HomeMy WebLinkAboutPlanning Commission Process Flow ChartsBUCKET 1-A: Planning Commission Recommendation & County Council Decision
State Land Use (15 acres or less), Change of Zone, Project District, & Agriculture Project District
REZ/APD/PD/SLU
APPLICATION SUBMITTED
Determination of Completeness
(15 Days)
APPLICATION Applicant
ACCEPTED INCOMPLETE Notification
Planning Director Recommendation
REZ/APD/PD: within 120 days of acceptance date
■ SLU: within 90 days of acceptance date
Favorable Recommendation
■ *Director inaction defaults to Unfavorable Recommendation
favorable recommendation
■
■
■
Planning Commission Hearin
■ SLU: within 60 days of Director recommendatio
■
:
■ Favorable Recommendation Unfavorable Recommendation
■ PC inaction defaults to unfavorable
' recommendation
:
■ County Council Review & Decision
REZ/APD/PD: within 90 days of PC recommendation receipt
Applicant APPROVAL
Notification ) &a
Applicant
Notification
3" Circuit
Court Appeal
: Optional Process
BUCKET 1-B: Planning Commission Recommendation & County Council Decision
County Council Initiated Zoning Code & Subdivision Code Amendments, Planning Director Initiated Zoning and
Subdivision Code Amendments
Planning Director Recommendationj
Planning Commission Hearing & Recommendation 1
CC initiated: within 120 days from receipt from CC J
FUnfavorable Recommendation
Favorable Recommendation
PC inaction defaults to unfavorable
recommendation
County Council Review
PD initiated: within 60 days of PC recommendation
CC initiated: after 120 days
APPROVAL
Applicant Applicant
Notificat' Notification
3ra Circuit
Court Appeal
: Optional Process
BUCKET 2: Planning Commission Decision
Planned Unit Development Permit, Special Permit (15 acres or less), Use Permit, Shoreline Setback Variance, Special
Management Area Use Permit
APPLICATION SUBMITTED
■
Determination of Completeness I
(15 Days) J
;
A*
ant
APPLICATION INCOMPLETE
Notification
ACCEPTED
Planning Director Recommendation
Favorable �
Unfavorable
■
Recommendation
Recommendation
Planning Commission Hearing
Within 90 days of acceptance date
Telecom USE: within 60 days of acceptance date
LN�oApplicant
tification is
3ra Circuit
Court Appeal
APPROVAL
Applicant Notification of PC Decision
Within 60 days of hearing
: Optional Process
BUCKET 3: Planning Commission Recommendation & Land Use Commission Decision
Special Permit (over 15 acres)
■APPLICATION SUBMITTED
Determination of Completeness
(15 Days)
Applicant
■ APPLICATION INCOMPLETE Notification
■ ACCEPTED hL
Planning Director Recommendation
I Favorable Recommendation
■
■
♦
♦
♦
♦
Unfavorable Recommendation
Planning Commission Hearing
Within 90 days of acceptance date
APPROVAL
DENIAL
PC Recommendation Transmitted to LU�
Within 60 days of PC decision
Land Use Commission Decision
1w Within 45 days of receipt from PC
DENIAL APPROVAL
w/ modifications
r Applicant Applicant
l Notification Notification
APPROVAL
Applicant
Notification
3ra Circuit
Court Appeal : Optional Process