HomeMy WebLinkAboutReport of Change Order Authorized 5.31.2021REPORT OF CHANGE ORDERS AUTHORIZED
FOR THE PERIOD OF:
5/16/2021-5/31/2021
CO
SA
PS
C
PTA
GS
Original Original % of Cumulative % of
Execution Job Contract Project Contract Dept.Contract Contract CO/SA CO/SA Orig CO/SA Orig Contractor Project Project Purpose
Date ##Title Type Amount Date No.Amount Cont Total Cont Manager Status
5/20/2021 NA C.008412 General Plan Comprehensive Review SA
Planni
ng $313,500.00 6/22/2020 1 $35,000.00 11.16%$35,000.00 11%Focused Planning Solutions, LLC
Bethany
Morrison Open
Additional services for General Plan Comprehensive
Review completion.
5/24/2021 NA PTA Kupuna Care Home and Community Based Services SA
Office
of
Aging $0.00 7/1/2020 1 $0.00 0.00%$0.00 0%
5 Point United Allegiance Corp. dba
Hi Care Solutions Clayton Honma Open Amends time of performance.
5/24/2021 NA PTA Family Caregiver Support Services SA
Office
of
Aging $0.00 7/1/2020 1 $0.00 0.00%$0.00 0%
5 Point United Allegiance Corp. dba
Hi Care Solutions Clayton Honma Open Amends time of performance.
5/24/2021 NA C.008252
Engineering Services to Prepare a Technical Memorandum for the Kaloko
Wastewater Treatment Plan SA DEM $125,220.00 4/15/2020 1 $228,580.00 182.54%$228,580.00 183%R.M. Towill Corporation Dora Beck Open
To authorize task 3 for the preparation and submittal of
RFP documents for a proposed MBR wastewater treatment
plant; and to incorporate the CDBG Special Conditions
CDBG/2021
5/26/2021 NA C.008878 COVID-19 Emergency Shelter, Kona Seaside Hotel CO Finance $802,566.81 10/28/2020 3 $376,963.20 46.97%$2,261,579.20 282%Kimi Hotels, Inc. Hamana Ventura Open Third lease extension through June 30, 2021 as necessary to respond to the COVID-19 pandemic.
5/26/2021 NA NA MOA with the State of Hawaii for reimbursement of emergency sheltering and wrap around services for COVID-19 SA Finance $0.00 12/29/2020 2 $0.00 0.00%$0.00 0%State of Hawaii, Dept of Health Hamana Ventura Open Second extension of MOA through July 31, 2021.
5/26/2021 NA C.007392 Using taro breeding to overcome disease and empower farmers SA R&D $12,000.00 12/26/2018 3 $0.00 0.00%$0.00 0%University of Hawaii Glenn Sako Open
No cost time extension from June 30, 2021 to December
31, 2021.
5/27/2021 PR-4223 C.008213 Pana'ewa Zoo & Pana'ewa Equestrian Center Accessibility Improvements CO DPW $8,988,700.00 2/28/2020 7 $198,387.07 2.21%$1,225,656.90 14%Stan's Contracting, Inc.Eydie Komata Open
Modifications necessary to address accessibility
compliance, building inspector's comments, modified truss
detailing (Bldg 18) and unforeseen utility failure and water
runoff/drainage issues.
Total CO/SA
for Period
Price Term Agreement
Other Goods & Services
Legend:
Change Order
Supplemental AgreementProfessional Services
Construction
Contracts
Total CO/SA $838,930.27Amount for Period
Total Original Contract $10,241,986.81 8Amount