HomeMy WebLinkAbout23-08-15 Semi-Annual Report (01-01-23 to 6-30-23) - SignedMitchell D. Roth
Mayor
Lee owl
Managing Director
County of Hawaii
DEPARTMENT OF ENVIRONMENTAL MANAGEMENT
345 Kekuanao`a Street, Suite 41 Hilo, Hawaii 96720
Ph: (808) 961-8083 fax: (808) 961-8086
Email: cohdem@hawaiicounty.gov
July 3, 2023
Mr. Jelani Shareem
EPA Region 9 Compliance Officer
75 Hawthorne Street
San Francisco, California 94105-3901
(Email shareem.jelani@epa.gov)
Ms. Kate Rao
EPA Region 9 LCC Project Coordinator
75 Hawthorne Street
San Francisco, California 94105-3901
(Email rao.kate@epa.gov)
Subject: Federal Administrative Order on Consent
EPA Docket No. SDWA-UIC-AOC-2017-0002
Pahala and Na`alehu Large Capacity Cesspools
SEMI ANNUAL REPORT (1/1/23 through 6/30/23)
Dear Mr. Shareem and Ms. Rao,
Ramzi I. IVlansour
Director
Brenda D. lokepa-Moses
Deputy Director
The County of Hawai' i Department of Environmental Management is submitting this report in
accordance with Section VI, Reporting Requirements, of EPA Docket No. SDWA-UIC-AOC-
2017-002 which requires that Semi -Annual Compliance Reports be submitted to the EPA Region
9 Compliance Officer and EPA Region 9 LCC Project Coordinator twice per year.
As per Item 62 of the Revised Administrative Order on Consent, this report covers the period of
January 1, 2023, through June 30, 2023.
Due to the separate facilities and multiple milestones, the report has been submitted in a tabular
format for clarity and is provided as ATTACHMENT 1.
Should there be any comments or questions on the report please contact Chris Laude, P.E.,
Acting Wastewater Division Chief at 808 961-8279 (Christopher.laude@hawaiicounty.gov) or
myself at 808-961-8083 (Brenda.iokepa-moses@hawancounty.gov).
County of Hawaii is an Equal Opportunity Provider and Employer
Or. Jelani Shareem
Ms. Kate Rao
July 3, 2023
Page 2
I certify under penalty of law that this document and all attachments were prepared under my
direction or supervision in accordance with a system designed to assure that qualified personnel
properly gather and evaluate information submitted. Based on my inquiry of the person or
persons who manage the system, or those persons directly responsible for gathering the
information, I certify that the information submitted is, to the best of my knowledge and belief,
true, accurate, and complete. I am aware that there are significant penalties for submitting false
information, including the possibility of fine and imprisonment for knowing violations.
Sincerely,
Brenda Iokepa-Moses
Deputy Director
County of Hawaii Department of Environmental Management
ATTACHMENT
cc: Mitch Roth, Mayor
Lee Lord, Managing Director
Diana Mellon -Lacey, Deputy Corporation Counsel
Ramzi I. Mansour, DEM Director
Chris Laude, P.E., Acting Wastewater Division Chief
Kimberly Wells, EPA Region 9 Counsel
Sina Pruder, P.E., DOH-WWB
Craig Lekven, P.E., Brown & Caldwell
County of Hawai' i is an Equal Opportunity Provider and Employer.
REVISED ADMINISTRATIVE ORDER ON CONSENT
DOCKET SDWA-UIC-AOC-2017-0002
NA`ALEHU AND PAHALA LARGE CAPACITY CESSPOOLS
SEMI-ANNUAL REPORT: January 1, 2023, through June 30, 2023
Section V.A Planning , ;
Compliance Date
1
Milestone
t' Current Status
Pending Actions ,
Comments
'
1,
, .
Within 60 days of
V.A.31.a
1. Revised AOC effective date is
None.
Complete.
execution of the
Submit Feasibility
8/22/20220
Revised AOC
Evaluation Report
2. Report submitted to EPA on
(NLT Oct 21, 2022)
for Pahala and
10/18/20220
Naalehu for EPA
3. EPA approved report on
approval
11/7/2022,
Within 180 days of
V.A.31.b
1. Report submitted on April 19,
1. Waiting for EPA
EPA's written approval
Submit Pahala
2021
approval.
of Feasibility Evaluation
Preliminary
report
Engineering Report
(NLT May 6, 2023)
for EPA approval
Within 300 days of
V.A.31.b
1. PER in preparation.
1. Submit PER to EPA by
EPA's written approval
Submit Naalehu
9/3/23.
of Feasibility Evaluation
Preliminary
Report
Engineering Report
(NLT Sep 3, 2023)
for EPA approval
ATTACHMENT 1
Page 1
TBD = To Be Determined
NLT = No Later Than
REVISED ADMINISTRATIVE ORDER ON CONSENT
DOCKET SDWA-UIC-AOC-2017-0002
NA`ALEHU AND PAHALA LARGE CAPACITY CESSPOOLS
SEMI-ANNUAL REPORT: January 1, 2023, through June 30, 2023
Within 30 days of V.B.32.a TBD TBD
EPXs written Submit Pahala
approval of EID Implementation Plan
for EPA approval
NLTJul 21, 2026 V.B.32.a TBD TBD
Close Pahala LCCs
ATTACHMENT 1
Page 2
TBD =To Be Determined
NLT = No Later Than
REVISED ADMINISTRATIVE ORDER ON CONSENT
DOCKET SDWA-UIC-AOC-2017-0002
NA`ALEHU AND PAHALA LARGE CAPACITY CESSPOOLS
SEMI-ANNUAL REPORT: January 1, 2023, through June 30, 2023
Within 60 days of EPA's V.C.33.a. TBD TBD
written approval of EID Submit
Implementation
Plan for EPA
approval
NLT Dec 31, 2027 V.C.33.a. TBD TBD
Close Naalehu
LCCs
Section V.D. Pahala Elderly Apartments Cesspool Replacement Project
Compliance Date
Milestone '
Current Status
Pending Actions
Comments
NLT Sep 28, 2018
V.D34.
1. LCCs have been closed. The
None.
Complete.
Close LCCs
backfill completion report
was received by EPA on
6/1/2018.
ATTACHMENT 1
Page 3
TBD =To Be Determined
NLT = No later Than
REVISED ADMINISTRATIVE ORDER ON CONSENT
DOCKET SDWA-UIC-AOC-2017-0002
NA`ALEHU AND PAHALA LARGE CAPACITY CESSPOOLS
SEMI-ANNUAL REPORT: January 1, 2023, through June 30, 2023
Section V.E. Outreach
Compliance Date
Milestone
Current Status
Pending Actions '
Comments
Within 30 days of
V.E.36.
1. Webpage established on
Monthly webpage updates
execution of the Revised
Maintain a public
9/20/2022.
AOC
webpage to keep
2• Updated on 1/18/2023.
(NLT Sep 21, 2022)
EPA and the
3. Updated on 2/2/2023.
public informed
4. Updated on 3/31/2023.
of the status of
S. Updated on 4/24/223.
the Community
6. Updated on 5/23/2023.
Cesspool Closure
7• Updated on 6/19/2023,
Projects. Update
at least monthly.
Within 45 days of
V.E.40.
1. Public meeting held in
None
Complete
execution of the Revised
Hold public
Naalehu 8/31/2022.
AOC
meeting to
(NLT Oct 6, 2022)
explain the
requirements of
the Revised AOC
Within 30 days of EPA
V.E.40.
TBD
TBD
approval of Pahala EID
Commence
solicitation of
public comment
on the project
options and
environmental
review
information
ATTACHMENT 1
TBD = To Be Determined
NLT= No Later Than
REVISED ADMINISTRATIVE ORDER ON CONSENT
DOCKET SDWA-UIC-AOC-Z017-0002
NA`ALEHU AND PAHALA LARGE CAPACITY CESSPOOLS
SEMI-ANNUAL REPORT: January 1, 2023, through June 30, 2023
Section V.E. Outreach
Compliance Date
Milestone
Current Status
Pending Actions
Comments
Within 30 days of EPA
V.E.40.
TBD
TBD
approval of Naalehu EID
Commence
solicitation of
public comment
on the project
options and
environmental
review
information
Starting NLT Aug 2022
V.E.42
1. Public meeting held in Pahala
1. Public meeting to be
Start holding
on 2/23/2023.
held in Naalehu on
semi-annual
2. Notice of public meeting sent
8/24/20230
public outreach
6/20234
meetings in
August and
February
ATTACHMENT 1
TBD =To Be Determined
NLT = No Later Than