HomeMy WebLinkAboutCOM 0307.003 2004-2006 COUNTY OF HAWAII
SOLID WASTE MANAGEMENT FACILITY
PROCUREMENT
TIMELINE AND TASKS
HAWKINS DELAFIELD & WOOD LLP
RICK SAPIR
JUNE 29, 2005
Comm. No. 31 q. 3
Ref. To: pJO EMC.
Ref. Uate ~N 2 ~ 2~~~ .
DELAFIELD & WOODua
FIRST PERIOD TECHNOLOGY AND APPROACH ASSESSMENT
SECOND PERIOD PROCUREMENT DOCUMENT PREPARATION
THIRD PERIOD COMPANY PROPOSAL PREPARATION
FOURTH PERIOD PROPOSAL CLARIFICATION AND EVALUATION
FIFTH PERIOD NEGOTIATIONS
First Second Third Fourth Fifth
Period Period Period Period Period
Pmjed COnnaCl
Starts ExeclIut ion
Techrw logy and Pmcurement Document Company Proposal Proposal Clarificet ion and Negotiazion Period 1
• Approach Assessment Preparation Period Preparation Period Evaluat ion Perbd
Perbd
3 -6 Months 2 -3 Months 3 Months 3 Months
f ~ ~ ~
. _ _ _ ..12 -15 Months _ _
Identify: • Prepare RFQ (if applicable) • Meetings • Review Proposals • Prepare Draft Contract
• Objectives • Receive SOQ's with Proposer .prepare Clarification and Appendices
• Technologies and • Evaluate anJ determine Teams Questions • Negotiate Final Contract
Approaches Qualified Respondents • Company's • Meeting with Companies and Appendices
• Site(s) Preparation of • Evaluate Proposals • Obtain Cowty Council
• Tran saaion STruct ure 'prepare RF'P (with contraa proposals • prepare Evaluazion Approval
•Pmcurement Structure princryles or drag contract) Report • Prepare and Negotiate
• Feasibility Issues 'Distribute Draft RFP • Assist Selection Guaranty Agreement
• Receive Comments Committee with
• Issue Final RF'P
Determination
2 DELAFIELD&WOODLLP
FIRST PERIOD -TECHNOLOGY AND APPROACH ASSESSMENT
¦ Identify objectives
¦ Identify feasible technologies and approaches
¦ Identify non-feasible technologies and approaches
¦ Identify preferred technologies and non-preferred technologies
¦ Identify site(s)
¦ Identify key elements of transaction structure, for example
¦ ownership
¦ Financing (public or private)
¦ contract delivery approach (e.g., design/build/operate)
¦ operating term
¦ allocation of significant risks
¦ Identify procurement structure (e.g., RFQ vs. RFP) -legal issues
¦ Review feasibility issues (e.g., permitting, proven technology, cost,
other)
3 DELAFIELD&WOOD~~P
SECOND PERIOD -PROCUREMENT DOCUMENT PREPARATION PERIOD
¦ Preparation of Request for Qualifications
¦ Prepare RFQ (as applicable)
¦ Identify technical and financial qualification requirements
¦ Identify key business/risk issues
¦ Evaluation and Determination of Qualified Respondents
¦ Preparation of Request for Proposals
¦ Description of required scope of services
¦ Provide background data and historical tonnages
¦ Information regarding the site
¦ Identification of acceptable and/or unacceptable technologies or
approaches
¦ Identification of minimum design requirements and performance
guarantees
¦ Description of evaluation criteria and weighting
¦ Preparation of applicable proposal forms
¦ Preparation of appendices (e.g., insurance requirements, communication
plan, key personnel, etc.)
¦ Refine risk allocation
¦ Preparation of comprehensive contract principles or draft contract (if
feasible)
¦ Distribution of draft request for proposals
¦ Receive comments from and attend meetings with qualified proposers
¦ Distribution of final request for proposals
Q DELAFIELD & WOOD LLP
THIRD PERIOD -COMPANY PROPOSAL PREPARATION PERIOD
¦ Meetings with individual proposer teams
¦ Company's preparation of proposals
G~~C~Cl1~Gf/yG6
$ DELAFIELD & WOOD ~~P
FOURTH PERIOD -PROPOSAL CLARIFICATION AND
EVALUATION PERIOD
¦ Review proposals for responsiveness and comprehensiveness
¦ Preparation of clarification questions regarding proposals (1 or 2
rounds)
¦ Meetings with individual teams to discuss clarification questions and
preliminary responses (allow companies to present proposals)
¦ Review of written responses to clarification questions
¦ Evaluate proposals based on RFP evaluation criteria (business, technical
approach, technical experience and cost)
¦ Preparation of evaluation report
¦ Assist Selection Committee with determination of most advantageous
proposer
c~Z~~u~tiJ?,~l
DELAFIELDSWOOD~~p
FIFTH PERIOD -NEGOTIATION PERIOD
¦ Preparation of draft contract and appendices if not previously
distributed in request for proposals (additional period of time will be
necessary if contract cannot be prepared prior to this time)
¦ Negotiation and preparation of final contract and appendices
¦ Obtain required County approval
DELAFIELD&WOOD~~P