HomeMy WebLinkAbout2023-07-26 Director's Report (Part II)Name Deadline Text30 %
Complete
Submit Naalehu PER
to EPA
Sun 9/3/23 Within 300 days of
EPA's Approval of
the Feasibility
Report
0%
August Public
Outreach Meeting
Thu 8/31/23 At Least Once in
August
0%
Provide Notice of
Public Meeting
Fri 8/18/23 At Least 14 Days in
Advance
0%
July Quarterly EPA
Meeting
Mon
7/31/23
Schedule Meeting
No Later Than July
20th
0%
October Quarterly
EPA Meeting
Fri 10/20/23 Schedule Meeting
No Later Than
October 20th
0%
Naalehu and Pahala Large Capacity Cesspool AOC
100%
41%37%
28%
0%0%0%0%
100%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
% COMPLETE
30%
Name Start Finish Duration % Complete
EPA to Review and
Approve Pahala PER
Mon 7/3/23 Mon 7/31/23 20 days?0%
LATE TASKS
Tasks that are Past Due
SAT 7/1/17 WED 10/20/27
PROJECT OVERVIEW
% COMPLETE
Status for All Top-Level Tasks
AOC DEADLINES
3 Month Outlook for AOC Deadlines
Deadline Details
Name Finish Deadline %
Complete
Construction (Pahala Elderly Apartments)Thu 7/14/22 NA 100%
Pahala Elderly Apartments Cesspool Replacement Project Thu 7/14/22 NA 100%
Implement the Pahala Elderly Apartments Compliance Plan Thu 7/14/22 NA 100%
Design (Pahala)Fri 7/12/24 NA 0%
Pahala Community Cesspool Closure Project Fri 7/12/24 NA 0%
Implement the Pahala Community Cesspool Closure Project Fri 7/12/24 NA 0%
Planning Mon 1/13/25 NA 37%
Feasibility Evaluation Report (Pahala)Mon 11/7/22 NA 100%
Submit Feasibility Evaluation Report (Pahala)Fri 10/21/22 Fri 10/21/22 100%
EPA Review & Approval of Feasibility Report (Pahala)Mon 11/7/22 Mon 11/7/22 100%
Feasibility Evaluation Report (Naalehu)Mon 11/7/22 NA 100%
Submit Feasibility Evaluation Report (Naalehu)Fri 10/21/22 Fri 10/21/22 100%
EPA Review & Approval of Feasibility Report (Naalehu)Mon 11/7/22 Mon 11/7/22 100%
Pahala Preliminary Engineering Report (PER)Mon 7/31/23 NA 87%
Submit PER for Pahala to EPA Sat 5/6/23 Sat 5/6/23 100%
Naalehu Preliminary Engineering Report (PER)Fri 9/29/23 NA 65%
Contract Award Tue 4/25/23 NA 100%
Kickoff Meeting Fri 5/5/23 NA 100%
Submit Naalehu PER to EPA Sun 9/3/23 Sun 9/3/23 0%
Pahala Pahala Community Cesspool Closure Implementation Plan Sat 4/13/24 NA 0%
Submit Pahala Implementation Plan Sun 3/24/24 NA 0%
Environmental Review Fri 10/25/24 NA 0%
Submit an Environmental Information Document (EID) for Pahala Sat 1/27/24 NA 0%
Submit an Environmental Information Document (EID) for Naalehu Sat 9/28/24 NA 0%
Naalehu Pahala Community Cesspool Closure Implementation Plan Mon 1/13/25 NA 0%
Submit Naalehu Implementation Plan Tue 12/24/24 NA 0%
Construction (Naalehu)Wed 2/19/25 NA 0%
PROJECT MILESTONES
Major Milestones for this Project Include Contract Execution, Tasks and Deliverables
Construction (Naalehu)Wed 2/19/25 NA 0%LCC Closure Wed 2/19/25 NA 0%
Close Naalehu Community Cesspool Wed 2/19/25 Fri 12/31/27 0%
Construction (Pahala)Tue 7/21/26 NA 0%
LCC Closure Tue 7/21/26 NA 0%
Close Pahala Community Cesspool Tue 7/21/26 Tue 7/21/26 0%
Public Engagement Wed 7/21/27 NA 41%
Create Public Webpage and Submit Address to EPA Thu 9/22/22 Wed 9/21/22 100%
Public Meeting to Explain AOC Requirements Thu 10/6/22 Thu 10/6/22 100%
Public Engagement (Pahala Project Options & EID)Sun 4/28/24 NA 0%
Commence Solicitation of Public Comment on the Project Options and EID for Pahala Mon 3/25/24 NA 0%
Provide Notice of all Public Meetings and Opportunities for Public Engagement & Instructions for Submitting Comments Tue 3/26/24 NA 0%
Hold At Least One Public Meeting within the Community Where the Project will Take Place Wed 3/27/24 NA 0%
Submit a Summary Response Document & Post on the Website Sun 4/28/24 NA 0%
Public Engagement (Naalehu Project Options & EID)Sun 12/29/24 NA 0%
Commence Solicitation of Public Comment on the Project Options and EID for Naalehu Mon 11/25/24 NA 0%
Provide Notice of all Public Meetings and Opportunities for Public Engagement & Instructions for Submitting Comments Tue 11/26/24 NA 0%
Hold At Least One Public Meeting within the Community Where the Project will Take Place Wed 11/27/24 NA 0%
Submit a Summary Response Document & Post on the Website Sun 12/29/24 NA 0%
Maintain Public Webpage and Submit Address to EPA Wed 7/21/27 NA 44%
Update Webpage (Monthly)Wed 7/21/27 NA 44%
Reporting and Meetings Wed 10/20/27 NA 28%
Semiannual Reports Thu 7/1/27 NA 29%
January Semiannual Reports Sat 1/2/27 NA 34%
July Semiannual Reports Thu 7/1/27 NA 23%
Semiannual Public Outreach Meetings Tue 8/31/27 NA 16%
February Public Outreach Meetings Sun 2/28/27 NA 16%
August Public Outreach Meetings Tue 8/31/27 NA 17%
Quarterly Meetings with EPA Wed 10/20/27 NA 25%
January Quarterly Meetings Wed 1/20/27 NA 20%
April Quarterly Meetings Tue 4/20/27 NA 33%
July Quarterly Meetings Tue 7/20/27 NA 17%
October Quarterly Meetings Wed 10/20/27 NA 29%
Number Project/Tasks Duration Finish % Complete
Kealakehe WWTP R-1 Phase I (Process and Treatment within the Facility) 2073 days Tue 2/25/25 16%
Planning 1753 days Tue 12/5/23 15%
Design 120 days Tue 4/25/23 90%
Construction 480 days Tue 2/25/25 0%
Kealakehe WWTP Sand Filter Upgrade Project (Alternative to KWWTP R-1 Phase I)894 days?Wed 3/19/25 13%
Design 894 days?Wed 3/19/25 59%
Advertisement & Award of Construction Project 52 days Fri 7/28/23 0%
Construction 300 days?Mon 9/23/24 0%
3 North Kona SPS, FM, Hina Lani Gravity Sewer, West Hawai'I Business Park Gravity Sewer 1186 days?Mon 5/20/24 3%
4 Kealakehe SPS Roof Repair Project 95 days?Mon 2/27/23 100%
Hale Halawai SPS FM Replacement Project 1078 days?Sun 3/9/25 39%
Design Contract Development 0 days?Mon 3/28/22 100%
Design 346 days?Tue 3/7/23 91%
Task 1 Project Management 26 days Fri 4/22/22 100%
Task 2 Site Investigations 344 days Mon 3/6/23 86%
Task 3 - Basis of Design Report (BODR)168 days?Mon 9/26/22 100%
Task 4 - Permitting and Clearances 161 days Mon 3/6/23 10%
Task 5 - Bid Documents 161 days Mon 3/6/23 8%
Advertisment and Award of Contruction Project 248 days?Wed 11/15/23 0%
Construction 480 days Sun 3/9/25 0%
1
2
5
Westside Projects
-
Hilo Wastewater Treatment Plant Upgrade
99%
67%
0%
65%
51%
8%
0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
% COMPLETE
28%
LATE TASKS
Tasks that are Past Due
Name Finish % Complete
Phase 2 Consultant Notice to
Proceed (NTP)
Thu 9/1/22 0%
Complete SHPD Clearance for
HRS 6E-8
Fri 12/30/22 75%
Complete Section 106 Clearance Fri 12/30/22 40%
Complete Section 7 Clearance Fri 12/30/22 40%
Draft Environmental Assessment Tue 11/21/23 0%
Final Environmental Assessment Tue 2/13/24 0%
50% Design Submittal Workshop Fri 7/21/23 0%
Final Design Submittal
Workshop
Mon 1/29/24 0%
MILESTONES DUE
Milestones that are Coming Soon
FRI 9/24/21 WED 8/2/28
PROJECT OVERVIEW
% COMPLETE
Status for All Top-Level Tasks
Name Start Finish Duration % Complete
Phase 2 Consultant
Notice to Proceed
(NTP)
Thu 9/1/22 Thu 9/1/22 0 days 0%
Complete SHPD
Clearance for HRS 6E-
8
Wed 6/1/22 Fri 12/30/22 153 days?75%
Complete Section 106
Clearance
Wed 6/1/22 Fri 12/30/22 153 days?40%
Complete Section 7
Clearance
Wed 6/1/22 Fri 12/30/22 153 days?40%
50% Design Submittal Thu 1/12/23 Tue 5/23/23 94 days 95%
Phase 2 Permitting
Process
Wed 5/24/23 Fri 3/1/24 203 days 0%
Name Finish %
Complete
Planning EA Exemption Fri 12/30/22 67%
Draft EA Exception Mon 9/19/22 100%
EA Exemption Wed
11/30/22
100%
Complete SHPD Clearance for HRS 6E-8 Fri 12/30/22 75%
Complete Section 106 Clearance Fri 12/30/22 40%
Complete Section 7 Clearance Fri 12/30/22 40%
Contract Development (Design) c.009652 Fri 3/31/23 99%
Phase 1 Contract Wed 1/26/22 100%
Consultant Notice to Proceed (NTP)Wed 1/26/22 100%
Phase 2 Supplemental Agreement Thu 9/1/22 99%
Phase 2 Consultant Notice to
Proceed (NTP)
Thu 9/1/22 0%
Planning EA Tue 2/13/24 0%
Permit Cooling Period Tue
11/21/23
0%
Draft Environmental Assessment Tue
11/21/23
0%
Final Environmental Assessment Tue 2/13/24 0%
Advertisement and Award of Construction Project Thu 6/13/24 51%
Phase 1 Bid/Award Period Wed 6/14/23 99%
Advertise for Bidding Thu 2/23/23 100%
Phase 2 Bid/Award Period Thu 6/13/24 0%
Advertise for Bidding Thu 2/15/24 0%
Notice of Award Thu 6/13/24 0%
Design Tue
12/10/24
65%
Phase 1 Design Tue 5/30/23 100%
Complete Conceptual Design
Submittal
Fri 6/3/22 100%
PROJECT MILESTONES
Major Milestones for this Project Include Contract Execution, Tasks and Deliverables
Name Start Finish %
Complete
Contract Development (Design) c.009652 Fri 9/24/21 Fri 3/31/23 99%
Phase 2 Supplemental Agreement Fri 2/25/22 Thu 9/1/22 99%
Phase 2 Consultant
Notice to Proceed (NTP)
Thu 9/1/22 Thu 9/1/22 0%
Planning EA Exemption Wed 6/1/22 Fri
12/30/22
67%
Complete SHPD Clearance for HRS
6E-8
Wed 6/1/22 Fri
12/30/22
75%
Complete Section 106 Clearance Wed 6/1/22 Fri
12/30/22
40%
Complete Section 7 Clearance Wed 6/1/22 Fri
12/30/22
40%
Contract Development (Construction)Wed 9/7/22 Fri
11/10/23
8%
Complete Fair and Reasonable
Analysis
Mon
10/17/22
Mon
10/17/22
50%
Submit to Draft Contract to BSS
Review and Finalization
Wed
10/19/22
Tue
11/1/22
75%
Route Contract Externally for
Signature
Wed 11/2/22 Wed
11/2/22
0%
Receive Certification of Funds
from Finance Dept.
Wed 11/2/22 Tue
1/31/23
0%
Route Contract Internally for
Signature
Wed 2/1/23 Tue
3/14/23
0%
Consultant Notice to Proceed
(NTP)
Wed 3/15/23 Tue 4/4/23 0%
Status of Tasks Sarting in the Next 3 Months
TASKS STARTING SOON
Complete Conceptual Design Submittal Fri 6/3/22 100%
Solids Conceptual Design Tue 5/31/22 100%
Headworks Conceptual
Design Workshop
Fri 6/3/22 100%
Complete 50% Design Submittal Tue 8/30/22 100%
50% Design Submittal
Workshop
Tue 8/30/22 100%
Complete Final Design Submittal/Bid
Documents
Mon 1/30/23 100%
Final Design Submittal
Workshop
Thu 1/12/23 100%
Phase 2 Design Tue 4/30/24 29%
Complete Conceptual Design
Submittal
Wed 1/11/23 100%
Conceptual Design
Workshop
Wed 1/11/23 100%
Complete 50% Design Submittal Wed 6/7/23 95%
50% Design Submittal
Workshop
Fri 7/21/23 0%
Complete Final Design Submittal/Bid
Documents
Fri 12/29/23 0%
Final Design Submittal
Workshop
Mon 1/29/24 0%
Construction Wed 8/2/28 0%
Phase 2 Construction Wed 8/2/28 0%
Notice to Proceed Wed 8/14/24 0%
-
Puna Wastewater PEIS and Facility Plan
100%100%
95%
100%
91%
86%
88%
90%
92%
94%
96%
98%
100%
Project
Execution
Project
Definition
Report (PDR)
Facility Plan Public Review
and
Participation
PEIS
% COMPLETE
94%
Name Start Finish Duration % Complete
HDEM Facility Plan
Review
Mon 5/29/23 Fri 7/7/23 30 days 50%
LATE TASKS
Tasks that are Past Due
Name Finish
Complete Final Facility Plan Sat 8/26/23
Final PEIS Publication Sat 9/23/23
MILESTONES DUE
Milestones that are Coming Soon
MON 3/14/22 SAT 9/23/23
PROJECT OVERVIEW % COMPLETE
Status for all top-level tasks.
Name Finish %
Complete
Project Execution Mon 3/14/22 100%
Notice to Proceed with Contract (c009727)Mon 3/14/22 100%
Project Definition Report (PDR)Tue 9/13/22 100%
Complete Final PDR Tue 9/13/22 100%
Public Review and Participation Mon
10/24/22
100%
PEIS Public Scoping Meeting Wed
10/12/22
100%
Facility Plan Sat 8/26/23 95%
Complete Draft Facility Plan Fri 2/24/23 100%
Prepare Final Facility Plan Sat 8/26/23 0%
Complete Final Facility Plan Sat 8/26/23 0%
PEIS Sat 9/23/23 91%
PEISPN Mon
10/24/22
100%
PEISPN Publication Fri 9/23/22 100%
Draft PEIS Mon 2/27/23 100%
Complete Draft PEIS Mon 1/9/23 100%
File Draft PEIS Wed 6/7/23 100%
File Draft PEIS Publication Sun 4/23/23 100%
Final PEIS Fri 9/8/23 62%
Final PEIS Publication Sat 9/23/23 0%
PROJECT MILESTONES
Major Milestones for this Project Include Contract Execution, Tasks and Deliverables
Name Start Finish %
Complete
Facility Plan Tue 6/28/22 Sat 8/26/23 95%
HDEM Facility Plan Review Mon 5/29/23 Fri 7/7/23 50%
Prepare Final Facility Plan Sat 8/26/23 Sat 8/26/23 0%
Complete Final Facility
Plan
Sat 8/26/23 Sat 8/26/23 0%
PEIS Fri 4/15/22 Sat 9/23/23 91%
Final PEIS Mon 4/17/23 Fri 9/8/23 62%
HDEM Review Mon 5/29/23 Wed
7/26/23
95%
Revise and Submit Final
PFEIS
Thu 7/27/23 Thu
9/21/23
0%
Final PEIS Publication Sat 9/23/23 Sat 9/23/23 0%
Status of Tasks Sarting in the Next 3 Months
TASKS STARTING SOON
-
Puako & South Kohala Regional Wastewater Master Plan
100%
53%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Project Execution Planning
% COMPLETE
53%
Name Start Finish Duration % Complete
LATE TASKS
Tasks that are Past Due
Name Finish
Complete Pre-Final Wastewater Master Plan Mon 8/19/24
Complete Final Wastewater Master Plan Sun 1/19/25
MILESTONES DUE
Milestones that are Coming Soon
FRI 7/15/22 SUN 1/19/25
PROJECT OVERVIEW
% COMPLETE
Status for All Top-Level Tasks
**THERE ARE NO LATE TASKS FOR THIS PROJECT**
Name Finish %
Complete
Project Execution Tue 8/30/22 100%
Notice To Proceed with Contract c.009861 Sun 7/17/22 100%
Planning Sun 1/19/25 53%
Project Definition Report (PDR)Sat 1/18/25 77%
Complete Draft PDR Sat 4/8/23 100%
Complete Final PDR Wed 7/19/23 100%
Wastewater Master Plan Sun 1/19/25 43%
Complete Pre-Final Wastewater
Master Plan
Mon 8/19/24 0%
Complete Final Wastewater Master
Plan
Sun 1/19/25 0%
PROJECT MILESTONES
Major Milestones for this Project Include Contract Execution, Tasks and Deliverables
Name Start Finish %
Complete
Status of Tasks Sarting in the Next 3 Months
TASKS STARTING SOON