
❑ Planning, feasibility, eng., or design study I
❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Purchase 500 bus stop signs and decals for installation at each bus stop located throughout Hawai'i Island.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑
N/A
A. Addresses public health/safety, ✓if Yes: 121
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to E Quality of [21 Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
Reduces cost by 20% or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ifYes: ❑
NIA
F. Fosters inter -departmental collaboration
-if Yes: F3
DPW
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: Provides identification of where to board Hele-On buses
Comm. Value
Details: Provides an opportunity for the communities to know where to board buses
COMMUNITY VALUES, check
least and all that apply,
❑ General Plan
Details: Included in the transit portion of the General Plan
Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at one
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
❑� Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS RECI'D? ✓if Yes: 0
DESCRIBE: The Mass Transit Agency will persue FTA funds and when successful, 20% local match will be required using GET
14. LEGAL MANDATE? /if Yes: ❑
I DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
Promotes energy and resource conservation
JE Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis
0 Promotes economic vitality
121 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓al I
❑� Project currently underway
[2] Previously Appropriated
Staff available to manage project
IDExternal funds/resources ready to proceed
that apply:
El Identified operating budget needs
E] Can realistically encumber funds
List phases already completed: Design
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
I FY 25-26
1 FY 26-27
1 FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
45
15
15
15
1
1
1
1
$94
TOTAL:
$45
$15
1 $15
I $15
1 $1
$1
1 $1
$1
$94
1s. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe) GET
45
15
15
15
1
1
1
1
$94
TOTAL:
$451
$15
$15
$15
$1
$1
1 $1
$1
$94
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Zero Emissions Infrastructure (Hilo Base)
4. LOCATION (COUNCIL DISTRICT): 3
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 6,000,000
PROJECT ELIGIBILITY, ✓ all
El Land acquisition
� Infrastructure improvement
El New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
t,
that apply:
❑ Nonrecurring rehabilitation
E Planning, feasibility, eng., or design study
❑ Information/communications tech.
I E High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Construct battery electric charging and hydrogen stations at Hilo Maintance Facility to support Mass Transit Agency's zero emission vehicles fleet through a public -private partnership.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infra/bldg., ✓if Yes: 0
Needed to continue current level ofservices.
A. Addresses public health/safety, ✓if Yes: El
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
Access to R] Quality of (] Quantity of
E. Operational efficiency and leveraging
opportunities:
Results In net decrease in operating cost and improves services.
Reduces cost by 20% or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, 'if Yes: ❑
N/A
F. Fosters inter -departmental collaboration
✓if Yes: 0
DPW
Additional info:
12. LONG RANGE PLANS/
VALUES,
❑ Dept. Priority
Details: Implements the ronsition to zero emission buses
Comm. value
Details: Improve air quallity, reduces noise through transition to zero emission buses
COMMUNITY check
least one and all that apply,
❑ General Plan
Details: Included in the transit portion of the General Pion
Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at
provide details:
❑SDP
Details:
❑Multi Hazard
Details:
Details:
❑✓ Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: 0
DESCRIBE: The Mass Transit Agency will persue FTA funds and when successful, 20% local match will be required using GET
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
21 Promotes energy and resource conservation
Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
El Promotes economic vitality
ILI Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
E Project currently underway
ElPreviously Appropriated
Staff available to manage project
External funds/resources ready to proceed
that apply:
PDI Identified operating budget needs
Jul Can realistically encumber funds
List phases already completed. None
Additional info:
17. EXPENDITURE PHASING (X $1000): IF I
Prior Funds Allotted
(not la sed)
This Request
FY 24-25
FY 25-26
1 FY 26-27
1 FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
200
285
250
$735
Land Acquisition
Design/Survey
200
354
250
$804
Construction
600
7,561
5,000
650
$13,811
TOTAL]i
$8,200
1 $5,500
1 $650
1
$15,350
18. O & M COSTS (x $1000):
$100
$200
$250
$300
$350
$400
$450
$2,050
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
Soo
6,000
5,000
650
$12,150
State Revolving Fund
State CIP
Federal
Soo
2,200
500
$3,200
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:11
$1,00011
$8,200
1 $5,500
1 $650
1
1
915,350
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Zero Emissions Infrastructure (Kona Base/Maintenance Facility)
4. LOCATION (COUNCIL DISTRICT): 6,7
S. COUNCIL BENEFIT DISTRICT(S): 6, 7, 8 or 9
16. TMK/CDP PLANNING AREA: Kona
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 350,000
8. PROJECT ELIGIBILITY, ✓ all
U Land acquisition
Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, "one:
that apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
I ❑ Information/communications tech.
0 High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
To perform planning, design, engineering, land acquisition, construction of a new base yard in Kailua-Kona to support transit operations West and North Hawai'i County. To construct battery
charging and hydrogen stations in Kailua-Kona to support Mass Transit's zero emission vechicles fleet.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 21
Needed to continue current level afservices.
A. Addresses public health/safety, ✓if Yes: ❑
N/A
B. Service improvements, ✓all that apply:
0 Access to E Quality of [21 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Reduces cost by 20% or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
NIA
F. Fosters inter -departmental collaboration
✓if Yes: 21
DPW
Additional info:
12. LONG RANGE PLANS/
VALUES,
❑' Dept. Priority
Details: A lows or the County to provide maintaince and administrative services in
West & North Hawaii County
❑� comm. value
Details: Ensures a reliablefleet as buses can be maintained timely when theyfail in West &
North Howai'I County
COMMUNITY check
least one and all that apply,
❑� General Plan
Details: Included in the transit portion of the General Plan
Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
0 Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? -if Yes:
DESCRIBE: Mass Transit Agency will persue FTA funds and when successful, 20% local match will be required using GET
14. LEGAL MANDATE? 'if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
I [D Promotes energy and resource conservation
ID Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis
0 Promotes economic vitality
ILI Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
❑� Project currently underway
� Previously Appropriated
Staff available to manage project
0 External funds/resources ready to proceed
that apply:
JE Identified operating budget needs
E Can realistically encumberfunds
List phases already completed: None
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted I
(not lapsed)
This Request
11 FY 24-25
1 FY 25-26
1 FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
546
175
$721
Land Acquisition
1,500
$1,500
Design/Survey
1,550
175
$1,725
Construction
14,000
2,500
1,200
$17,700
TOTAL:
$3,59611
$350
1 $14,000
1 $2,500
1 $1,200
1
$21,646
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
$475
$500
$525
$1,500
Cty G.O. Bond
860
350
14,000
2,500
1,200
$18,910
State Revolving Fund
State CIP
Federal
2,736
$2,736
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$3,596
$350
1 $14,000
1 $2,500
1 $1,200T
$21,646
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Waimea Hub Planning -Construction
4. LOCATION (COUNCIL DISTRICT): 1,9
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Waimea
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 525,000
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
El Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurringrehabilitation
El Planning, feasibility, eng., or design study
I ❑ Information/communications tech.
I ❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Construct transit hubs in Waimea with bus bays, shelters, benches, trash cans, bike racks, parking, building with community room/restroom, electric vehicle charging and secure bus parking.
3l. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current services for underserved area/demographic.
A. Addresses public health/safety, /if Yes: ❑
NSA
B. Service improvements, ✓all that apply:
0 Access to El Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Reduces cost by 20Y or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
NIA
F. Fosters inter -departmental collaboration
Yes: 0
planning
Additional info:
12. LONG RANGE PLANS/
COMMUNITY VALUES, check
❑' Dept. Priority
p y
Details: Provides a sae lace or passengers to ride Hele-On
f p f p g
Comm. Value
Details: Provides an o
opportunityfor the communities to board buses in sole places
at least one and all that apply,
0 General Plan
Details: Included in the transit portion of the General Plan
Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
provide details:
❑� CDP
Details: Included in the Pahoo and Kona CDPs
Multi Hazard
Details:
Details:
❑ Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: [2]
DESCRIBE: Mass Transit Agency will persue FTA funds and when successful, 20% local match will be required using GET
14.LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
Q Promotes energy and resource conservation
0 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
[±_1 Promotes economic vitality
L11 Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
project currently underway
0 Previously Appropriated
0 Staff available to manage project
0 External funds/resources ready to proceed
that apply:
E Identified operating budget needs
0 Can realistically encumber funds
List phases already completed: None
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
1 FY 26-27
1 FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
Construction
300
225
150
1,000
500
2,600
3,000
$450
$1,000
$725
$5,600
TOTAL:
$525
$4,250
$3,000
$6,650
$6,650
$6,650
$27,725
18. O & M COSTS (x$1000):
$5
$6
$8
$101
$10
$39
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
525
4,250
3,000
6,650
6,650
6,650
$27,725
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$525
$4,250
$3,000
$6,650
$6,650
$6,650
$27,725
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Kailua-Kona Hub Planning and Construction
4. LOCATION (COUNCIL DISTRICT): 6,7
S. COUNCIL BENEFIT DISTRICT(S): 6, 7, 8 or 9
6. TMK/CDP PLANNING AREA: Kona
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 525,000
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
2 Infrastructure improvement
El New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
0 Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High 0 Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
To perform planning, design, engineering, land acquisition, construction of a new base yard in Kailua-Kona to support transit operations West and North Hawai'i County.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: P1
Needed to continue current level ofservices.
A. Addresses public health/safety, ✓if Yes: ❑
N/A
B. Service improvements, ✓all that apply:
El Access to E Quality of 0 Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
Reduces cost by 20% or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of _
facility/infrastructure/building, ✓if Yes: L1
N/A
F. Fosters inter -departmental collaboration
✓if Yes:
DPW
Additional info:
12. LONG RANGE PLANS/
❑ Dept. Priority
Details: A lows or the County to provide maintaince and administrative services in
West & North Hawaii County
0 Comm. value
Details: Ensures a reliablefleet as buses can be maintained timely when t ey ail in West &
North Howai'l County
COMMUNITY VALUES, check
least that
General Plan
Details: Included in the transit portion of the General Plan
Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at one and all apply,
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
❑� Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: 0
I DESCRIBE: Mass Transit Agency will persue FTA funds and when successful, 20% local match will be required using GET
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
0 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
El Promotes economic vitality
ILI strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
Project currently underway
Q Previously Appropriated
0 Staff available to manage project
External funds/resources ready to proceed
that apply:
r[21 Identified operating budget needs
� Can realistically encumber funds
List phases already completed: None
17. EXPENDITURE PHASING (X $1000): I IFPrior
Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
300
$300
Land Acquisition
1,000
$1,000
Design/Survey
225
200
$425
Construction
3,000
$3,000
TOTAL:
$525
$1,200
$3,000
$4,725
18. O & M COSTS (x $1000):
$5
$6
$8
$10
$10
$39
FUNDING SOURCE (x $1000):G.O. Bond
525
1,200
3,000
$4,725
e Revolving Fund
r
e CIP
eral
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$525
$1,200
$3,000
$4,725
(This Page Intentionally Left Blank)
County of Hawai'i
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA - Park and Ride Lots
4. LOCATION (COUNCIL DISTRICT): All
5. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,070,000
8. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
0 Infrastructure improvement
� New Bldg., structure, or addition
9. PROJECT URGENCY/NEED, "one:
that apply:
❑ Nonrecurring rehabilitation
El Planning, feasibility, eng., or design study
❑ Information/communications tech.
❑ High 0 Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
Build park and ride lots to transit hubs and at key locations on the island where people can park their vehicles and ride commuter buses to destinations around the island. Potential locations are
in Ocean View, Waimea, Hilo, Kailua-Kona and Honoka'a.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Fills gap in current servicesfor underserved area/demographic.
A. Addresses public health/safety, if Yes: ❑
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
Access to 0 Quality of E Quantity of
E. Operational efficiency and leveraging
opportunities:
No change in operating costs.
Reduces cost by 20%or more by bundling with adjacent projects.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
NIA
F. Fosters inter -departmental collaboration
Yes:
DPW
Additional info:
12. LONG RANGE PLANS/
VALUES,
❑' Dept. Priority
Details: Provides an opportunityforpotential riders to drive to ride Hele-On express
and intercommunity routes
Comm. value
Details: Provides an opportunity or potential riders to drive to ride Hele-On express and
intercommunity routes
COMMUNITY check
least one and all that apply,
0 General Plan
Details: Included in the transit portion of the General Plan
❑ Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at
provide details:
❑' CDP
Details: Included in the Pohoo and Kona CDPs
❑Multi Hazard
Details:
Details:
❑✓ Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: El
I DESCRIBE: The Mass Transit Agency will pursue FTA funds and when successful, 20% local match will be required using GET
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
Q Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
El Promotes economic vitality
1A Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
project currently underway
0 Previously Appropriated
0 Staff available to manage project
El External funds/resources ready to proceed
that apply:
EJ Identified operating budget needs
E Can realistically encumber funds
List phases already completed: None
Additional info:
17. EXPENDITURE PHASING (X $1000): IF
Prior Funds Allotted
(not lapsed) 11
This Request
FY 24-25
FY 25-26
1 FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
ISO
350
$500
Land Acquisition
370
300
300
300
300
$1,570
Design/Survey
100
350
70
70
70
70
$730
Construction
700
700
700
700
$2,800
TOTAL:
$25011
$1,070
1 $1,070
1 $1,070
1 $1,070
1 $1,070
1
$5,600
18. O & M COSTS (x $3000):
$25
$27
$29
$31
$33
$35
$37
$217
19. FUNDING SOURCE (x$1000):
Cty G.O. Bond
250
1,070
1,070
1,070
1,070
1,070
$5,600
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$250
$1,070
$1,070
$1,070
$1,070
$1,070
$5,600
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Mass Transit Agency, Administrative Support
2. SUBMITTER: Victor Kandle DATE: 12/27/2023
3. PROJECT NAME: MTA- Hilo Base Yard Expansion (Maintenance -Office -Training)
4. LOCATION (COUNCIL DISTRICT): 3
S. COUNCIL BENEFIT DISTRICT(S): All
6. TMK/CDP PLANNING AREA: Various
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 325,000
B. PROJECT ELIGIBILITY, ✓ all
El Land acquisition
Infrastructure improvement
0 New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
that apply:
❑ Nonrecurring rehabilitation
El Planning, feasibility, eng., or design study I
❑ Information/communications tech.
❑ High El Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
To perform design, land acquisition, construction of expansion of the Hilo Maintenance Facility, addition of office/training/meeting space due to being undersized for the current operations.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes:
Needed to continue current level ofservices.
A. Addresses public health/safety, -'If Yes: ❑
N/A
B. Service improvements, ✓all that apply:
El Access to M Quality of El Quantity of
E. Operational efficiency and leveraging
opportunities:
Results in net decrease in operating cost and improves services.
No opportunity, not adjacent to project to capitalize on cost saving.
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El✓if
N/A
F. Fosters inter -departmental collaboration
Yes: 0
DPW
Additional info:
12. LONG RANGE PLANS/
❑� Dept. Priority
Details: AI ows or the County to provide maintenance and administrative services in
East and South Hawai'I County
Comm. Value
Details: Ensures a re iab a eet as uses can a maintainedtimely when they ail in East and
South Howai'l County
COMMUNITY VALUES, check
least one and all that apply,
❑� General Plan
Details: Included in the transit portion of the General Plan
❑ Admin Priority
Details: Addressess implementing the recommendations of the Transit Master Plan
at
provide details:
0 CDP
Details: Included in the Pahoo and Kona CDPs
❑Multi Hazard
Details:
Details:
❑� Other Plans
Details: Included in the Multi -Modal Transit and Transportation Master Plan
❑ Mitigation Plan
Additional info:
13. CTY. MATCHING FUNDS REQ'D? -'If Yes: El
I DESCRIBE: The Mass Transit Agency will persue FTA funds and when successful, 20% local match will be required using GET
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
Promotes energy and resource conservation
0 Reduces hazard risk
ID Preserves/protects our natural/cultural env.
rED—Cost benefit analysis
El Promotes economic vitality
lal Strengthens and sustains our community
Additional info:
16. PROJECT READINESS, ✓all
JE Project currently underway
FZ] Previously Appropriated
El Staff available to manage project
171 External funds/resources ready to proceed
that apply:
El Identified operating budget needs
F21 Can realistically encumber funds
List phases already completed: None
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
1 FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Sol
50
$100
Land Acquisition
75
75
$150
Design/Survey
Construction
200
4,236
$4,436
TOTAL:
$125
$325
1 $4,236
1
$4,686
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
Cty G.O. Bond
325
4,236
$4,561
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe) GET
225
$125
TOTAL:
$125
$325
1 $4,236
$4,686
(This Page Intentionally Left Blank)
OFFICE OF HOUSING AND
COMMUNITY DEVELOPMENT
SUSAN KU NZ,
HOUSING ADMINISTRATOR
169
(This Page Intentionally Left Blank)
170
SUMMARY OF DEPARTMENT REQUESTS
SIX YEAR CAPITAL IMPROVEMENTS PROGRAM
Department: Office of Housing & Community Development
FISCAL YEAR 2024-2025
PRIORITY
PROJECT
2024-25 FY FUNDING
in thousands
FUNDING FORECAST BY FISCAL YEAR
in thousands)
TOTAL
ESTIMATED
PROJECT
COST
County
G.O. Bond
State
Federal
Private*
CBA,
Other-
Prior
Funds
Allotted
T Is
Request
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
Beyond 6
years
1
OHCD - Facilities Repairs/Maintenance and Renovation
1,500
778
1,500
1,500
1,500
1,500
1,500
1,500
9,778
2
OHCD - Haihai Affordable Housing Project
15,000
1,000
15,000
-
-
-
-
-
16,000
3
OHCD- Ainako Affordable Housing
16,000
1,000
16,000
16,000
-
-
-
-
33,000
4
OHCD- Alnaola Affordable Housing Project
20,000
1,000
20,000
-
-
-
-
-
21,000
5
OHCD - Ka'iminanl Affordable Housing Project - roads and WWTP
10,000
10,000
6
7
8
9
10
TOTAL
52,500
-
-
3,778
52,500
27,500
1,500
1,500
1,500
1,50o
-
89,778
Created By: Anne Bailey " Private: Foundation Grants
Date: 1/24/2024 '" Community Benefit Assessments: Fair Share, Park Dedication, Etc. Other: GET, Fuel Tax and other non -bond sources
N (This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Office of Housing & Community Development
2. SUBMITTER: Susan K. Kunz DATE: 1/2/2024
3. PROJECT NAME: OHCD - Facilities Repairs/Maintenance and Renovation
4. LOCATION (COUNCIL DISTRICT): Various
5. COUNCIL BENEFIT DISTRICT(S): Various
6. TMK/CDP PLANNING AREA: Various islandwide
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 1,500,000
8. PROJECT ELIGIBILITY, ✓ all
that apply:
❑ Land acquisition
Wnfrastructure improvement
o New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
I 0 High ❑ Med. ❑ Low
❑ Nonrecurring rehabilitation
I El Planning, feasibility, eng., or design study
I ❑ Information/communications tech.
10. PROJECT/PROGRAM
DESCRIPTION:
OHCD maintains several facilities throughout the island. Three of the facilities are more than 20 years old. The existing buildings are in need of constant renovations/repairs & maintenance. Repairs and
maintenance & renovations of the projects are medium to large scale. Repairs and maintenance are needed to ensure continued project viability. Some of the repairs we have scheduled includes
resurfacing roads, ADA compliance, and building interior unit renovations including energy efficiency fixtures and appliances and routine tree trimming.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., -ifYes: 0
Addressesonticipotedfutureneed.
A. Addresses public health/safety, -if Yes:
Reduces risk of a documented hazard.
B. Service improvements, ✓all that apply:
0 Access to 0 Quality of ❑Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, -ifYes:
Necessary repair/maintenance/replacement.
F. Fosters inter -departmental collaboration
-ifYes: ❑�
planning
Additional info:Reduce expenditures on operational budget to address aging facilities before it becomes a bigger problem. Eliminate temporary and piece meal fixes.
12. LONG RANGE PLANS/
E]Dept.Priority
Detolls:mointainsandextends the lifeofOHCDfacilities/projects
❑Comm. Value
Details:
COMMUNITY VALUES, check at
General Plan
Details: Section 9, Housing
❑� Admin Priority
Details. preservation of affordable housing and homeless facilities, and increasing units
least one and all that apply,
provide details:
❑CDP
Details:
❑Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info:Reduce expenditures on operational budget to address aging facilities before it becomes a bigger problem. Eliminate temporary and piece meal fixes.
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: 0
DESCRIBE: ADA accessibility as required (where applicable)
15. SUSTAI NABILITY FOCUS, ✓al I that apply:
Provide additional information as appropriate:
0 Promotes energy and resource conservation
❑ Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
❑ Cost benefit analysis
I R1 Promotes economic vitality
0 Strengthens and sustains our community
Additional info: Reduce expenditures on operational budget to address aging facilities before it becomes a bigger problem. Eliminate temporary and piece meal fixes.
16. PROJECT READINESS, ✓all
[�] Project currently underway
❑ PreviouslyAppropriated
❑ Staff available to manage project
❑ External funds/resources ready to proceed
that apply:
❑ Identified operating budget needs
Can realistically encumberfunds
List phases already completed: various physical needs assessments on OHCD projects
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
1 FY 26-27
1 FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
Land Acquisition
Design/Survey
350
$350
Construction
778
1,150
1,500
1,500
1,500
1,500
1,500
$9,428
TOTAL:
$7781
$1,500
1 $1,500
1 $1,500 1
$1,500 1
$1,500
1 $I'S_0_0F
$9,778
18. O & M COSTS (x $1000):
19. FUNDING SOURCE (x $3000):
Cty G.O. Bond
778
1,500
1,500
1,500
1,500
1,500
1,500
$9,778
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
TOTAL:
$7781
$1,500
$1,500
$1,500
$1,500
$1,500
$1,500
$9,778
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Office of Housing & Community Development
2. SUBMITTER: Susan K. Kunz DATE: 1/2/2024
3. PROJECT NAME: OHCD - Haihai Affordable Housing Project
4. LOCATION (COUNCIL DISTRICT): 3
5. COUNCIL BENEFIT DISTRICT(S): 1,2,3,4
6. TMK/CDP PLANNING AREA: (3)-2-4-051:111, 094, 107,108
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 15,000,000
ELIGIBILITY, ✓ all
ElLand acquisition
El Infrastructure improvement
❑ New bldg., structure, or addition
Ell❑�
9. PROJECT URGENCY/NEED, ✓one:
rPROJECT
t apply:
El Nonrecurring rehabilitation
El Planning, feasibility, eng., or design study
❑ Information/communications tech.
High ❑ Med. ❑ Low
10. PROJECT/PROGRAM
DESCRIPTION:
OHCD will complete the construction of the subdivision infrastructure road, water, electric, wastewater, and drainage improvements for a mixed single family, multifamily 150 unit affordable
housing subdivision on this 34.13 acre parcel located in Waiakea, South Hilo. These parcels have been Executive Ordered to the County via EO-4686 on November 15, 2022. The project will
prepare the parcel for an affordable housing subdivision to be completed by OHCD and affordable housing development partners. This includes any and all related costs.
11. PROJECT JUSTIFICATION & OUTCOME(5), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: ❑J
Addresses anticipated future need.
A. Addresses public health/safety, "ifYes: e
Community concerns exists around conditions.
B. Service improvements, Vail that apply:
0 Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities: subdivision for affordable housing
N/A
N/A
C. Repair/maintenance/replacement of
acility/infrastructure/building, ✓if Yes: ❑
N/A
F. Fosters inter -departmental collaboration
✓if Yes:
Planning
[Additional info:
12. LONG RANGE PLANS/
❑.r Dept. Priority
Details: Creating affordable housing opportunities is the Department's mission
❑Comm. Value
Details:
COMMUNITY VALUES, check
E General Plon
Details: Section 9, Housing
❑.r Admin Priority
Details: Development of affordable housing is this Administration's priority.
at least one and all that apply,
provide details:
E)CDP
Details:ldentify and facilitate use of suitable public lands; expand affordable housing
❑Multi Hazard
Details:
Details:
❑Other Plans
Details:
❑ Mitigation Plan
Additional info: OHCD has identified this parcels for affordable housing .
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE:
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
2 Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
I ❑ Cost benefit analysis
❑� Promotes economic vitality
R1 Strengthens and sustains our community
Additional info: Housed individuals and families reduces homelessness and allows for improved health and safety, while promoting economic improvements within a household, and strengthening our communities.
16. PROJECT READINESS, -'all
that apply:
� Project currently underway
y Y
Y
❑ Previously Appropriated
Staff g project
❑ Sta available to manage ro ect
❑External unds/resources read to proceed
f Y
❑ Identified operating budget needs
El Can realistically encumber funds
List phases already completed: the preliminary due dilligence, additional subdivision and planning
work In FY23-24 in progress.
Additional info:
17. EXPENDITURE PHASING (X $1000):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
500
$500
Land Acquisition
Design/Survey
500
1,000
$1,500
Construction
14,000
$14,000
TOTAL:1
$1,00011
$15,000
1$16,000
18. 0 & M COSTS (x $1000):
$0
19. FUNDING SOURCE (x $3000):
$0
Cty G.O. Bond
1,000
15,000
$16,000
State Revolving Fund
State CIP
Federal
Private (Grants)
CBA (Fair Share, Park Dedication, etc)
Other Cty Fund - (describe)
IL
TOTAL:
$1,000
H $15,000
1
$16,000
(This Page Intentionally Left Blank)
v
4
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Office of Housing & Community Development
2. SUBM17TER: Susan K. Kunz DATE: 1/2/2024
3. PROJECT NAME: OHCD -Ainako Affordable Housing
4. LOCATION (COUNCIL DISTRICT): 2
5. COUNCIL BENEFIT DISTRICT(S): 1,2,3,4,5,
6. TMK/CDP PLANNING AREA: (3)2-3-030:004
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 16,000,000
B. PROJECT ELIGIBILITY, ✓ all
that apply:
❑ Land acquisition
21 Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, ✓one:
[�] High ❑ Med. ❑ Low
❑ Nonrecurring rehabilitation
❑� Planning, feasibility, eng., or design study
❑ Information/communications tech.
10. PROJECT/PROGRAM
DESCRIPTION:
h FY 23-24 funds, OHCD is completing a phased planning and design work for an affordable housing and multi -family subdivision on this 60.59 acre parcel located in Waiakea, South Hilo to be
mpleted by OHCD and affordable housing development partners. This FY 24-25 will request funds to begin building the infrastructure and roads for the Phase 1 subdivision(about 30 acres) off
EianuenueAvenue. This includes any and all related costs.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 2
Addresses anticipated future need.
A. Addresses public health/safety, ✓if Yes:
ElCommunity
concerns exists around conditions.
B. Service improvements, ✓all that apply:
❑� Access to 0 Quality of ❑ Quantity of
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: El
NIA
NIA
F. Fosters inter -departmental collaboration
Yes: D
Planning
Additional info:
12. LONG RANGE PLANS/
❑✓ Dept. Priority
Details:Creating affordable housing opportunities is the Department's mission
❑Comm. Value
Details:
COMMUNITY VALUES, check
0 General Plan
Details:Section 9, Housing
RAdmin Priority
Details3dentify and facilitate use of suitable public lands; expand affordable housing
at least one and all that apply,
provide details:
❑� CDP
Details:ldentify and facilitate use of suitable public lands; expand affordable housing
MMultiHazard
Details:
Details:
❑Other Plans
Details:
I ❑ Mitigation Plan
Additional info:OHCD identified this parcel for affordable housing, and has completed a feasibility study indicating positive conditions for an affordable housing and multi -family development.
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
1 DESCRIBE:
14. LEGAL MANDATE? '"if Yes: 0
DESCRIBE: General Plan and all CDP.
15. SUSTAINABILITY FOCUS, Vail that apply:
Provide additional information as appropriate:
❑ Promotes energy and resource conservation
❑� Reduces hazard risk
❑ Preserves/protects our natural/cultural env.
Cost benefit analysis
I [I Promotes economic vitality
❑� Strengthens and sustains our community
Additional info: Housed individuals and families reduces homelessness and allows for improved health and safety, while promotin economic improvements within a household, and strengthening our communities.
16. PROJECT READINESS, ✓all
that apply:
1Z projectcurrentl underway
1 Y Y
❑ Previous) Appropriated
Yff
Sta available to manage project
9 1
❑ External unds/resources read to proceed
f Y
❑
Identified operating budget needs
❑�
Can realistically encumber funds
List phases already completedwarious due diligence EA reports, and subdivision planning scenarios. Final
subdivision planning beginning.
Additional info:
17. EXPENDITURE PHASING (X $3000):
Prior Funds Allotted
(not lapsed)
11 This Request
FY 24-25
FY 25-26
1 FY 26-27
1 FY 27-28
FY 28-29
FY 29-30
Beyon 6
Years
TOTAL:
Planning
Soo
$500
Land Acquisition
$0
Design/Survey
Soo
$500
Construction
16,000
16,000
$32,000
TOTAL:
$1, 000
$16,000
$16,0001
1
1
1 $33,000
18. O & M COSTS (x $1000):
$0
19. FUNDING SOURCE (x $3000):
Cty G.O. Bond
1,000
16,000
16,000
$0�
$33,000
State Revolving Fund
$0
State CIP
$0
Federal
$0
Private (Grants)
$0
CBA (Fair Share, Park Dedication, etc)
$0
Other Cty Fund - (describe)
11
$0
TOTAL:
$1,000
$16,000
$16,000
$33,000
(This Page Intentionally Left Blank)
County of Hawaii
PROJECT DATA/FINANCIAL IMPACT STATEMENT
Fiscal Year 2024 - 2025
1. DEPARTMENT AND DIVISION: Office of Housing & Community Development
2. SUBMITTER: Susan K. Kunz DATE: 1/2/2024
3. PROJECT NAME: OHCD- Ainaola Affordable Housing Project
4. LOCATION (COUNCIL DISTRICT): 2
5. COUNCIL BENEFIT DISTRICT(S): 1,2,3,4,5,
6. TMK/CDP PLANNING AREA: (3)2-4-005: 001 & 2-4-005: 012
7. TOTAL COUNTY FUNDS NEEDED THIS FY: 20,000,000
8. PROJECT ELIGIBILITY, ✓all
that apply:
❑Land acquisition
Infrastructure improvement
❑ New bldg., structure, or addition
9. PROJECT URGENCY/NEED, -one:
❑J High ❑ Med. ❑ Law
❑ Nonrecurring rehabilitation I
❑ Planning, feasibility, eng., or design study I
❑ Information/communications tech.
10, PROJECT/PROGRAM
DESCRIPTION:
In FY 23-24, OHCD is completing the design and planning for this affordable housing subdivision on this 71.26 acre parcel located in WaMea, South Hilo. The new CIP FY 24-25 request will complete the
road and infrastructure (electrical, water, sewer) for an affordable housing subdivision to be built by OHCD and affordable housing development partners. FY 24-25 will request funds to build the
infrastructure and roads for this subdivision. This includes any and all related costs.
11. PROJECT JUSTIFICATION & OUTCOME(S), select and/or answer all that apply:
D. New facility/infr./bldg., ✓if Yes: 0
Addresses anticipatedfuture need.
A. Addresses public health/safety, ✓if Yes: ❑
NIA
B. Service improvements, ✓all that apply:
2 Access to R1 Quality of ❑ Quantity o
E. Operational efficiency and leveraging
opportunities:
N/A
N/A
C. Repair/maintenance/replacement of
facility/infrastructure/building, ✓if Yes: ❑
N/A
F. Fosters inter -departmental collaboration
✓if Yes:
planning
Additional info: OHCD has complete conceptual planning and due diligence studies and is in the process of hiring design and planning consultants for the road infrastructure plan.
12. LONG RANGE PLANS/
❑' Dept. Priority
Details:Creating affordable housing opportunities is the Department's mission
El Comm. Value
Details:
COMMUNITY VALUES, check
❑J General Plan
Details:Section 9, Housing
❑J Admin Priority
Details: Development of affordable housing is this Administration's priority.
at least one and all that apply,
provide details:
E)CDP
Detalls:ldentify ondfacilitate use of suitable public lands; expand affordable housing
❑Multi Hazard
Details:
I Details:
El Other Plans
Details:
❑ Mitigation Plan
Additional info: OHCD identified this parcel for affordable housing in the Hilo region.
13. CTY. MATCHING FUNDS REQ'D? ✓if Yes: ❑
DESCRIBE:
14. LEGAL MANDATE? ✓if Yes: ❑
DESCRIBE: General Plan and All CDP
J
❑ Promotes energy and resource conservation Reduces hazard risk ❑ Preserves/protects our natural/cultural env.
15. SUSTAINABILITY FOCUS, ✓all that apply:
Provide additional information as appropriate:
❑ Cost benefit analysis
p Promotes economic vitality
ID Strengthens and sustains our community
Additional info:Housed individuals and families reduces homelessness and allows for improved health and safety, while promoting economic improvements within a household, and strengthening our communities.
16. PROJECT READINESS, -'all
0 Project currently underway
❑ Previously Appropriated
E] Staff available to manage project I ❑ External funds/resources ready to proceed
that apply:
Identified o eratin budget needs
❑operating 9
J can realistically encumber funds
❑ Y
List hoses already completed. due dilli ence reports
P Y P 9 P
Additional info: Due diligence reports have been completed; selection of contractor for planning and design underway.
17. EXPENDITURE PHASING (X $lODO):
Prior Funds Allotted
(not lapsed)
This Request
FY 24-25
FY 25-26
FY 26-27
FY 27-28
FY 28-29
FY 29-30
Beyond 6
Years
TOTAL:
Planning
S00
$500
Land Acquisition
$0
Design/Survey
500
$500
Construction
20,000
$20,000
TOTAL:
$1,000
$20,000
$21,OD0
18. 0 & M COSTS (x $1000):
19. FUNDING SOURCE (x $1000):
$0
$0
Cty G.O. Bond
1,000
20,000
$21,000
State Revolving Fund
$0
State CIP
$0
Federal
$0
Private (Grants)
$0
CBA (Fair Share, Park Dedication, etc)
$0
Other Cty Fund - (describe)
$0
TOTAL:
$17000
$20,0001
1
$21,000
(This Page Intentionally Left Blank)