HomeMy WebLinkAboutCOM 0460.001 1992-1994 OF
Stephen K. Yamashiro -tarry A. Takahashi
Mayor Director
OF
A 4w J Li
*(4,74"1W a fu afi,
DEPARTMENT Of FINANCE
25 Aupuni Street,Room 118 Hilo,Hawaii 96720-4252
(808)961-8231 ® Fax(808)961-8248
July 16, 1993
The Honorable Spencer K. Schutte, Chairman
and Councilmembers
Hawaii County Council
25 Aupuni Street
Hilo, Hawaii 96720
Dear Chairman Schutte and Councilmembers :
RE: Amendment to Bill 99
Alenaio Stream Flood Control - $320, 000
Attached please find a proposed Amendment to Bill 99 which
will establish an appropriation for the above-mentioned
project . Condemnation costs for the involved lands have
been higher than expected.
The condemnation is under way and the Corp of Engineers
would like to commence with the bid process upon
acquisition of all involved lands. We hope to have the
project and funding secured before the federal -fiscal year
is concluded.
We are requesting that Bill 99, scheduled for first
reading by the Council on July 28, 1993, be the vehicle
for this appropriation. Hopefully, Bill 99, Draft 2, will
be enacted no later than August 11, 1993 .
Sincerely,
Harry Takahashi
Finance Director
APPROVED BY:
S en K. mashiro
yor Comm No.
a t tmt File No. p
a
cc: Chief Eng e e in r -L Tolk µ w
Ref. Dam J U L 1 9 1993
, IN
1
AL
UUUNr.rLx.Lr 0 F HAW, All
.y ATnt'. lt...'.•
Y.
BILL NO. 99
(DRAFT 2)
ORDINANCE NO.
AN ORDINANCE AMENDING ORDINANCE N0. 93-50 RELATING TO PUBLIC
IMPROVEMENTS AND FINANCING THEREOF FOR THE FISCAL YEAR JULY 1, 1993
TO JUNE 3 0, 19 9 4 .
BE IT ORDAINED BY THE COUNCIL OF THE COUNTY OF HAWAII :
SECTION 1 , ordinance No. 93-50, Relating to Public Improvements
and Financing Thereof For the Fiscal Year July 1, 1993 to June 30,
1994, is hereby amended by adding the following projects:
FIRE DEPARTMENT
FireP Maintenance Shop Extension - Waiakea $ 167,000
Fire Headquarters and Communications Building 11420,000
POLICE DEPARTMENT
Public Safety Building Phase III 500,000
PUBLIC WORKS DEPARTMENT
Alenaio Stream Flood Control 320,000
SECTION 2. Funds for the aforementioned projects shall be
provided from General Obligation Bonds or any available source of
funds.
SECTION 3. This ordinance shall take effect upon its approval.
INTRODUCED BY:
COU1 CIL M ESR, COUNTY OF HAWAII
Hilo, Hawaii
Date of Introduction:
Date of 1st Reading:
Date of 2nd Reading:
Effective Date:
Y
OF.�!
� qY
o °
/'-%C T T
UUNTY
. o
. _ o
COUNCIL
County of Hawaii
Hawaii County Building
25 Aupunt Street
Hilo, Hawaii 96720
TO Harry A. Takahashi' , Dir w l-
inance Department I IF
2
---
FROM.Ge Council Chairperson"'",
r
RES md r ent to Bill ,
A'-Lenalo Stream Flood Co-ntrol $320,000
I have on ull 19, 1993
16, 1993 ® regarding the above subject
matter,
to the Counc'l for
OF
SPENCER K.SCH E -- - \�,��!,;; JAMES Y.ARAKAKI
Chairman&Presiding Officer EIKO ON -ABRA SON
s. 0 WILLIAMK.C ILDS
ii
BRIAN J.DE LIMA �gr�'oFrN�� TAKASHI DOMINGO
Vice-Chairman HELENE H.HALE
COUNTY COUNCIL JAMES M.RATH
County of Hawaii
ROBERT F.ROSEHILL
Hawaii County Building
25 Aupuni Street
Hilo, Hawaii 96720
August 6, 1993 C-460
TO: Police Chief Victor Vierra '
FROM: Robin J. Yahiku, County C1 r
RE: Bill 99, Draft 2 - A Capital Budget amendment which
includes the Public Safety Building Phase III project
($500, 000)
Councilman Brian De Lima requests that someone from
your department be available to answer questions in
regard to the above-mentioned matter at the
August 11, 1993 , Council Meeting, scheduled to begin
at 8 : 00 a .m, in the Councilroom, at which time the
item will be up for second and final reading®
A transcript of that portion of the minutes is
attached for your information.
Thank you for your attention to this matter.
Att .
cc: Councilman De Lima
kkd
F r
i
SPENCER K.SCHUTTE ®a 0 JAMES Y.ARAKAKI
�
Chairman&Presiding Officer EIKO BON -ABRA SON
• •
•
••-
WILLIAM K.CHILDS
BRIAN J.DE LIMA 'qrF•oF."•NP.e� TAKASHI DOMINGO
Vice-Chairman HELENE H.HALE
COUNTY COUNCIL
JAMES M.RATH
ROBERT F.ROSEHILL
County of Hawaii
Hawaii County Building
25 Aupuni Street
Hilo, Hawaii 96720
E
August
, 1993
C-460
•® Fire Chief Nelson Tsuj *1
® 0
FROM: Obin J. Yahlku, Count er
RE: Bill 99, Draft 2 - A Capital Budget amendment which
includes the Fire Maintenance Shop Extension -
Waiakea ($167, 000) , and Fire Headquarters and
Communication Building ($1,420, 000) projects
Councilman Brian De Lima requests that someone from
your department be available to answer questions in
regard to the above-mentioned matter at the
August 11, 1993, Council Meeting, scheduled to begin
at 8 : 00 a .m. in the Councilroom, at which time the
item will be up for second and final reading®
A transcript of that portion of the minutes is
attached for your information.
Thank you for your attention to this matter,
tt ®
cc: Councilman De Lima
kkd
'I
j
Hawaii o Council , 1993
ORDINANCE A Bill for an Ordinance numbered 99, amends
BILL 99 : Ordinance 93-50J. relating to Public Improvementsand
(FC-72) Financing Thereof for the Fiscal Year July 1, 1993 to
C-460)_ June 30, 1994 , by addingthe following projects :
Fire Maintenance ShopExtension - Waiakea ($167,,* 000) ..
Fire Headquarters and Communications Building
($1,420, 000) , and Public Safety BuildingPhase III
($500, 000) ; funds for these projects shall be
provided from General Obligationand
available source of funds, was introduced
Mr, Arak_ai;
and
COMM, 460 . 01: From Finance Director HarryTakahashi, ate
July 16, 1993 , transmitting a proposed Draft 2 of
Bill 99 by adding an appropriation of $320, 000 for
the Alenaio Stream Flood Control Project;
and
COMM, 460 . 02: From Legislative Assistant Donald Ikeda, dated
July 20, 1993 , regarding Bill 99 , were read.
Mr. Arakaki moved for the passage of
Bill 99 on first reading, and to adopt
Finance Committee Report 72. Seconded by
Mr. Rosehill,
CHR. SCHUTTE: It ' s been moved and seconded that we
adopt Bill 99 . Mrs . Hale, do you want to comment on
Bill 99?
MRS. HALE: Yes, Mr, Chairman. I would like to
know---Bill 99 appropriates $1,420, 000 for the Fire
Headquarters and Communications Building. But in the
committee report, they don't say where we' re going
to---it says, "The committee' s understanding, the
present Administration will issue GO bonds for
$500, 000 to fund the Public Safety Building
Phase III . The additional funding from the County,
with the remaining balance from Act 296 (1991) of
$789 , 000 will allow the Police Department to build
the Evidence Storage Warehouse.
How are we going to build the Fire Headquarters and
Communications Building?
MR. ARAKAKI : Are you asking me?
MRS. HALE: Yeah, well, I 'm asking whoever can answer.
1
3
i
'I l
f
ii
I
1
Hawaii o t
ARA I : We' re going to have to either float
os or getmoney from the Legislature
it .
CHR. T , do you want to come up and---
(Ati time, Finance Director
came forward to address theCouncil , )
S. HALE: Well, why does the committee report only
talk about the GO bonds for $500, 000 and not talk
about the Fire Headquarters and Communication
Building at the same time?
MR. TAKAHASHI : As we discussed in the Finance
Committee, what we' re doing right now is just
reauthorizing the appropriation that had lapsed,
okay, nothing more than that. Recognizing that in
future there will be more funding the ut g requirements,
hopefully, perhaps, the State will provide us some
assistance; if not, then we ' ll have to come in for
additional appropriations at the time when, you know,
we' re ready for another bond issue.
MRS. HALE: How much is it anticipated the Fire
Headquarters and Communication Building is going to
cost?
MR. TAKAHASHI : From what the Chief had indicated, it
seems in the neighborhood of $5 to $6 million.
MRS. HALE: That ' s right. So, we' re just going to
put this on the books, so to speak, and then go to
the Legislature and ask for more money, or what?
MR. TAKAHASHI : Well, what happens here is, at least
if we have this appropriation, they can do some
preliminary work.
MRS. HALE: They can start the planning?
MR. TAKAHASHI : Yeah.
MRS, HALE: And then we can use that, maybe, as
justification to go to the Legislature?
MR, TAKAHASHI : That ' s right.
2
I
Hawaii County Council July 28, 1993
MRS, HALE: Thank you.
CHR. SCHUTTE: Mr. Childs .
MR. CHILDS: Yes, Mr. Chairman, thank you.
Mr. Takahashi, I wanted to clarify something on the
memo from Mr. Ikeda,
clarifying some of the
background events here. It indicates that the State
CIP for $1. 5 million ,
construction, of the Public Safety Building,
including the warehouse.
In the next paragraph it mentions that roughly half
of it, a little over $700, 000 was used to purchase
land for a different purpose--a Fire Department
Administration Buildin . Is that within the scope of
flexibility that the State grant was given in, is
that legal?
MR. TAKAHASHI : We didn' t do the acquisition. The
acquisition, upon our request, okay.
State did the acqu�s p q .Y
So, these monies did not float through the County
coffers . I believe the Administration at that time
discussed the essence with the Governor, and the
Governor gave his approval. So,---
MR. CHILDS: So, the comment here that the County
expended $700, 000 is not quite correct?
MR. TAKAHASHI : No.
MR. CHILDS: And so the State sanctioned the
expediture for a different purpose than the
appropriation? They appropriated for Fire Safety,
but authorized expenditure for a different
Administration Building.
MR, ARAKAKI : Maybe I can answer Mr. Childs, because
I was involved in the negotiation for this money.
What happened was, when we went in to ask for money
for the fire station, our local legislators got us
$1 million; and then the Mayor, at that time, said,
"Oh, we need more money, because now we've got money
to do some plans and designs, but we don' t have money
to buy the land, " and assuming that they would have
money to buy the land.
3
Hawaii County Council July 28, 1993
So, the only vehicle we had was the evidence
warehouse, you know, the Police Safety Building; and
it was supposed to be on the same plot of land at
that time. So, they appropriated money using that
vehicle. So, we used that vehicle to purchase the
money; the State purchased it, the land, with it,
Since that, the Police have decided to build their
Public Safety Building on another parcel; but now the
County owns this particular parcel* So, we want to
go ahead and move ahead with the Fire Safety Building
on that particular parcel .
CHR., SCHUTTE: All right, Mr. De Lima.
MR, DE LIMA: Thank you, Mr. Chairman. You know,
when this matter came up for the Fire Department
building when they did the designs, you know, some
criticism was in regard to the design in that it
included a workout area in an administration
building. The criticism was that we didn't need
another fitness room in an administration building
for the Fire Department, because the firefighters are
actually out in the various fire stations .
Unlike the Police Department where they have a
fitness room, but their police officers report to
that headquarters as well. I 'm just hoping that
given that they may go back to the Legislature, I
would hope that we can get some discussion on the
designs of these buildings before we approve the
appropriation of the monies .
I would like to at least have a concept of what we' re
approving For example, this Public Safety Building
Phase III, you know, I can appreciate the need for an
evidence locker storage room, but I don' t think---you
know, I don' t know what is the concept. So, perhaps
on second reading, they can come to our meeting and
give us a little bit more of a foundation in terms of
what they intend to build.
Because if they' re going to build a monument for an
evidence storage locker, I 've got a problem with
that. But if it ' s going to be something that we can
afford, which hopefully that' s their plans, if we can
4
a aii County Council1
get a better understanding. Because I don'tthink
any of us sitting here have a real concept of what
they' re oin build.
, if
they cancome concept
what ' s goingto be built, my comfortlevel 0
increase. Because I was not really satisfied
the designs of the Fire Headquarters Building. I
fact, I took great exception the thing was .
So, when we asked the architect as to how that plan
derived, what occurred was, they interviewed all
different fire officials, and everybody tossed t,
you know, what they would like to see; and theyput
p a plan based on that comprehensive input. But
maybe that ' s not really in the interest of the
taxpayers to do it that way.
So, I 'm a little concerned about that. I recognize
that this is only a portion of the funding, but if we
can get some input in the terms of what ' s going to
actually be constructed, I 'd feel a little bit more
comfortable.
So, if we could do that in second reading, I think
that would be appropriate. Thank you.
5