HomeMy WebLinkAbout2009-10-16 TPUAKOBAY
LEEWARD PLANNING COMMISSION
COUNTY OF HAWAIÒI
HEARING TRANSCRIPT
OCTOBER 16, 2009
PUAKO BAY INVESTORS, LLC (SMA
A regularly advertised hearing on the application of
07-16)
was called to order at 9:43 a.m. in the Waikoloa Beach Marriott Hotel, AliÒi III Room,
69-275 Waikoloa Drive, Waikoloa, HawaiÒi, with Chairman Rodney Watanabe presiding.
PRESENT: Rodney Watanabe
Brandi Beaudet
Geraldine Giffin
Frederic Housel
Wayne Iokepa
, Deputy Corporation Counsel
Bill Brilhante
BJ Leithead Todd, Planning Director
Norman Hayashi, Planning Program Manager
Phyllis Fujimoto, Staff Planner
Jeff Darrow, Staff Planner
Maija Cottle, Staff Planner
Lani Bowman
ABSENT & EXCUSED:
And three people from the public in attendance
APPLICANT: PUAKO BAY INVESTORS, LLC (SMA 07-16)
Amendment to condition no. 2 (secure water commitment) and relat
Management Area Use Permit No. 07-16 which allowed the developme
subdivision and related improvements. The property is located on the makai side of Puak
Beach Drive, adjacent to and east of the Puak boat ramp, Lalamilo, South Kohala, HawaiÒi,
TMK: 6-9-2:1 and 2.
WATANABE: We will proceed to Agenda Item No. 1. The applicant i Bay
Investors, LLC, and itÓs SMA Permit 07-16. Jeff?
DARROW: Thank you, Mr. Chairman. Good morning, Members of the Planning
Commission. IÓd like to welcome you this morning. If I can direct your attention to the
presentation. This morning our first applicant is Puak Bay Investors, LLC. They are requesting
an amendment to Condition No. 2 for Special Management Area Use Permit No. 07-16. The
location of this application is within the South Kohala District. More specifically, we are
looking in the entrance to the Puak area. We have, on our location map, we have the entrance
from Queen KaÒahumanu Highway, which is on the right side of the map, and this will go onto
Puak Beach Drive heading makai. And the area of the subject properties are identified with two
black outlines; this is just south of the boat harbor thatÓs located down in this area. As you will
EXHIBIT A
1
notice the different colors of zoning, the light green is Agricultural 5 acres, we have, the darker
green is Open zoning and then we have Resort zoning for the purple. W
e also have some Single-
Family Residential identified in yellow and darker yellow. Here is an aerial photo of the actual
properties. These are in this general location; again, we have the boat harbor, or the boat launch,
just to the north of this property.
The applicant is requesting a one-year time extension to comply with Condition No. 2, which is
the requirement to secure the water commitments for the developm
to allow the development of an eight-lot single-family residential subdivision and related
improvements. The Planning Director is recommending approval of their request. Are there any
questions?
WATANABE: Fellow Commissioners, do we have any questions of staff? Seeing none,
for the record, before I forget, no one has signed up to testify
Fuke, I believe you are the representative for Puak Bay Investors?
FUKE: Yes, sir.
WATANABE: Yeah, just for, you know, swear you in. Do you swear or affirm to tell the
truth now before the Planning Commission?
FUKE: Yes, I do.
WATANABE: Thank you. And then, of course, name and address.
FUKE: Good morning, Mr. Chairman, Members of the Commission. My name is
Sidney Fuke. IÓm a planning consultant. IÓm working on this application with the owner.
Unfortunately, the owner is in his second home, which is Las Vegas, so he is not able to attend.
IÓll give him a report after the outcome of todayÓs meeting Î hopefully, itÓs favorable.
Just to add a little bit to the staff report, IÓd like to kind of note a couple of things. One is that in
terms of the water system, what the applicant has done to date is that we had a number of
meetings with the existing resort developers who have previously participated with the
Department of Water Supply. And so they do have excess water commitments that conceivably
could be assigned to this property, and these are particularly Mauna Lani Resort and Mauna Kea
Resort Properties. Nothing has been, you know, consummated with either of these resorts.
WeÓve also had discussions with the former developers of the Bridge Òina LeÒa property,
which is Bridge Capital. But since the new owners, DW Òina LeÒa Development Corporation,
bought the Urban designated area, and is now obligated to fulfill a lot of the water related
requirements, there have been active discussions with DW Òina LeÒa. So we hope that over the
next year, or within the extended time period, if the Commission so grants it, you know, weÓd be
able to consummate something and the project can proceed.
The other thing I want to kind of note is that since the original SMA Permit was issued, the only
substantive regulatory change that has occurred was the adoption of the South Kohala
Community Development Plan. And since the adoption back in November of 2008 -. And if
EXHIBIT A
2
you look at that Plan compared to whatÓs being proposed, itÓs totally consistent with the Puak
conceptual land use plan for that area. So aside from
that, if there are any questions the
Commissioners have, IÓll be happy to answer.
WATANABE: Fellow Commissioners, any questions of Mr. Fuke? I have one. I noted
that, okay, we gave you apparently in the original SMA one year, and I believe Bobby Jean, or
the Director, gave you an administrative extension. Is Î I donÓt want to muddy the water but Î is
one year sufficient?
FUKE: Like any development we would like to have like infinity in terms of
planning; but I think itÓs realistic and I think that the standard practice on the part of the
Commission in matters like this has always been like one year, so -.
WATANABE: Typically, traditionally itÓs been one year, so you are okay?
FUKE: Correct, yes.
WATANABE: Okay, then I wonÓt, yeah, I wonÓt pursue that. Yes, Mr. Hayashi.
HAYASHI: That is what I wanted to clarify, because the applicant actually requested a
two-year extension to that particular condition.
FUKE: We said like up to two years, so if the Commission is willing to extend up
to two years, then you know, that would, as I said, itÓs better than, I mean itÓs short of infinity but
way better than one year. But IÓll leave that to the Commission. I really donÓt know what the
Commission or the DepartmentÓs policy has been in terms of time
would have been equivalent to like the original request, which was one year plus a one-year
administrative time extension, so -.
WATANABE: Mr. Hayashi?
HAYASHI: Yes, as far as the time extension, in the initial administrative time
extension the Director is allowed to do that; but the maximum would be whatever is was -.
WATANABE: Originally, and originally it was one year, right?
HAYASHI: Yeah, so if it was one year, then it would have to be for one year. There is
no policy set as to if the Commission were to grant a time extension request.
WATANABE: Yeah, okay, then I guess my next question would be directed to the
Director, and IÓd rather have your input than just the Commission voting.
LEITHEAD TODD: I think the two-year is a reasonable request, especially considering both
the applicants and my experience in the Department in terms of how long it takes to work out
these agreements, especially when you are dealing with multiple
EXHIBIT A
3
WATANABE: Okay. Yeah, there was about that and others because the economic
situation we find ourselves in. So you know, maybe itÓs just an exercise, yeah, if one year. But
along those same lines, though, I have, oh, Condition No. 3 within the conditions, we say, ÐFinal
Subdivision approval shall be secured within five (5) years from the effective date of this
permit.Ñ I guess my question is, does the effective date now change to this date?
FUKE: Mr. Chairman, if I can respond to that -.
WATANABE: Yes.
FUKE: It really wouldnÓt affect the developerÓs overall schedule because, you
know, as your staff indicated previously, the Planning Director is entitled to grant an additional
administrative extension; so if we cannot complete within the five years, then conceivably an
additional five years could be secured.
WATANABE: Right, exactly, exactly. But the clock does not actually restart on this.
LEITHEAD TODD: No.
WATANABE: No. Okay. I just, for the record. Then I guess my question would be
directed to the fellow Commissioners. Do we, in light of the new information, do we want to
revise this to two years as opposed to a one-year extension?
HAYASHI: Mr. Chair, since the Director had no objections to extending the request to
two years, Condition 2 would be amended by the Department to state that the time extension
would be for two years from the effective date of the amended permit.
WATANABE: Thank you. Is everybody okay with that? Then if thatÓs the case, may I
have a mo-?
GIFFIN: Mr. Chairman?
WATANABE: Ms. Giffin.
GIFFIN: Okay, so then we are changing the wording of the condition, correct?
WATANABE: Just on Condition 2 we are replacing ÐoneÑ with Ðtwo.Ñ
GIFFIN: Correct. I have a question of Mr. Fuke.
WATANABE: Yes.
GIFFIN: On the first page of the background report under Proposed Action No. 2,
the Reasons for the Request, the second to the last sentence, ÐCurrently, the best option appears
to be securing excess water commitments from landowners and developers in the area.Ñ And I
know you addressed and you mentioned Mauna Lani and Mauna Kea. How far along are those
EXHIBIT A
4
discussions and how realistic is it that their water commitments could be used up, or used
towards this project?
FUKE: Conceivably, you know, at this point in time there is excess water
commitments thatÓs already been earned by Mauna Lani and Mauna Kea. Mauna Lani has, in
our discussions with Mauna Lani, they do have a few, well, basically they donÓt have any
developable lands because whatever lands that they had originally satisfied for development have
already been parceled out or sold to different investors; however, in our discussion Î and so
based on the amount of water availability required for their projects, if you take that aside,
Mauna Lani would still be in the position to assign the additional water commitments, their water
commitments to this project Î however, what they have told us is that because in the past the
different units have used sometimes in excess of the normally allocated 600 gallons per day,
some for example have used, you know, like the single-family dwellings anyway, have used like
4,000 to 5,000 gallons per day, and then so this has created some issues for Mauna Lani, and thus
Mauna Lani and Mauna Kea have had to construct new well systems, you know, to secure
additional water commitments. And based on that Mauna Lani is saying that they would not
want to put themselves in jeopardy at this point in time; so they are saying maybe four or five
years from now after the project has developed, we can consider it. As it relates to Mauna Kea,
Mauna Kea is saying that, yeah, they do have more than enough water; however, what they told
the applicant is that, however, if you can give us some assuranc
this water come back to us, you know, then maybe we can work som
why we are trying to work with DW Òina LeÒa because DW Òina LeÒa already has a water
agreement with the Water Department to construct two wells at thuli system, and that will
then provide considerable amount of water not only for their project but being in the position
where Òina LeÒa could then restore the water that was assigned from Mauna Kea to Puak Bay
Investors. So it becomes a little bit convoluted, but Î and thatÓs why I appreciate what the
Planning Director is saying that if you have to do a tri-party agreement, it might take longer than
a year to have it established.
GIFFIN: Thank you.
WATANABE: Okay. Do we have any further -? Mr. Brilhante.
BRILHANTE: Yes. Sorry to interject here, but just a little housekeeping matter. As a ,
you know, in the, I guess, proposed change in the condition, just directing us back to Item No. 3
where it says the Ðfinal subdivision approval shall be secured within five (5) years from the
effective date of this permit,Ñ I know there was some discussion about the automatic five-year
extension; what I donÓt want to have happen is there be any confusion as to when that automatic
extension takes effect. I notice the date of the original permit, I believe, is a Ð07Ñ number, so
there might be at least a two-year difference between when the original permit was granted and
todayÓs approval. So what I propose is language to the effect of the Ðfinal subdivision approval
shall be secured within five (5) years from the effective date of the original permit,Ñ if thatÓs
something that you guys would want to have discussion on this, my proposal.
WATANABE: Mr. Fuke, I believe that was what we previously discussed, and it seems
like it summarizes what we discussed.
EXHIBIT A
5
FUKE:
ThatÓs the understanding, and so for clarity what your counsel is advising
is perfectly fine.
WATANABE: Okay, thank you. And while we are on the subject Î I know we are not
making any amendments to any of the others but Î everything else is fine, right, as far as
conditions?
FUKE: Well, we canÓt request any amendments because we didnÓt make the
request, so -. Yeah, thank you.
WATANABE: Okay, okay, thank you. So then we are, the original permit -.
GIFFIN: So Mr. Chairman?
WATANABE: Yes.
GIFFIN: The clock has started to tick already then, right, is what was -?
WATANABE: Yeah, in essence approximately two years have elapsed for the first five
years. And they would still be, you know, dependent upon the Di
allowed a five-year administrative extension.
GIFFIN: Okay.
WATANABE: So, is everybody clear on this? We have two minor revisions. I would,
since we have no one signed up to testify and it doesnÓt appear like we have any questions, I
entertain a motion.
GIFFIN: Mr. Chairman, IÓd like to move that the request for an amendment to
Condition No. 2 of the SMA Use Permit 07-16 be approved with the
two-year and Condition No. 3 as amended by our counsel. Is that the correct wording?
WATANABE: Yes, thatÓs correct. And the amendment would be inserting -.
GIFFIN: ÐOriginal -.Ñ
WATANABE: Replacing, yeah, inserting Ðthe original,Ñ or replacing ÐthisÑ with Ðthe
original.Ñ Okay, is everybody clear on that? Do we have a second?
HOUSEL: IÓll second that.
WATANABE: Thank you, Mr. Housel. If there is no further discussion, Mr. Darrow?
EXHIBIT A
6
DARROW: Thank you, Mr. Chairman. The motion is to approve with the
amendments to Condition No. 2 and Condition No. 3. With that, IÓll take the roll.
Commissioner Giffin?
GIFFIN: Aye.
DARROW: Commissioner Housel?
HOUSEL: Aye.
DARROW: Commissioner Beaudet?
BEAUDET: Aye.
DARROW: Commissioner Iokepa?
IOKEPA: Aye.
DARROW: And Mr. Chairman?
WATANABE: Aye.
DARROW: The motion passes, five to zero.
WATANABE: Okay. So youÓll be notified in writing, Mr. Fuke.
FUKE: Thank you very much, Director and Commission, for the additional year
especially.
The discussion ended at 10:00 a.m.
Respectfully submitted,
Noriko Sauer, Secretary
Leeward Planning Commission
EXHIBIT A
7