June 16, 2006 ~ - - -
= r.., `i
m
-c
t~
Stacy Higa, Chairman, and
Members of the Hawaii County Council
-_a
Hawaii County Council
25 Aupuni Street
Hilo, HI 96720
Subject: Solid Waste Reduction Project: RFP Monthly Update, June 16, 2006
Enclosed, please find the monthly update of the Solid Waste Reduction RFP, as requested by the
Environmental Management Committee.
Should you have any questions or concerns, please call Barbara Bell or me. Thank you very
much.
1~4i
William T caba
Director
cc: Mayor Harry Kim
Barbara Bell
Enclosure
Comm. No. J 2
Ref. 70:
Re#• dote-
J
ii i~~(
County of Hawaii
Waste Reduction Facility Design-Build-Operate
Monthly Update -June 16, 2006
¦ Solicitation Documents
R.W. Beck furnished copies of the most recent Volume I of the Stage 2 RFP to
County staff for review and is in the process of receiving and incorporating
County comments. Volume III (Technical Appendices to the Service Contract) is
currently being reviewed by the consultants and will subsequently be given to
County staff for review. Once drafts of the three volumes (including the draft
Service Contract) aze completed by the team and approved by the County, they
will be sent to the short-listed Proposers for comment. Any meaningful
comments from the Proposers that are approved by the team will be incorporated
and the Final Stage 2 RFP will then be issued.
R.W. Beck has also contacted staff at HELCO to begin coordination of work and
to ensure that interconnection can be made with the Waste Reduction Facility.
¦ Contract Preparation
Hawkins Delafield & Wood LLP continues to prepare a draft Service Contract
(Volume II of the Stage 2 RFP).
¦ Environmental Impact Statement /EISPN
The second EISPN Public Meeting was held at 6 PM on May 17, 2006 in Hilo
and the public comment period (initiated on May 8th) ended on June 7, 2006. The
three resulting comment letters will be answered in early July.
Presentations and Workshops
The team anticipates a meeting with the Council Environmental Committee
regarding the Stage 2 RFP on August 22, 2006.
• Project Schedule
Based on the adjustment of intermediate milestones, the overall schedule has
shifted slightly. The anticipated contract execution date has moved to March
2007.
¦ Action Items and Responsibilities
o R.W. Beck and Hawkins Delafield & Wood LLP to complete the 1st draft
of the Stage 2 RFP for review by Proposers.
o Hawkins Delafield & Wood LLP to complete the 1st draft of the Service
Contract for review by Proposers.
1
Y
¦ Upcoming Milestones /Dates
o August 22 -Stage 2 RFP Meeting with Council Environmental
Committee.
2