HomeMy WebLinkAbout16-061County of Hawaai`i
WINDWARD PLANNING COMMISSION
Aupuni Center • 101 Pauahi Street,Suite 3 • Hilo,Hawaii 96720
Phone(808)961-8288 • Fax(808)961-8742
APR 18 2016
Ms.Danette Martin
General Dynamics
do MP Property Services
76-6357 Kololia Street
Kailua-Kona,HI 96740
Dear Ms. Martin:
SUBJECT: Use Permit No. (USE 16-000061)
Applicant: Cellco Partnership dba Verizon Wireless
Approved Use: Construction of a 105-foot Steel Monopine
Telecommunication Tower and Related Improvements
Tax May Key: 1-5-053:093(yor.)
The Windward Planning Commission, at its duly held public hearing on April 7,2016,voted to
approve the above-referenced request to allow the construction of an unmanned
telecommunication facility,including a 105-foot tall steel monopine and related facilities within
a 1,050 square-foot portion of a one-acre parcel situated in the County's Agricultural-1 acre(A-
1 a)zoning district. The project site is situated at 15-1506 3`C Avenue,approximately 540 feet
northwest ofits intersection with Kaloli Drive in Hawaiian Paradise Park Subdivision,Kea'au,
Puna,Hawaii.
A Petition for Standing in a Contested Case Hearing was received from Petitioner,Robert C.
DeDell Jr. on this matter. The Commission subsequently voted to deny the Petitioner's request
for Intervention.
Approval of this permit is subject to the following conditions:
1. The applicant, its successors or assigns shall be responsible for complying with all
stated conditions of approval.
2.Construction of the monopole shall be completed within five(5) years from the
effective date of this permit. Prior to construction, the applicant, successors or
assigns shall secure Final Plan Approval for the proposed development from the
Planning Director in accordance with Section 25-2-71(c)(3), 25-2-72, 25-2-74 and
25-4-12, Chapter 25 (Zoning Code), Hawai`i County Code. Plans shall identify
Hawai`i County is an Equal Opportunity Provider and Employer
APR1B2°16
Ms. Danette Martin
General Dynamics
do MP Property Services
Page 2
proposed structures,fire protection measures,access easements and any fencing
associated with the use. Landscaping shall also be indicated on the plans along
northeast and northwest corner of the property for the purpose ofmitigating any
adverse noise or visual impacts to adjacent properties. The plans shall identify
existing landscaping and new landscaping in the areas that do not currently have
landscaping in place. The antenna plans shall be stamped by a structural engineer.
3.Co-location of antennas upon the existing tower and expansion of related support
equipment within the project site may be allowed within the parameters of the
tower height as approved by the Planning Commission,provided that ground lease
areas of co-locating carriers are adjacent to the existing ground lease area and not
located within the open yard setback areas.
4. Prior to the issuance of Final Plan Approval,the applicant shall secure and
finalize any building permits for the subject property required by the Department
of Public Works Building Division.
5. Within 120 days of the permanent abandonment of the tower,the applicant shall
remove the tower and its antenna and accessory structures(including the
equipment building and the fence),down to,but not including,the concrete
foundation. The applicant shall immediately provide written notification to the
Planning Director of the termination of the telecommunication tower and related
improvements and the removal of all structures.
6.Should any unidentified sites or remains such as lava tubes, artifacts, shell,bone,
or charcoal deposits,human burials,rock or coral alignments,pavings,or walls be
encountered,work in the immediate area shall cease and the Department of Land
and Natural Resources—Historic Preservation Division(DLNR-HPD) shall be
immediately notified. Subsequent work shall proceed upon an archaeological
clearance from the DLNR-HPD when it finds that sufficient mitigative measures
have been taken.
7.Comply with all applicable rules,regulations and requirements ofthe affected
agencies for the proposed development, including the Federal Aviation
Administration and Federal Communications Commission. All exterior lighting
shall be shielded.
8. An initial extension of time for the performance of conditions of the permit may
be granted by the Planning Director upon the following circumstances:
Ms. Danette Martin
General Dynamics
do MP Property Services
Page 3
A. Non-performance is the result of conditions that could not have been
foreseen or are beyond the control ofthe applicant,successors or assigns,
and that are not the result of their fault or negligence.
B. Granting of the time extension would not be contrary to the General Plan
or the Zoning Code.
C. Granting of the extension would not be contrary to the original reasons for
the granting ofthe permit.
D. The time extension granted shall be for a period not to exceed the period
originally granted for performance(i.e., a condition to be performed within
one year may be extended for up to one additional year).
Should any of the conditions not be met or substantially complied with in a timely
fashion,the Director may initiate procedures to revoke the permit.
This approval does not,however, sanction the specific plans submitted with the application as
they may be subject to change given specific code and regulatory requirements of the affected
agencies
Approval ofthis permit is based on the reasons given in the attached Findings Report.
Should you have any questions,please contact Christian Kay of the Planning Department at
961-8136.
Sin
f
Ch: les •- hairman
W' dwarf ' a.9fi : s'ssion
LCellcopartnershipUSE16-06Iwpc
Enclosure: PC Findings Report
cc: Cellco Partnership dba Verizon Wireless
Department of Public Works
Department of Water Supply
County Real Property Tax Division- Hilo
Department of Land &Natural Resources -HPD
GIS Section
COUNTY OF HAWAII
PLANNING COMMISSION FINDINGS
CELLCO PARTNERSHIP DBA VERIZON WIRELESS
USE PERMIT APPLICATION(USE 16-000061)
Based on the following, Use Permit No. 16-000061 is hereby issued to allow the
construction of a new telecommunication facility, including a 105-foot tall steel monopine and
related facilities within a 1,050 square-foot portion of a 1 acre parcel is approved by the Planning
Commission.
CELLCO PARTNERSHIP DBA VERIZON WIRELESS is requesting a Use Permit to
allow the construction of a new, unmanned telecommunication facility, including a 105-foot tall
steel monopine with 8-foot tall panel antennas and related facilities within a 1,050 square-foot
portion of a one (1) acre parcel situated in the County's Agricultural 1-acre (A-1a) zoning
district. The property is located at 15-1506 3rd Avenue, approximately 680 feet northwest of its
intersection with Kaloli Drive in Hawaiian Paradise Park Subdivision, Kea'au, Puna, Hawaii,
TMK: 1-5-053: Portion of 093.
The applicant, Cellco Partnership dba Verizon Wireless is requesting a Use Permit to
construct a 105-foot tall steel monopine with twelve(12) 8-foot panel antennas. A monopine is a
monopole and antennae disguised with branches to resemble a pine tree. The facility would be
designed to accommodate other carriers (co-location). In addition to the monopine, the 1,050-
square foot (30'x 35') leased area would be used for accessory ground facilities, which include
outdoor equipment cabinets and a diesel emergency generator, and a retaining wall on a concrete
slab. The leased area will be surrounded with 6-foot high chain link security fencing with locked
gates. The pole will be constructed of structural galvanized steel and built to withstand 105 mph
wind load. The proposed facility would be unmanned,and maintenance and repair activities will
be performed by a technician on a periodic basis. The applicant will comply with all Federal
Communications Commission (FCC) and Federal Aviation Administration (FAA) rules.
Additionally,the monopole will not interfere with the County's public safety radio system.
According to the applicant,the majority of the Hawaiian Paradise Park(HPP)subdivision
has little to no wireless coverage. The objective of this project is to allow Verizon to expand
wireless telephone and E911 services to the subdivision by adding several cell sites strategically
placed to provide coverage to the majority ofthe residences in the area.
Telecommunication towers and antennas previously required a Special Permit to operate
within the State Land Use Agricultural District. In 2007, the State Legislature adopted Act 171
to allow the construction and operation of wireless communication antennas and towers as
permitted uses within the State Land Use Agricultural District. In 2010, the Hawaii County
Council approved Ordinance No. 10-17 to require a Use Permit for telecommunication antennas
and towers in the County's Agricultural zoned district. As the applicant is proposing to construct
a new tower in the County's Agricultural (A-1a) zoned district, a Use Permit is required.
In considering a Use Permit for any proposed use, Rule 7 of the Planning Commission
relating to Use Permits,requires that such action conform to the following guidelines:
A. The granting of the proposed use shall be consistent with the general purpose of
the zoned district, the intent and purpose of the Zoning Code and the County General Plan;
1-
B. The granting of the proposed use shall not be materially detrimental to the public
welfare nor cause substantial adverse impact to the community's character or to surrounding
properties; and
C. The granting of the proposed use shall not unreasonably burden public agencies to
provide roads and streets, sewers, water, drainage, school improvements, police and fire
protection and other related infrastructure.
The proposed request meets the guidelines for approval of a Use Permit, for the reasons
outlined below:
The granting of the proposed use shall be consistent with the general purpose of the
zoning district, the intent and purpose of the Zoning Code and the County General Plan.
The Use Permit process provides an avenue to review and analyze a proposed project on a case-
by-case basis relative to infrastructure and impacts on surrounding properties and existing uses,
as well as consistency with the goals and polices of the General Plan. The Zoning Code allows
for telecommunication antennas and towers to be a permitted use within the County's
Agricultural zoned district if a Use Permit is approved by the Planning Commission.
The Land Use Pattern Allocation Guide(LUPAG)Map component of the General Plan is
a representation of the document's goals and policies to guide the coordinated growth and
development ofthe County. It reflects a graphic depiction of the physical relationship among the
various land uses. The LUPAG Map establishes the basic urban and non-urban form for areas
within the County. The General Plan designations for this property is Rural, which includes
existing subdivisions in the State Land Use Agricultural and Rural districts that have a
significant residential component. Typical lot sizes vary from 9,000-square feet to two acres.
These subdivisions may contain small farms, wooded areas, and open fields as well as
residences. Allowable uses within these areas,with appropriate zoning,may include commercial
facilities that serve the residential and agricultural uses in the area, and community and public
facilities. The Rural designation does not necessarily mean that these areas should be further
subdivided to smaller lots. Most lack the infrastructure necessary to allow further subdivision.
Telecommunication facilities may be allowed in this area with the approval of a Use Permit from
the Planning Commission.
The telephone is an essential means of voice communication for the majority of residents
in Hawai`i County. However, over the last decade, the County has seen acceleration in the
development of telecommunication technology and a transformation of the telecommunications
industry. In addition to traditional phone communication, the telecommunications industry now
includes technologies such as wireless cellular and digital mobile phones, the internet and World
Wide Web.
During the last decade,wireless telecommunications has experienced a dramatic decrease
in cost and a phenomenal increase in availability. Changes in technology and competition in the
industry have made wireless communication more affordable to the general public.
Advances in telecommunications are not without cost or concerns. One such concern is
the construction and location of telecommunication towers. Telecommunication towers are the
physical structures to which antennas are attached to facilitate wireless communication. Because
of the need for a clear line-of-site, telecommunication towers are usually located in areas with
minimum obstructions between the tower and its area of service. Line-of-site refers to the
imaginary line between a mobile phone antenna and a telecommunication tower. If there are
impediments between the mobile phone antenna and the telecommunication tower, there may be
2-
signal degradation or signal loss. For example, the loss of line-of-sight occurs when a person
uses a mobile phone while driving through a tunnel. Most often, communication is lost or
unclear. The line-of-sight requirement often necessitates the conspicuous location of many
telecommunication towers. Consequently, the telecommunications tower is usually much taller
than the surrounding structures or vegetation and may negatively impact the scenic nature of a
given area.
A standard in the Public Utilities element of the General Plan states that in the
development and placement of telephone facilities, such as lines, telecommunications and
cellular towers, poles, and substations, the design of the facilities shall consider the existing
environment, and scenic view and vistas shall be considered and preserved where possible. The
tower site is located on a small portion of a 1-acre property. There is significant public benefit to
be gained by the installation of the proposed telecommunication tower for the residents in this
area. Therefore, approval of this request will not run contrary to the goals,policies and standards
of the General Plan.
Lastly, the Puna Community Development Plan (CDP) was adopted by the Hawai'i
County Council on September 10, 2008. The request is consistent with Action 3.4.3. (e) under
the Public Safety and Sanitation Services section in the plan, which states, "Encourage
enhancement of cell phone service to expand coverage to more remote areas."
Based on the above, the request is consistent with the general purpose of the zoned
district,the intent and purpose ofthe Zoning Code, the County General Plan, and the Puna CDP.
The granting of the proposed use shall not be materially detrimental to the public
welfare nor cause substantial, adverse impact to the community's character or to
surrounding properties. The project site is a 1,050 square- foot (30' x35') portion of a 1-acre
property. There is an existing single-family dwelling which was built in 2011 and a detached
garage/single story lanai situated being the single-family dwelling, built in 2015. The remainder
ofthe property is undeveloped. The surrounding properties are similarly zoned A-la and consist
of scattered dwellings, agricultural uses and vacant land. The nearest dwelling is located
approximately 340 feet south of the project site.
In order to mitigate possible visual impacts, the monopine facility will emulate the
appearance of a pine tree with the monopole and antennae disguised with branches to resemble a
pine tree.
It is anticipated that the approval ofthe telecommunication tower will be beneficial to the
community as it will provide increased cell phone coverage in the area and will be a significant
resource for emergency services.
Therefore,based on the above, the proposed use shall not be materially detrimental to the
public welfare nor cause substantial, adverse impact to the community's character or to
surrounding properties.
The granting of the proposed use will not unreasonably burden public agencies to
provide roads and streets, sewer, water, drainage, school improvements, police and fire
protection and other related infrastructure.
The desired use shall not unreasonably burden public agencies to provide roads and
streets, sewers, water, drainage, school improvements, and police and fire protection. Only
electrical and telephone services are required for the use and they are already available to the
property. Access to the property will be from 3rd Avenue, which is a private road that has an
approximately 20-foot paved asphalt road within a 50-foot right-of-way. As traffic is anticipated
3-
to be minimal, the access to the site on the property is adequate. Fire and police services are
available to the project area in Kea'au and Pahoa. Finally, the applicant will be required to meet
all applicable agency requirements, including the Federal Communications Commission and the
Federal Aviation Administration.
In addition to the criteria for granting a Use Permit, the request is not contrary to
Chapter 205A, Hawaii Revised Statutes, relating to Coastal Zone Management Area. The
subject property is located approximately one (1) mile from the nearest shoreline and is not
located in the Special Management Area, and therefore will not be impacted by coastal hazards
and beach erosion. There are no identified coastal recreational resources, coastal scenic and
open space resources, coastal ecosystems, and beach or marine resources in the area. Thus, the
proposed request will not adversely impact coastal resources. Additionally, there is no record of
a designated public access to the shoreline or mountain areas that traverses the property.
Lastly, this approval is made with the understanding that the applicant remains
responsible for complying with all other applicable governmental requirements in connection
with the approved use, prior to its commencement or establishment upon the subject properties.
Additional governmental requirements may include the issuance of building permits, the
installation of approved wastewater disposal systems, compliance with the Fire Code, installation
of improvements required by the American with Disabilities Act (ADA), among many others.
Compliance with all applicable governmental requirements is a condition of this approval; failure
to comply with such requirements will be considered a violation that may result in enforcement
action by the Planning Department and/or the affected agencies.
4-