Change of Zone Ordinance No. 94-78 (REZ 767)
Special Permit No. 863 ~ W
Use Permit No. 74
Applicant: Big Island County Club and Estates
Subject: Annual Progress Report
Tax Map Key' 7-1-5: Various
This is to acknowledge receipt of your annual progress report for the above-referenced project.
Thank you for complying with the annual report requirement.
We shall forward your report to the Planning Commission and County Council for their review.
As a reminder, your next annual monitoring report will be due on or before July 13, 2000.
Should you have any questions regarding this matter, please contact Susan Gagorik or Phyllis
Fujimoto at 961-8288.
Sincerely,
V Jv~
VIRG IA G ,L STEIN
Planning Direct
SG:gp
r:\wpwin60\susanVarbi c01 skg
cc: C~'ounty Planning Commission
?County Council Z,y~Q. Qo9
Comm. NoF yy rG..
131e No. ZNG/KN
Ref. To:
Ref. Date SEP 2 1 1999
SidneyFuke, Planning Consultant
100 Pauahi Street, Suite 212 • Hilo, Hawaii 96720 •Planning•Variance•ZOning
Telephone: (808) 969-1522 • Faz: (808) 969-7996 • Subdivision • Land Use Permits
• Environmental Reports
August 25, 1999
.
Ms. Virginia Goldstein, Director
Planning Department
COUNTY OF HAWAII ;
25 Aupuni Street
Hilo, HI 96720
Dear Ms. Goldstein:
Subject: Annual Progress Report (1999) -Big Island Country
Club and Estate, Tax Map Key: 7-1-5: Various
Based on your letter of April 15, 1997, the next annual report covering Ordinance
No. 94-78, Special Permit No. 863, and Use Permit No. 74 relating to the subject project was
due on or before July 13, 1998. The last report was submitted on August 18, 1999, and it
was assumed that that was the date. I apologize for this oversight.
Please also note that the annual report requirement for the proposed lodge (SPP 95-
24) is also due on September 27. Given the relatedness of this project and the proximate due
dates, we respectfully request your acceptance of this report to satisfy the annual report
requirement for all of the permits covering this project.
Use Permit No. 74
This permit covered the construction of a 27-hole golf course. With your acceptance
of the developer's community benefits program and the understanding that the channelized
intersection and community park would be in place by the end of 1998, a "sob" opening of
the first 18-holes commenced during the latter part of December 1997.
As the required improvements were not able to be met, the developer requested a
time extension as well as certain modifications to the community benefits program. This was
approved by the Planning Commission at its meeting of April 1, 1999. The amended
conditions require:
a. The community recreation and volunteer fire station facilities be completed by
December 1, 2000; and
b. The proposed 10+_ acre community park be subdivided and conveyed to the
Community Association within six months from the effective date of the
amendment to Ordinance No. 94-78. The effective date of this ordinance is q,
~.u'i~f",. ~-,y.
Ms. Virginia Goldstein
August 25, 1999
Page 2
June 23, 1999, and as a result, the park must be conveyed before December
23, 1999.
According to information provided me by the applicant's president, Ms. Noriko Saiga,
the delay in fulfilling these commitments is attributable to the time needed to secure the
required financing. At this stage, the prospective lender has required an appraisal of the
property, and said appraisal is nearing completion. Ms. Saiga believes that the financing
component should be finalized within the next 3 months. Under that basis, construction of
certain activities can begin in February or Mazch of the yeaz 2000.
In the meantime, a surveyor has been retained to proceed with the prepazation of the
proposed consolidation/resubdivisionrnaps to allow for the subdivision of the 10+_ acre
parcel. It is hoped that this application will be filed in September and that final approval can
occur before the end of the year. That would make it possible for the applicant to fulfill the
pazk conveyance requirement.
Special Permit No. 863
This permit relates to the expanded use of the golf clubhouse and the community
park.
A time extension for completion of the pazk and clubhouse was approved by the Planning
Commission at its meeting of April 1, 1999. Said extension required completion of the
community park by December 1, 2000.
Over the past year, work on the clubhouse and the community park has been
suspended due to the lack of funds. Should the pending loan be approved, the applicant
believes that this requirement can be fulfilled.
Ordinance No. 94 78
This ordinance allowed the creation of up to 100 1-acre lots. There were also
conditions that required provision of the community pazk, similar to the terms of the Use
Permit. As such, Ordinance No. 99 79, which became effective on June 23, 1999, essentially
granted a similar time extension for conveyance of the community pazk and completion of the
park improvements.
Relative to the subdivision itself, tentative subdivision approval has already been
granted. It was hoped that final approval for the first phase covering approximately 601ots
would have been secured eazly part of this yeaz. However, because of financing, the project
Ms. Virginia Goldstein, Director
August 25, 1999
Page 3
was put on hold. Like the balance ofthe project, this aspect will get re-started upon receipt
of the pending loan; and construction should begin in the first quarter of 2000.
Special Permit No. 95-24
Although the Commission's decision was appealed, the appellants and the applicant
reached an agreement on June 25, 1998. This technically cleared the way for construction of
the proposed lodge.
Like the balance of the project, however, this project, too, was affected by the
applicant's financial circumstances. The applicant still has every intention of pursuing this
project and would like to see it completed within the next two years.
We trust that the foregoing adequately addresses the annual report requirement. If
not or if there are further questions on this matter, please feel free to contact me. The next
annual report will be submitted on or before July 13, 2000. Thank you very much.