HomeMy WebLinkAboutReport of Change Orders Authorized 2.28.2023REPORT OF CHANGE ORDERS AUTHORIZED
FOR THE PERIOD OF:
2/16/2023-2/28/2023
CO
SAPS
CPTA
GS
Original Original % of Cumulative % ofExecutionJob Contract Project Contract Dept.Contract Contract CO/SA CO/SA Orig CO/SA Orig Contractor Project Project Purpose
Date ##Title Type Amount Date No.Amount Cont Total Cont Manager Status
2/16/2023 NA C.008783 Design-Build for Kukuiola Access Road SA OHCD $214,857.58 9/9/2020 6 $22,693.95 10.56%$6,655,913.76 3097.83%Tinguely Development S Hirota Open
Budget adjustments to reflect change in scope of work and the removal of
work related to the "Village".
2/16/2023 WW-4631 C.009858 Kapehu WWTP Perimeter Security Fence CO DEM $301,017.10 6/16/2022 1 -$28,397.00 -9.43%-$28,397.00 -9.43%Isemoto Contracting Co. Ltd.M Grant Open
Incorporation of Field Orders 1,2,4 to provide: Extension of time from
August 30, 2022 through February 3, 2023, additional materials, hauling and disposal, and reduction of Hydro-seeding and grass maintenance.
2/16/2023 IFB#4076 PTA Heavy Equipment for Various Locations Island Wide for DEM, COH SA FIN $0.00 5/3/2021 4 $0.00 0.00%$0.00 0.00%Bacon Universal Company N Charon Open
Extend by three-month period from February 1, 2023 through April 30,
2023.
2/16/2023 IFB#4076 PTA Heavy Equipment for Various Locations Island Wide for DEM, COH SA FIN $0.00 7/20/2021 4 $0.00 0.00%$0.00 0.00%Sanborn General Contracting Inc.N Charon Open
Extend by three-month period from February 1, 2023 through April 30, 2023.
2/17/2023 H-4672 C.009847 Ulu Wini Housing Exterior Building Repairs and Maintenance SA DPW $886,186.00 6/13/2022 3 $4,978.32 0.56%$88,893.35 10.03%Isemoto Contracting Co. Ltd.TJ Oesterling Open
Fabricate and install metal grates at the junction of roof gutters and
downspouts in order to filter out foreign materails washing off roof which could obstruct downspouts and outfall lines.
2/22/2023 RFP#3909 PTA Furnish/Operate Hele-On Fixed Route Transit Service for MTA, COH SA FIN $0.00 2/25/2020 4 $0.00 0.00%$0.00 0.00%
Robert's Tours and Transportation,
Inc.N Charon Open
Extend by optional one-year term from February 24, 2023 through
February 23, 2024.
2/22/2023 B-4614 C.010091 Pahala Fire Station Perimeter Fencing CO DPW $267,900.00 7/16/2022 1 $1,710.00 0.64%$1,710.00 0.64%Site Engineering, Inc.J Imanaka Open Relocate entry pad pedestal 12 feet away from the gate.
2/23/2023 T-4650 PTA Traffic Signal Repairs and Installation for the East Side District SA DPW $0.00 2/22/2022 1 $0.00 0.00%$0.00 0.00%T&T Electric, Inc.A Takaba Open Extend for 126 day period from February 25, 2023 through June 30, 2023.
2/27/2023 IFB#4211 PTA Septage Hauling and Pumping Services for Various Septic Tanks, Wastewater Facilities, and Collection Systems SA FIN $0.00 5/22/2022 2 $0.00 0.00%$0.00 0.00%Kona Lua N Charon Open Extend for optional one-year period from May 1, 2023 through April 30, 2024.
2/28/2023 IFB#3834 PTA Furnishing and Delivering LD Streetlights for DPW, COH SA FIN $0.00 7/29/2019 4 $0.00 0.00%$0.00 0.00%Wesco Distributions, Inc.N Charon Open
Extend for optional one-year period from July 1, 2023 through June 30,
2024.Total CO/SA
for PeriodContracts
Total CO/SA $985.27Amount for Period
10 Total Original Contract $1,669,960.68 10Amount
Price Term AgreementOther Goods & Services
Legend:
Change OrderSupplemental Agreement
Professional ServicesConstruction