Use Permit Application (UP 92-4)
Applicant: Daniel, Mann, Johnson & Mendenhall, Hawaii
Request: Church Use and Related Improvements
Tax Mao Key: 6-5-04.33
The Planning Commission at its duly held public hearing on
June 18, 1992, voted to approve your application, Use Permit No.
103, to allow the establishment of a church and related improvements
on 4.60 acres of land situated within the County's Agricultural -1
acre (A -la) zoned district. The property is situated approximately
700 feet from the Lindsey Road-Kapiolani Road intersection on the
north side of Kapiolani Road, Waimea Homesteads, South Kohala,
Hawaii.
Approval of this request is based on the following:
The proposed church use would be consistent with the
general purpose of the zoned district, the intent and purpose of
the Zoning Code, and the County General Plan. The establishment
of a church and related improvements in the County's
Agricultural and the State Land Use Urban District may be
allowed through the granting of a Use Permit. The General Plan
designates the area for Medium Density Urban uses. Such a
designation may allow for village and neighborhood commercial
uses and residential and its related functions. This proposed
use also conforms to a goal of the Land Use Element of the
General Plan which states: "Designate and allocate land uses in
appropriate proportions and mix and in keeping with the social,
cultural, and physical environments of the County." The
proposed use would support the development of community -oriented
JUN 2 9 1992
David Harris Hart, AIA
June 25, 1992
Page 2
facilities for the neighborhood and would enhance the
community's character by supporting and providing needed
community services.
The granting of the proposed use will not be materially
detrimental to the public welfare nor cause substantial, adverse
impact to the community's character or to surrounding
properties. The property presently has two existing
single-family dwellings on the lot which will be retained and
used as missionary housing. The adjacent properties are in
single family residential use or vacant. To minimize noise and
visual impacts to neighboring residences, a minimum 50 -foot
structural setback is being imposed along all side and rear
property lines with provisions for landscaping. In the past,
this 50 -foot setback has been imposed on other church structures
where nearby residences could be affected. The minimum setback
requirement and landscaping should provide an efficient buffer
from noise or visual impacts that may be generated by the
proposed church. It will also accommodate for future increases
in residential density in areas immediately surrounding the
subject property. To ensure that such impact is minimized and
the residential/agricultural character of the area be
maintained, it is recommended that these be included as
conditions of approval.
The granting of the proposed use will not adversely affect
similar or related existing uses within the surrounding area,
community or region. The proposed church facilities will
replace an existing meeting house located in Waimea. The
services offered by the church will supplement existing
religious services and needs in the region.
The granting of the proposed use will not unreasonably
burden public agencies to provide roads and streets, sewer,
water, drainage, schools, police and fire protection and other
related infrastructure. Access to the subject property from
Mamalahoa Highway is via Lindsey Road, which has a 60 -foot
right -of way with a 16 -foot wide pavement. Access from Lindsey
Road to the project site is via Kapiolani Road, a County road
which has a 40 -foot right-of-way with a 19 -foot wide pavement.
A draft Traffic Impact Analysis Report (TIAR) submitted by the
applicant has been reviewed by the Department of Public Works
and the Planning Director. The traffic assessment concludes
that traffic volumes on Kawaihae-Waimea Road will increase by
less than one percent during the weekday 24-hour period, weekday
David Harris Hart, AIA
June 25, 1992
Page 3
AM peak hour and weekday PM peak hour. The report also states
that since Sunday traffic volumes are lower than average
weekday, Kawaihae-Waimea Road should adequately accommodate the
Sunday peak hour demand. The Department of Public Works has
reviewed the TIAR and determined that the proposed use of the
church on Sundays and during the specified hours on weekdays
should not have an adverse impact on traffic patterns in the
area.
All other necessary services are available or will be
available to the property. With the fulfillment of all
requirements specified by affected agencies, the proposed use is
not anticipated to have an adverse impact on infrastructure in
the area. The use is consistent with the Land Use Policy of the
General Plan to "Promote and encourage the rehabilitation and
use of urban and rural areas which are served by basic community
facilities and utilities."
Approval of this request is subject to the following conditions:
1. The applicant, its successors or assigns shall be
responsible for complying with all stated conditions of
approval.
2. Final Plan Approval for the proposed church and related
improvements shall be secured from the Planning Department
within one year from the effective date of this permit. To
assure adequate time for plan approval review and in
accordance with Chapter 25-244 (Zoning Code), plans shall
be submitted a minimum of forty-five days prior to the date
by which plan approval must be secured. Plans shall
identify all structures, interior driveway circulation,
fire protection measures, and paved parking stalls
associated with the proposed church. Plans shall indicate
a minimum 50 -foot structural setback from all side and rear
property lines. Plans shall also show detailed landscaping
for the church buildings and parking area to create a
visual and noise buffer area between existing and future
residential properties. The applicant shall maintain
parking for all church functions on the subject property.
Parking shall comply with the requirements of Chapter 25
(Zoning Code).
3. Construction of the church and related improvements shall
commence within one year from the date of receipt of Final
David Harris Hart, AIA
June 25, 1992
Page 4
Plan Approval and shall be completed within two years
thereafter.
4. Driveway access from Kapiolani Road shall comply with the
requirements of the Department of Public Works.
5. A 5 -foot wide road widening strip along Kapiolani Road
shall be delineated on the plans submitted for plan
approval review. No structural improvements shall be
allowed within this road widening strip, provided, however,
any required landscaping may be permitted within this
strip. Further, applicable setbacks shall be taken from
the 5 -foot future road widening strip line.
6. All other applicable laws, rules, regulations, and
requirements shall be complied with, including those of the
Department of Health and the'Fire Department.
7. Preschool or day-care activities shall not be permitted.
B. Should any unidentified sites or remains such as artifacts,
shell, bone, or charcoal deposits, human burials, rock or
coral alignments, pavings or walks be encountered, work in
the immediate area shall cease and the Planning Department
shall be immediately notified. Subsequent work shall
proceed upon an archaeological clearance from the Planning
Department when it finds that sufficient mitigative
measures have been taken.
9. An annual progress report shall be submitted to the
Planning Director prior to the anniversary date of the
approval of the permit. The report shall include, but not
be limited to, the status of the development and to what
extent the conditions of approval are being complied with.
This condition shall remain in effect until all of the
conditions of approval have been complied with and the
Planning Director acknowledges that further reports are not
required.
10. An extension of time for the performance of conditions
within the permit may be granted by the Planning Director
upon the following circumstances: a) the non-performance
is the result of conditions that could not have been
foreseen or are beyond the control of the applicant,
successors or assigns, and that are not the result of their
David Harris Hart, AIA
June 25, 1992
Page 5
fault or negligence; b) granting of the time extension
would not be contrary to the General Plan or Zoning Code;
c) granting of the time extension would not be contrary to
the original reasons for the granting of the permit; and
d) the time extension granted shall be for a period not to
exceed the period originally granted for performance (i.e.,
a condition to be performed within one year may be extended
for up to one additional year). Further, should any of the
conditions not be met or substantially complied with in a
timely fashion, the Director shall initiate procedures to
revoke the permit.
This approval does not, however, sanction the specific plans
submitted with the application as they may be subject to change
given specific code and regulatory requirements of the affected
agencies.
Please feel free to contact the Planning Department if there are
any questions on this matter.
Sincerely,
64 X A LOL/
Mike Luce, Chairman
Planning Commission
7474d
jdk
xc: Department of Public Works
Department of Water Supply
County Real Property Tax Division
West Hawaii Office
DLNR
Mayor
Planning Director
Plan Approval Section