HomeMy WebLinkAboutReport of Change Orders Authorized 4.15.22REPORT OF CHANGE ORDERS AUTHORIZED
FOR THE PERIOD OF:
4/01/2022-4/15/2022
COSAPSCPTA
GS
Original Original % of Cumulative % of
Execution Job Contract Project Contrac Dept.Contract Contract CO/SA CO/SA Orig CO/SA Orig Contractor Project Project Purpose
Date ##Title Type Amount Date No.Amount Cont Total Cont Manager Status
4/8/2022 IFB#4076 PTA PTA for heavy equipment for various locations island wide, DEM, COH SA Fin $0.00 5/3/2021 1 $0.00 0.00%$0.00 0%Herc Rentals, Inc. Rory O'Donnell Open Extend for an additional four month period beginning April 1, 2022 and ending July 31, 2022.
4/11/2022 B-4559 C.009078 Civil Defense EOC Expansion SA DPW $1,528,000.00 4/20/2021 3 $18,510.00 1.21%$92,953.46 6%Diede Construction Inc. James Imanaka Open
Additional scope of work required to patch new opening in existing wall, provide sound base for paint, divert water away from accessible walkway and parking stall,
prevent condensation from air conditioning overflowing and draining to office floor,
and minimize disruption to the facility and staff.
4/12/2022 NA C.008188 Structural engineering services for the Waimea Trails and Greenway Project Phase 1 SA DPW $693,875.00 2/14/2020 1 $222,544.62 32.07%$222,544.62 32%Okahara & Associates Inc. Allan Simeon Open
Additional work due to changed and unforeseen conditions which were not covered in
the original contract.
4/14/2022 NA C.005379 Special counsel - legal services, Department of Human Resources, Workers Compensation Division SA
Human
Resources $300,000.00 12/3/2015 3 $60,000.00 20.00%$310,000.00 103%Leong Kunihiro & Brooke Waylen Leopoldino Open
To provide additional legal services to the County in the area of workers compensation
law.
Total CO/SA
for Period
\
Price Term AgreementOther Goods & Services
Legend:Change Order
Supplemental Agreement
Professional Services
Construction
Contracts
Total CO/SA $301,054.62Amount for Period
4 Total Original Contract $2,521,875.00 4Amount