HomeMy WebLinkAboutRES 250 Draft 01 2000-2002 COUliTTY OF I~I~~VI~ ~~~E Off' ~I~Wr~I`I
1~S®LUTION 10T0. p~~
RESOLUTION AUTHORIZING THE MAYOR TO ENTER INTO A PROJECT
AGREEMENT WITH STATE OF HAWAII AND FEDERAL GOVERNMENT
AGENCIES FOR FEDERAL AID SPOT IMPROVEMENTS ON KEANAKOLU
ROAD FROM ITS INTERSECTION WITH THE JOHN A. BURNS WAY (MAUNA
KEA SUMMIT ROAD) TO THE NORTHERN BOUNDARY OF THE MAULUA
TRACT OF THE HAKALAU FOREST NATIONAL WILDLIFE REFUGE (MILE 16)
TMK: 3~a Div 3-8-01.
WHEREAS, Keanakolu Road is the primary and most direct access to the
Hakalau Forest National Wildlife Refuge (HAFO) located on the eastern flank of Mauna
Kea; and
WHEREAS, Keanakolu Road lies upon lands under the jurisdiction of the
Department of Hawaiian Home Lands and the State of Hawaii Department of Land and
Natural Resources; and
WI-IEREAS, The County of Hawaii Office of the Corporation Counsel has
reviewed available history regarding Keanakolu Road, and has opined that Keanakolu
Road was opened, laid out and constructed by the Federal and/or state governments, and
should be considered a County Highway pursuant to Hawaii Revised Statutes (HRS)
Section 264-1; and
WHEREAS, Keanakolu Road is a one-lane 4-wheel drive access with no
engineered components and includes areas of historical cobblestone surfacing; and
WHEREAS, The Central Lands Highway Division (CFLHD) of the Federal
Highway Administration (FHWA), in cooperation with the U.S. Fish and Wildlife
Service (FWS), is proposing to make spot improvements along the Keanakolu Road for
safety purposes and to reduce maintenance costs, at no cost to the County of Hawaii,
with funding through the Public Lands Highway Discretionary (PHLD) program; and
WHEREAS, the spot improvements proposed will occur in an approximately
16-mile long area beginning at the Keanakolu Road intersection with John A. Burns Way
(Mauna Kea Summit Road) and extending to the northern boundary of the Maulua tract
of the HAFO, and will include concrete fords across drainage ravines; roadway surfacing
to improve traction on several steep grades; minor roadway widening at the top of several
vertical curves; and replacement of two existing road closure gates with cattle guards;
and
WHEREAS, the CFLHD and FHWA desire to enter into a Project Agreement
with the County of Hawaii for the aforementioned spot improvements, in the form
attached hereto and incorporated by reference as Exhibit "A"; and
WHEREAS, the County would have no obligation under the Project Agreement to
participate in the spot improvements except to assist with coordination among local
agencies as needed, and to maintain the road after completion of construction; and
WHEREAS, Hawaii County Charter Section 13-21 requires County agencies, in
the performance of their functions, to cooperate with United States government agencies
having similar functions, and the County of Hawaii Director of Public Works
.recommends approval of the subject Project Agreement; and
WHEREAS, pursuant to HRS Section 46-7, the County Council may consent to
agreements with the federal government respecting action to be taken pursuant to the
County powers and fuiTaish, expend, ~~nd receive any funds or other assistance in
connection with projects to be undertaken pursuant to the County's powers;
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE
COUNTY OF HAWAII, in accordance with HRS Section 46-7, that the Mayor of the
County of Hawaii is authorized to execute, on behalf of the County, the Project
Agreement in substantially the form attached hereto and incorporated by reference herein
as Exhibit "A" to enable the County to receive federal assistance in making spot
improvements to Keanakolu Road as provided in said Project Agreement.
Dated: Hi7.~ , Hawaii, November 8, 2002 .
INTRODUCED BY:
i
c~ t. , ;
COUN IL MEM R, UNT OF HAW
s:lreso\keanakolu road reso\9-02\IMTfc.doc
COUNTY COUNCIL: ROLL CALL VOTE
County of Hawaii
]Hilo, Hawaii AYES NOES ABS EX
ARAKAKI X
I hereby certify that the foregoing RESOLUTION was by the CHUNG X
vote indicated to the right hereof adopted by the COUNCII. of ELARIONOFF X
the County ofliawai`i on November 8 , 2002 7ACOBSON X
LEITHEAD-TODD X
ATTEST:
PISICCHIO
SAFARIK X
TYLER X
YAGONG X
9 0 0 0
Reference C-767/PW&IRC-61
COUNTY CLERK CHAIRMAN ~z PRESII~ING OFFICER RESOLUTION NO.
~X~iI~I~' ~'A,'
Ply®J~CT ~G~1~E1®T~'
Hakalau Forest National Wildlife Refuge
HI PLH HAFO 10(1)
Spot Improvements on Keanakolu Road
July 2002
This is an agreement among the US. Fish and Wildlife Pacifrc Region, Hakalau Forest National
T~ildlife .Refuge, the County of Hawaii, and Central Federal Lands Highway Division, Federal
Highway Administration describing speck project requirements to be fulfilled and duties to be
performed by all parties to produce or supply the services as described below.
Richard Wass, Refuge Manager Date
Hakalau Forest National Wildlife Refuge
Nathan Caldwell, Regional Coordinator Date
Region 1 Refuge Road Program Coordinator
Harry Kim Date
Mayor, County of Hawaii
L
David H. Gedeon Date
Project Manager, FHWA -CFLHD
~ O~
Jaan W. Keeley Date
Dire for of Project Delivery, AIWA CFLHD
RECOMMEND APPROVAL:
UQ~.~ < w . ocu.
DENNIS K. W. LEE, P.E.
Director, Department of Public Works
County of Hawaii
APPROVED AS TO FORM AND
LEGALITY:
Deputy Corporation Counsel
County of Hawaii
Date:
INTRODUCTION
The Central Federal Lands Highway Division (CFLHD) of the Federal Highway Administration
(FHWA), in cooperation with the U.S. Fish & Wildlife Service (FWS), the Hawaii Department
of Transportation (HDOT), and Hawaii County, is proposing to make spot improvements along
the Keanakolu Road for safety purposes and to reduce maintenance costs. Funding is provided
through the Public Lands Highway Discretionary (PLHD) program.
PROJECT LOCATION
Hakalau Forest National Wildlife Refuge (HAFO) is located on the eastern flank of Mauna Kea
in the County of Hawaii. Keanakolu Road is the primary and most direct access to the Refuge
and is also used by local ranching operations and for public recreation. This project begins at the
Keanakolu Road intersection with John A. Burns Way (Mauna Kea summit road) and extends to
the northern boundary of the Maulua tract of the HAFO National Wildlife Refuge, a length of
approximately 16-miles. The existing road is a one-lane primitive 4-wheel drive access, with no
engineered components. A cobblestone surface is visible at various locations. Although the road
is gated as it passes through ranching tracks, the gates are not locked to preclude public access.
Keanakolu Road lies on lands under the jurisdiction of the Department of Hawaiian Homelands
and the Department of Land and Natural Resources.
SCOPE OF VVORI~
The proposed scope of work was developed to address the most pressing safety and maintenance
needs of the Keanakolu Road without resulting in significant environmental impacts. Because of
the historic nature of the cobblestone, a section 4(fj evaluation is required. CFLHD anticipates
preparing a categorical exclusion for this project. Four types of improvements are proposed:
• Concrete fords across several drainage ravines;
• Roadway surfacing to improve traction on several steep grades;
• Minor roadway widening at the top of several vertical curves;
• Replace two existing road closure gates with cattle guards.
PROJECT FUNDING
The FWS, in cooperation with the HDOT, submitted a project proposal for PLH funding in
federal fiscal yeax (FY) 2000. Congress approved a total of $958,000 for the proposed project.
Under FHWA policy, funds authorized under the PLH program must be obligated in the same
fiscal year in which they are appropriated, however exceptions to this policy are occasionally
granted. For the Keanakolu Road project, CFLHD has been able to have these funds restored for
the past two fiscal years.
-2-
ROLES AND RESPONSIBILITIES
PLHD Application: ?FWS ?FHWA ? County ? HDOT
Allocation of funds: ?FWS ?FHWA ? C~aunty ? HDOT
Scope of Work: ?FWS ?FHWA ? County
Environmental Compliance: ?FWS ?FHWA ? County
Design/Engineering: ?FWS ?FHWA ? County
Contract Administration: ?FWS ?FHWA ? County
Right of Entry: ?FWS ?FHWA ? County
Construction Engineering: ?FWS ?FHWA ? County
Maintenance: ?FWS ?FHWA ? Cs~unty
Fish and Wildlife Service will be responsible for the following:
1. Review and sign Project Agreement.
2. As desired, provide overall direction regarding FWS policy and concur with the final
plans and specifications.
3. As desired, review plans and specifications at each phase of the design and provide
project development support.
4. As desired, attend field reviews.
5. If requested, assist with any necessary coordination with local ncies.
6. If necessary, provide a Special Use permit for any work within National Wildlife
Refuge.
7. Enter into a formal partnering work session and agreement with all parties involved in the
construction contract (CFLHD, contractor, possibly Hawaii County).
8. Designate a representative as the primary point of contact.
9. As desired, attend final inspection with the CFLHD upon completion of construction.
10. If proposed, provide design of interpretive panels or informational signs.
Federal Highway Administration will be responsible for the following:
1. Develop and sign Project Agreement.
2. Manage project development schedule and preliminary engineering costs.
3. Provide environmental compliance; a categorical exclusion is anticipated.
4. Obtain any necessary permits.
5. Prepare plans, specifications, and estimates (PS&E) for proposead improvements based on
the program amount available.
-3-
6. Develop contract documents for project advertisement.
7. Advertise and award contract. Bids will not be solicited by CFLHD until the FWS and
Hawaii County have concurred with the plans and specifications.
8. Provide a Project Engineer and staff to administer the construction contract and inspect
the work. The construction will be governed by the Standard Specifrcations for
Construction of Roads and Bridges on Federal Highway Projects, FP-96 (or latest
edition). Construction contract administration will be in accordance with the FLH
Construction Manual. The Project Engineer is CFLHD's designated contact for the FWS
during the construction phase.
9. Determine the need for any proposed changes to contract documents, evaluation of
change impacts, coordination of technical reviews as needed, and ensuring that the
construction meets the requirements intended in the PS&E.
County of Ilawaii will be respoaasible for tl?e following:
1. Review and sign Project Agreement.
2. As desired, provide overall direction regarding County policy and concur with the final
plans and specifications.
3. As desired, review plans and specifications at each phase of the design and provide
project development support.
4. As desired, attend field reviews.
5. If requested, assist with any necessary coordination with local agencies.
6. If desired, enter into a formal partnering work session and agreement with all parties
involved in the construction contract (FWS, CFLHD, contractor).
8. Designate a representative as the primary point of contact.
9. As desired, attend final inspection with the CFLHD upon completion of construction.
MAINTENANCE IZESP®NSI~ILITY
After construction of the project, the County will operate and maintain, or cause to be
maintained, the road in accordance with 23 U.S.C. 116. Maintenance is defined as the
preservation of the entire road including the surface, shoulders, the roadside, environmental
features, structures, such traffic control devices as are reasonably necessary for its safe and
efficient use, and environmental protection and erosion control measures. During construction,
the contractor will maintain traffic over the project as specified in the construction contract
documents. The project will be accepted by the County of Hawaii for operation and maintenance
when the contracting officer has accepted all construction work. Any environmental
commitments noted in the construction contract will be maintained or monitored by the County
after construction. The County shall not install, or permit to be installed, any signs, signals, or
markings not in conformance with the MUTCD after construction is completed.
-4-
PROJECT TEAM MEMBERS
Fish and Wildlife Service:
Richard Wass Refuge Manager, Hakalau Forest National Wildlife Refuge
(808) 933-691 s; FAX: (808) 933-6917
Primary FWS point of contact
Mr. Jerry Leinecke Project Leader, Refuges Division, Honolulu FWS
(808) s41-1201; (808> s41-1216
Nathan Caldwell Regional Refuge Road Coordinator, Region 1
(s03) s41-202s; FAX: (s03) 231-2364
Regional contact
Federal 1<Iighway Administration:
Dave Gedeon Project Manager
(303) 716-2131; FAX: (303) 969-6936
Provide general leadership, overall project coordination, and serve
as CFLHD's primary contact. The CFLHD PM is responsible for
the overall coordination and scheduling of FI-1WA work, managing
the FHWA budget, and addressing any changes in scope.
Ed DeCleva Environmental Protection Specialist
(303) 716-2190; FAX: (303) 969-5903
Coordination with regulatory agencies and preparation of the
environmental compliance document.
Mike McCann Design Team Leader (DTL)
(303) 716-2120; FAX: (303) 969-s903
Provide direction and technical assistance to CFLHD's design
team and responsibility for preparing the PS&E documents.
Kevin Black Construction Operations Engineer
(303) 716-2153; FAX: (303) 969-5516
Constructibility reviews, construction management, evaluation of
change impacts, and coordination of technical reviews as needed of
proposed post-design changes to ensure that the request meets the
intentions of the PS&E.
-5-
PROJECT BUDGET
Funding source: TEA-21 Public Lands Highway Discretionary Program, Fiscal Year 2000.
Activity Description FY 00/O1 FY 02 FY 03 'Total
Consultant Services (A/E) $85,000 $ 0 $10,000 $95,000
Project Development (PE) $62,000 $20,000 $ 35,000 $117,000
Construction Engineer $ 0 $ 0 $679,000 $679,000
Construction Estimate $ 0 $ 0 $67,000 $67,000
Total $147,000 $20,000 $791,000 $958,000
Total Project Cost Estimate: $ 958,000
Available PLH-D Funding: $ 958,000
-6-
a~
a~
o
ass' °
~ o
~ ~ ~
~a •a
U i
O ~ ~
~ ~
C 'w 4 1s +v
~ ~ ~ Uv ~ ~ ti~~hti~~ti
~-s
O _ N ry N N M M M M M M
~ ~ O O O O O p 0 0 0 0 0 0 O D
p~„sd N N O N ry N fV N s
N~s N a
N~ N O N
~ ~ ~ _
~S""e ~ d\ O O O O O N O O O O O O O M
y~ ~ N N o N N O N N N N N N N O
y ~ y C ~ ~ c~ N U ~ cad ~ ~ ~ ~~c N
~ ~
~ 3
~ ~
ao° v
~ ~ ~~3 wx ~~,33 ww~~~ o
o w 3w~ ~ ~w w ~~w ~ ~ ~ ~
V ~ ~ ~ w O ce ~ N ~ ~ ~ of cd ~ c~a v p ~ Cd
.O ~ vVi ~ y N U ~ ~ U N N U U ~ ~
~ ~AA~ ~HGa~~wu ~~v~rs ~
~ ~
~ ~ .g
s ~ ~ ~ aoo ~
~ ~ ~ ~ ~ ~ Q ~ o ~ ~
~ y ~ 0~
~ ~ ~ ~ ~ ~ q W ~ ~ ~
CJ O~ U ~ ~Q.~o23 ~ ~ avi ~ ~ ~
o f rye o c o~ i ~ o~ :°A'~°~ ~
~o--+ GIB °v v > 'y O 'a ~ ~ ~ c° > ~ ~ ti
a~ ~ 4R,' 'ts a~ o ~ o ~ o a~ o ar ~ '0 3 0
~ ~ o ~ W a.. U~.~~v~WA.w¢¢U
CONTRACTING
This project may be offered to the Small Business Administration in support of the 8(a)
business development plan of an approved contractor. CFLHD as the contracting office will
review the available contracting options, and with the concurrence of the FWS, utilize the
most advantageous method.
Competitively bid contracts will normally offer a "partnering" opportunity to the contractor
with all parties involved in the contract. In addition, the contractor would be encouraged to
develop, prepare, and submit value engineering change proposals (VECPs) and share in any
contract savings realized from accepted VECPs.
CONFLICT RESOLUTION PLAN
By signing this project agreement, the signatories formally agree to partner the development
phase of this project. This purpose of the design partnering process is to help identify problems
and resolve complex problems sooner and more efficiently. The FWS and FHWA agree that, in
the event of a dispute, both parties shall use their best efforts to resolve the dispute in an
informal fashion through consultation and communication.
PRODUCT VVARRANT~'
Project participants will complete all work outlined in this agreement within the established
schedule and budget, as updated and amended.
PROJECT AGREEMENT AMENDMENT PROCESS
The project agreement maybe amended by any party to the agreement, subject to the
concurrence by all original signatories. Circumstances that may result in an amendment to this
agreement includc major changes in scope, schedule, products, budgets, and key team members.
Amendments will be in the form of revisions to the original project agreement or changes
documented through standard correspondence or electronic mail. Amendments will be
distributed to all signatories of the original agreement.
-8-