Loading...
HomeMy WebLinkAbout2022_09_Waipio_Valley_Rd_Eval_Project-Rockfall_and_Slope_Instability_Mitigation_and_Conceptual_Design_Summary_Report www.haleyaldrich.com HALEY & ALDRICH, INC. 6 Waterfront Plaza 500 Ala Moana Boulevard, Suite 6-250 Honolulu, HI 96813 808.587.7747 www.haleyaldrich.com 30 September 2022 File No. 0203303 County of Hawai’i Department of Public Works 101 Pauahi Street, Suite 7 Hilo, Hawai’i 96720 Attention: Stephen M. Pause, P.E. Director, Department of Public Works SUBJECT: Rockfall and Slope Instability Mitigation and Conceptual Design Summary Report Valley Road Evaluation Project Honokaa , Hawai‘i Haley & Aldrich, Inc. (Haley & Aldrich) is pleased to submit this report providing mitigation recommendations for rockfall and slope instability hazards along Waipi‘o Valley Road. Valley ‘o. The Road is narrow and winds along the steep hillside of the south valley wall, with an approximately 800 feet elevation change in 0.7 mile. The location of the project area is shown on Figure 1 and the overall alignment on Figure 2. Our work was completed in general accordance with our scope and fee estimate provided on 11 March 2022, and our subconsultant agreement with County of Hawai‘i Department of Public Works (DPW) dated 20 April 2022. 1 Project Understanding gic slope hazards and related roadway stability issues. As part of a Preliminary Geotechnical Engineering Evaluation, Hart Crowser, Inc. (now a part of Haley & Aldrich) geologists conducted an initial investigation, rating the slope hazards within the scope of the Federal Highway Administration (FHWA) Rockfall Hazard Rating System (RHRS) and assessing for risk using a numerical approach developed by the Australian Geomechanics Society. The results from this study were provided in a report, dated January 2022 (the “Initial Evaluation”), that highlighted the need for remediation and provided preliminary recommendations for rockfall mitigation. Haley & Aldrich has conducted further site reconnaissance to evaluate in more detail the conditions identified during the initial evaluation and to define the type of mitigation recommended for segments of the roadway. The findings of this evaluation are to be used by the team to develop strategies and methods to avoid and minimize geologic hazards and to design rockfall mitigation measures. This report provides a summary of the findings of our additional field evaluation and estimated order-of-magnitude costs for recommended mitigations. Valley Road Evaluation Project 30 September 2022 Page 2 2 Scope of Work Our scope of work for this additional field assessment included conducting a drone LIDAR survey of the work area and conducting site reconnaissance to evaluate potential changes in conditions at the three sections (upper, central, and lower) identified during the Initial Evaluation. Our work also further identifies the nature and scope of mitigation recommended along the roadway corridor; identifies priority areas, such as areas where vegetation and slopes could be cut back, that could be addressed quickly to reduce risk; and recommends priorities for scheduling/phasing the mitigation. Our findings are detailed in this report. 3 Field Evaluation We conducted the additional field evaluation of the project alignment from May 16 through 20, 2022. The purpose of the evaluation was to further evaluate features and areas of geologic concern identified in our Initial Evaluation as well as to note changes in conditions and additional features of geologic concern. The roadway sections delineated in the Initial Evaluation were also assessed for geologic feature and mitigation considerations and were updated to generate revised section limits along the roadway. See Table 1 below. Limitations of the field work included constraints on visibility from vegetative obstructions and, due to the shear steepness of the site, limited access on both the upslope and downslope sides. In our Initial Evaluation report, the term “Section” referred to the Upper, Central, and Lower lengths of the roadway that were grouped together based on similar conditions. In this report, these groupings are referred to as the Upper, Central, and Lower Areas. The term “Section” is used to discuss subsections of the Upper, Central, and Lower Areas. The Sections discussed in this report are based on the 11 transects defined for use in the “Rockfall Hazard Rating System,” or RHRS assessment of the Initial Evaluation. The Stationing referenced herein is strictly a project stationing created for our geologic hazard analysis and does not correspond to formal County roadway stationing. Table 1. Revised Section Coverages with Stationing Section Area Start Station End Station Approx. Length (ft) 1 Upper 0+00 2+15 215 2 Upper 2+15 7+35 520 3 Central 7+35 11+50 415 4 Central 11+50 20+85 935 5 Lower 20+85 24+85 400 6 Lower 24+85 27+70 285 7 Lower 27+70 29+95 225 8 Lower 29+95 31+25 130 9 Lower 31+25 33+45 220 10 Lower 33+45 36+35 290 11 Lower 36+35 39+50 315 Valley Road Evaluation Project 30 September 2022 Page 3 4 Findings As discussed in our Initial Evaluation, along the Upper Area of the roadway, steep, exposed residual soil slopes are susceptible to instability, as indicated by past failures. Along the Central and Lower Areas of the roadway, rockfall hazards are present on the upslope side of the road and quantitative hazard ratings from RHRS scoring and RocFall modeling indicates mitigation for the hazard is warranted. We also discussed that there are several mitigation options that can help stabilize the road (upslope and downslope) and reduce the risk to vehicle and pedestrian travel from potential rockfall and slope instability. Our findings from our additional field evaluation are discussed below. UPSLOPE HAZARDS FEATURES Our Initial Evaluation of geologic hazards on the upslope side of the roadway found rockfall and failing masses of soil and vegetation to be the predominant geologic hazards to the roadway. To further evaluate the upslope geologic hazards along the roadway, nine unique geologic hazard feature types were observed and recorded by physical and relative location. The physical location of each feature was captured using a GPS device and mapped in Figures 3 through 13. The relative location for each feature is defined by the section containing the feature. We note that the accuracy of the GPS point and line features was limited due to poor satellite connectivity related to topographic and vegetative obstructions along the roadway. Thus, GPS feature locations shown on Figures 3 through 13 are approximate and not intended for survey or construction use. The nine upslope geologic hazard types are listed and defined in Table 2 below. Table 2 also includes the shorthand symbol assigned to the feature type used to label the features, as shown in Figures 3 through 13 as well as a reference to an example photo, which has been included in our Photo Log (Appendix A). A full list of the collected GPS points is included in Appendix B. Table 2. Upslope Geologic Hazard Feature Types Feature Type Feature Type Symbol Definition Example Photo (Feature ID) Corestone CS Variably sized, spherical blocks of differentially weathered basalt via spheroidal weathering, within weathered bedrock, or saprolite. Photo 1 (CS-01) Differential Erosion DE Increased rates of erosion due to lithologic occurrence of fractures, voids, pores, or similar properties, and leading to overhanging or undercutting conditions on the slope. Photo 2 (DE-02) Overhang OH An overhanging feature such as a root mat or undercut block of rock. Photo 3 (OH-01) Rock Package RP A discernable group of rocks that has similar composition, weathering patterns or joints, with dilated jointing and translation along joints. These groups of rocks generally pose a greater risk of failure than the surrounding rocks of an outcrops. Photo 4 (RP-36) Root Wedging RW Exacerbation of joints by the infiltration of growing roots. Photo 5 (RW-01) Valley Road Evaluation Project 30 September 2022 Page 4 Table 2. Upslope Geologic Hazard Feature Types Feature Type Feature Type Symbol Definition Example Photo (Feature ID) Scallop SC A mass of soil and rock that remains on the slope face after erosion of surrounding material. Photo 6 (SC-02) Tree Tree Trees growing on the crest of, or in the face of, the roadcut or outcrop. Photo 7 (Tree-02) Upslope Gully UG An observable topographic relief and debris chute caused by surface runoff, possibly exacerbated by constructed water control features such as swales. Photo 8 (UG-05) Upslope Rock Source RS An upslope outcrop of rock that can be visibly seen from the road and has the potential of shedding rock down slope. Photo 9 (RS-04) DOWNSLOPE HAZARD FEATURES Our evaluation of geologic hazards on the downslope side of the roadway found gullies to be the predominant hazard to the corridor. These gullies display both head and side wall scarps and are vegetated with young growth. Surface water runoff was not observed during the investigation; however, given the proximity of the gullies to swales constructed along the roadway, it is likely that the diverting of surface water is adding to gully formation. To further evaluate the downslope landslide hazards along the roadway, unique geologic hazard feature types were observed and recorded by physical and relative location. The physical location of each feature was captured using a GPS device and mapped in Figures 3 through 13. The relative location for each feature is defined by the section containing the feature. The scope of our evaluation for the downslope hazard features was limited to what was visible from the roadway and does not consider a remediation for these hazards. The downslope geologic hazard is listed and defined in Table 3 below. Table 3 also includes the shorthand symbol assigned to the feature type used to label the features, as shown in Figures 3 through 13, as well as a reference to an example photo, which has been included in our Photo Log (Appendix A). A full list of the collected GPS points is included in Appendix B. Table 3. Downslope Geologic Hazard Feature Types Feature Type Feature Type Symbol Definition Example Photo (Feature ID) Downslope Gully DG An observable topographic relief and debris chute caused by surface runoff, possibly exacerbated by constructed water control features such as swales. Photo 10 (DG-10) GEOLOGIC HAZARDS SUMMARY To summarize the upslope and downslope geologic hazard features, Table 4 provides counts of the 10 observed feature types and a total geologic hazard features count by section. For a full list of individual features by section, see Appendix C. Valley Road Evaluation Project 30 September 2022 Page 5 For Section 1, none of the geologic hazard features above were identified due to heavy vegetation. However, the slope is a mixed soil and rock slope and signs of rockfall and soil slope failure were observed along the roadway and the toe of the slope, indicating hazards are likely present. Table 4. Counts of Observed Geologic Hazard Feature Types by Section Section Corestone Differential Erosion Downslope Gully Overhang Rock Package Root Wedging Scallop Tree Upslope Gully Upslope Rock Total Hazard Features 1 0 0 0 0 0 0 0 0 0 0 0 2 4 0 3 2 0 0 5 3 0 0 17 3 0 0 0 3 2 0 1 3 0 0 9 4 0 0 1 3 13 0 0 4 0 0 21 5 0 2 1 1 5 0 0 2 1 0 12 6 0 5 2 0 3 2 0 1 2 1 16 7 0 0 0 0 3 0 0 1 0 0 4 8 0 2 0 0 0 0 0 3 1 2 8 9 0 2 2 0 2 0 0 1 0 1 8 10 0 0 1 0 6 0 0 6 2 0 15 11 0 0 2 1 3 2 0 3 1 0 12 Total 4 11 12 10 37 4 6 27 7 4 122 OTHER FEATURES AND CONSIDERATIONS During our evaluation, we noted additional features other than those specifically related to upslope and downslope geologic hazards along the roadway. These are briefly summarized in Table 5 below. Table 5 also includes the shorthand symbol assigned to the feature type used to label the features, as shown in Figures 3 through 13, as well as a reference to an example photo, which has been included in our Photo Log (Appendix A). A full list of the collected GPS points is included in Appendix B. Table 5. Other Feature Types Feature Type Feature Type Symbol Description Example Photo (Feature ID) Boulder Boulder A large boulder on the downslope shoulder located in Section 3, approximately 19 feet up the road from TP-05. Photo 11 (Boulder-01) Culvert Culvert A culvert located in Section 1 along stream leading to Kaluahine Falls. Photo 12 (Culvert-01) Headwall Headwall Three headwalls were observed in our field evaluation. The walls generally appear to be stabilizing the roadcut slope. Photo 13 (Headwall-03) Valley Road Evaluation Project 30 September 2022 Page 6 Headwall 03 appears to have been constructed along with other roadway improvements, including concrete paving and a cut or trimmed roadcut outcrop face. Telephone Pole TP Telephone poles are installed on the downslope shoulder along the roadway. Telephone Pole 08 was observed to be leaning in the downslope direction. Photo 14 (TP-08) Swale SW A constructed berm in the pavement that appears to, or was intended to, divert surface water to a specific location. Photo 15 (SW-03) 5 Sections Summaries The section summaries follow the roadway from the top of the road, at the ranger station, down to the valley floor at the beach access road. A note for each section has been added on the RHRS score calculated in our Initial Evaluation. Among the 10 parameters used in the RHRS evaluation, the following roadway conditions are worth reiterating: (1) along the entire road there is no ditch catchment for rocks (although occasional drainage swales are present), (2) the roadway width ranges from 11 to 29 feet, and (3) the sight distance for most of the road is limited. The grade of the road varies between each section and is calculated for each section. Each hazard feature has a unique failure mechanism that may act individually or in combination with other hazards. While some hazards may be more likely to harm roadway users, the identified hazards all pose a risk to the roadway and traveling public and could cause failure at any time. Due to their unpredictability, a relative ranking of hazards is not appropriate or useful and our report does not rank individual hazards by risk. Instead, to provide a measure of “hazard density” that estimates the relative risk between sections, we have calculated the Hazard to Length Ratio (H:L) for each section. This ratio was multiplied by 100 and rounded to generate whole number values for easier comparison. The ratio is used as one of the factors for prioritization of sections. SECTION 1 Section 1 is in the Upper Area outlined in the Initial Evaluation and is immediately down the roadway from the ranger station. The alignment of the road includes a sharp curve as the road pushes up against the slope face. Along the 215-foot length of the road, the elevation changes from ~886 feet to ~864 feet above mean sea level (MSL), generally yielding a 10% grade. While no hazards were mapped within Section 1, there is a noted sloughing of soil along the embankment between Station 0+00 and Station 2+15. The heavy vegetation obscures much of the potential sloughing but evidence of outwash and small cobbles is present along the side of the road. Table 6 summarizes the basic details of Section 1. Table 6. Section 1 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Upper Area 1 Upper 0+00 2+15 215 0* - 375 * Hazards may be obscured by dense vegetation Valley Road Evaluation Project 30 September 2022 Page 7 SECTION 2 Section 2 is in the Upper Area outlined in our Initial Evaluation and is a broadly curving section of the road. Along the 520-foot length of the section, the elevation changes from ~864 feet to ~748 feet MSL, generally yielding a 22% grade. Within Section 2, a thick layer of saprolite (rock that has weathered to soil) has formed atop the basalt bedrock. The failure of the saprolite has led to “scallops” of undermined material remaining on the face of the slope and overhanging root mats of large trees that protrude out several feet in some cases. Exposed corestones were observed in the face of the upslope in this section with boulders up to 8 feet in their longest dimension. Along the downslope side of the road, an ephemeral stream, which leads to Kaluahine Falls, continues to erode a gully that extends beyond the scope of this investigation. The potential for large-scale landsliding (global instability) along of Section 2 has not been evaluated; however, the conditions observed in the field indicate that the surficial sloughing may have deeper-seated failure planes. These deep-seated landslide-type failures typically do not represent an immediate hazard and their evaluation was generally beyond the scope of this work. Future evaluation of these features may be easier after initial mitigation and clearing work is completed. To avoid inducing a large-scale failure, any excavation in this area must be limited to removal of surficial material. We noted a significant downslope gully (DG-10), which appeared to be a shallow landslide, located down-road from swale SW-12. Table 7 summarizes the basic details of Section 2. Table 7. Section 2 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Upper Area Upper 2+15 7+35 520 17 3 375 SECTION 3 Section 3 is in the Central Area outlined in our Initial Evaluation. The alignment of the road in this section is straight and, along the 415-foot length of the road, the elevation changes from ~748 feet to ~662 feet MSL, generally yielding a 21% grade. Within Section 3, the saprolite becomes less prevalent, and more competent rock begins to outcrop around Station 11+50. As such, the scallops of saprolite are less common but discrete zones of rock packages emerge as the most common geologic hazard. Overhanging trees and their root mats are a hazard throughout Section 3. Table 8 summarizes the basic details of Section 3. Table 8. Section 3 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Central Area 3 Central 7+35 11+50 415 9 2 327 Valley Road Evaluation Project 30 September 2022 Page 8 SECTION 4 Section 4 is in the Central Area containing the 2019 downslope landslide feature discussed in our Initial Evaluation. Section 4 is the longest section. The alignment of the road is a straight corridor and along the 935-foot length of this section, the elevation changes from ~662 feet to ~428 feet MSL, generally yielding a 25% grade. Within Section 4, trees and overhanging root mats persist but the dominant hazards are the rock packages stemming from the variations in lava flows, mainly arising from ‘a’ and associated clinker layers. As an example of the combined effects, near Station 13+85 a bench has formed around a tree causing root wedging, and a void has formed below Tree-08. Along the downslope side of the road, a gully is forming near Station 15+00 but is difficult to ascertain from the topographic contours generated in the LiDAR drone survey. Table 9 summarizes the basic details of Section 4. Table 9. Section 4 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Central Area 4 Central 11+50 20+85 935 21 2 327 SECTION 5 Section 5 is in the Lower Area outlined in our Initial Evaluation. The alignment of this 400-foot section of road is broadly curving, forming somewhat of an open “z” shape. The elevation changes from ~428 feet to ~346 feet MSL, generally yielding a 21% grade. Within Section 5, the loose packages of highly fractured rock continue and differential erosion of the weaker ‘a’ competent rock of the flows. Typical of this differential erosion, near Station 21+30, clinker was observed weathering out as differential erosion, DE-01. Two discernable gullies have formed, extending from the upslope to the downslope sides of the road. However, these features are not well detailed in the topographic contours generated in the LiDAR drone survey. Table 10 summarizes the basic details of Section 5. Table 10. Section 5 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Lower Area 5 Lower 20+85 24+85 400 12 3 381 Valley Road Evaluation Project 30 September 2022 Page 9 SECTION 6 Section 6 is in the Lower Area outlined in our Initial Evaluation, and along this 285-foot section of broadly curving road, the elevation changes from ~346 feet to ~280 feet MSL, generally yielding a 23% grade. Within Section 6, the combined effects of differential erosion, root wedging and rock packages continue to pose hazards along the road. Extensive root systems are present at Tree-13, creating a “web”, and exemplifying the ability of roots to infiltrate rock fractures. An area of fracture-bound rock, RP-23, extends several feet along the crest of the slope and displays signs of recent rockfall. Also, within Section 6, two observable upslope rock sources, RS-01, were visible from the roadway. A range finder was used to measure the distance from the downslope edge of pavement (EOP) to these outcrops, and as a rough measurement, they were found to up ~35 feet and ~60 feet from EOP. Section 6 also contains a headwall structure, Headwall-03, on the downslope side near Station 24+95. This structure appears to have been constructed in conjunction with other roadway improvements, but the engineering properties or purpose were not discernable from the field. Table 11 summarizes the basic details of Section 6. Table 11. Section 6 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Lower Area 6 Lower 24+85 27+70 285 16 6 381 SECTION 7 Section 7 is in the Lower Area outlined in our Initial Evaluation. Along this 225-foot section of roadway, a single tight curve at Station 29+00 separates a steeper gradient from a gentler gradient down-slope of the station. The total elevation along Section 7 changes from ~280 feet to ~250 feet MSL, generally yielding a 13% grade. Section 7 continues to see the hazard of rock packages, especially along the crest of the slope. Section 7 also contains a headwall feature, Headwall-02, near Station 29+25. Again, the intent of this structure could not be determined from the field work. Table 12 summarizes the basic details of Section 7. Table 12. Section 7 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Lower Area 7 Lower 27+70 29+95 225 4 2 381 Valley Road Evaluation Project 30 September 2022 Page 10 SECTION 8 Section 8 is the shortest section in the Lower Area outlined in our Initial Evaluation. Along the 130-foot length of straight road the elevation changes form ~250 feet to ~218 feet MSL, generally yielding a 25% grade. A surface water flow path, forming upslope and downslope gullies, was noted as an erosional feature undercutting the roadway and the crest of the slope. These gullies are visible in the topographic contours, generated from the LiDAR drone survey data, as the “v” shape of the topographic contours near UG-04 and DG-05. Within Section 8 extensive root structures exacerbate differential erosion with notable voids forming as seen near DE-07. Table 13 summarizes the basic details of Section 8. Table 13. Section 8 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Lower Area 8 Lower 29+95 31+25 130 8 6 381 SECTION 9 Section 9 is in the Lower Area outlined in our Initial Evaluation. In this 220-foot length of curving road the elevation changes from ~218 feet to ~169 feet MSL, generally yielding a 22% grade. Within Section 9, two downslope erosional gullies were noted but no upslope flow path could be attributed to these features. The topographic contours generated from the LiDAR drone survey data vaguely indicate these features. Although we did not observe water flowing in this area, surface water being diverted from the constructed swales may be contributing to these features. Large boulders stemming from a rock source ~80 feet upslope from EOP, RS-04, were observed in the talus of the upslope, and a 10-inch rock was noted lodged in a tree near Tree-18. The main hazards along the slope face of Section 9 are the differential erosion and formation of rock packages. Table 14 summarizes the basic details of Section 9. Table 14. Section 9 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Lower Area 9 Lower 31+25 33+45 220 8 4 381 SECTION 10 Section 10 is in the Lower Area outlined in our Initial Evaluation and is a straight-broadly curving section of roadway. Along the 290-foot length of road, the elevation changes from ~169 feet to ~101 feet MSL, generally yielding a 23% grade. Two upslope erosional gullies and a single downslope gully were noted in Section 10, and the topographic contours, generated from the LiDAR drone survey data, highlight the paths of water flowing from upslope for UG-03, DG-03, and UG-02. The hazards along the slope face in Section 10 are columnar rock packages with minor differential erosion along the crest, exacerbated by heavy tree coverage with extensive root systems. A downed tree, Tree-22, was noted as being a recent fall in UG-02. A resident passing through at the end of the day confirmed that this tree had fallen the Valley Road Evaluation Project 30 September 2022 Page 11 morning of 18 May 2022, and that he had moved the fallen tree to the side of the road. Table 15 summarizes the basic details of Section 10. Table 15. Section 10 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Lower Area 10 Lower 33+45 36+35 290 15 5 381 SECTION 11 Section 11 is in the Lower Area outlined in our Initial Evaluation and is the final section of the road that was evaluated for hazards. The roadway is another straight-broadly recurving section of the roadway. Along the 315-foot length of road, the elevation changes from ~101 feet to ~38 feet MSL, generally yielding a 20% grade. Two downslope erosional gullies were observed, but like Section 9, no upslope features were attributed to their formation. Again, the diverting of over wash by the constructed swales may be contributing to DG-01 and DG-02. An upslope erosional gully, UG-01, was observed at the end of Section 11 but given the intersection of the valley road with the beach access road and the low elevation, no associated down slope erosional feature was observed. The hazards along the slope face in Section 11 stem from heavy tree cover and extensive root systems that are inducing root wedging in rock packages. A slumping root mat was also noted at Tree-26, forming an overhanging feature. Table 16 summarizes the basic details of Section 11. Table 16. Section 11 Data Summary Section Area Start Station End Station Length (ft) Hazard Count Hazard-Length Ratio (H:L)*100 RHRS Score Lower Area 11 Lower 36+35 39+50 315 12 4 381 6 Schema for Section Prioritization and a Phased Approach for Mitigation The prioritization of sections is based on several factors, with the main factor being the presence of geologic hazards in each section, as identified in Table 4. However, because of the variability between the hazards (e.g., hazard type, size, etc.) and the unpredictability of hazards occurring individually or in combination with others, a simple ratio of the number of mapped hazards in a section to the section’s length (the H:L ratio) was used as a normalization factor to prioritize sections. Sections with higher Hazard to Length Ratios have more hazards per linear foot of roadway than do sections with lower ratios. The second factor for prioritization includes a level of professional judgement based on field observations and the geometry of the road itself. Valley Road is steeply graded and narrow, with sharp curves winding down into the Valley. The steep grade and condition of the pavement necessitates the use of 4-wheel drive vehicles and slow travel speeds. The combined effect of this situation is a prolonged exposure to hazards from the upslope face with minimal distance separating the Waipi o Valley Road Evaluation Project 30 September 2022 Page 12 travelers and the slope face.Curved sections of the road will be pinch points for traffic and increase the exposure to hazards. Lastly,prioritization of sections also considers the cost and feasibility of construction of remedial measures.To minimize the impact to the public,the level of effort to construct mitigations and the time expected to undertake the construction must be considered. Based on the above factors and as requested by the County,we developed a phased mitigation approach.Table 17 below highlights mitigation of sections based on a prioritized multi phased construction approach to addressing the numerous hazards along the roadway.The phases were established based on the factors for the prioritization schema to facilitate the quick response sought by the County.This approach would first address areas that may not require a specialty contractor for construction,followed by phases of construction that will require prolonged road closures and specialty construction to mitigate the higher risk features.Specifications and provisions for the appropriate qualifications of a contractor will be included in the design package. Phase 1:This phase would include the mechanical excavation of scallop features within the saprolitic material,minor rock packages,root mats,tree removal,and general vegetation clearing within Sections 1 and 2.This work can best be described as hazards removal/excavation and is intended to address areas that pose less risk than others and require less time to conduct the mitigation.Where feasible,the County should also clean out and re establish surface drainage features,such as roadside ditches and diversion berms,so that water is not directed in an uncontrolled manner over slopes. Phase 2:This phase would consist of mitigation of the slope faces,including scaling loose debris and rock packages,and the installation of draped mesh.Scaling is expected to be undertaken across the entire slope face and will likely extend upslope as deemed necessary for the safety of construction crews.However,it is preferred to limit upslope disturbance beyond the immediate slope face adjacent to the roadway,as any disturbance may increase the limits of mesh installation or necessitate the need for other remediation such as dowel installation,shotcrete,or additional barriers. As the mitigation style for hazards in Phase 2 varies depending on the co occurrence of hazards,a further prioritization of sections in this phase was required.At this point,the Hazard to Length Ratio was added to the consideration for level of effort during construction and judgement based on the subject matter experts’field observations to group sections of higher concern into subphases 2A through 2D, ranked from highest priority to lowest priority,respectively. Subphase 2A includes Sections 7,8,and 9 and will focus on scaling rock packages and erosional features exacerbated by root wedging,as well as installation of a draped mesh to contain further rockfall and sloughing overburden from reaching the road. Subphase 2B includes Sections 10 and 11 and will focus on scaling columns of rock packages and removal of extensive root structures and any rock attached,especially along the crest of the slope face.Tree removal will uncover new packages of loose rock,which will also need to be scaled.Installation of draped mesh to avoid excessive upslope disturbance is expected for much of Section 10 and into Section 11. Valley Road Evaluation Project 30 September 2022 Page 13 Subphase 2C includes Sections 5 and 6 and will focus on scaling highly fractured rock packages along the crest of the slope and addressing the effects of differential erosion stemming from the variation in lava flows. Removal of trees causing extensive root jacking will dislodge additional rocks, which will need to be removed with minimal upslope disturbance. A rockfall attenuation fence is proposed to be installed in Section 6 (in Phase 3) and may necessitate the need to extend the mesh further down station to approximately Station 27+50. Subphase 2D includes Sections 3 and 4 and will focus on the removal of saprolitic material that was unable to be removed in Phase 1. The transition from saprolite to competent rock in Section 3 is expected to require light scaling to avoid the creation of undermined slope conditions. Overhang removal will need to limit disturbance to the upper slope and the scaling of differentially eroded rock packages will need to be light to not create any further undermined areas. It is important to note that the limits for mesh installation are approximate and will be refined during final design. For this reason, Figures 14 through 24, Mitigation Features, are not strictly intended to approximate limits of installation but rather to identify the general area of coverage for the slope face in developing an estimate for cost of installation. Phase 3: This phase includes the installation of rockfall impact fence systems in Sections 6, 8, and 9. The fences are intended to prevent rockfall from the observed upslope rock sources from reaching the roadway. Installation of the fences during this phase are broken out as a separate phase as a time consideration for prolonged construction. The approximate delineation of the impact fences is marked in Figures 19, 21, and 22. As access to the upper slope is expected to be difficult, this phase of construction is more intensive than the other Phases. However, the sections requiring impact fence systems will also be worked on in Phase 2, thus Phase 3 may be combined with the work of Phase 2 to save on mobilization costs, should the County wish to do so. Furthermore, the recommended limits of impact fences may be refined during the Phase 2 work based on conditions exposed during vegetation clearing and grubbing, as well as rock scaling. In general, all construction operations should be completed under the direction of an engineer or geologist with professional experience in rockfall and slope hazard remediation. Tree removal including root systems and overburden along the crest of the slope should be addressed at the beginning of each construction phase. Valley Road Evaluation Project 30 September 2022 Page 14 7 Mitigation Phasing Summary Based on our evaluation, multiple geologic hazards are present along the Valley Road study area that pose risk to the traveling public. We have classified the road into differing geologic hazard sections and summarized likely mitigation scopes and costs for these areas. A three-phase approach for the remediation of these hazards is proposed based on a prioritization of sections and the desire to remediate the more easily constructed Sections followed by Sections prioritized by highest hazard risk. The remediation approaches vary between each phase but are expected to include excavation of surficial soil and rock, hand scaling of loose rock and saprolitic material, installation of draped mesh systems to retain rock falling from the face of the slope, and a series of rockfall impact fences intended to stop rockfalls stemming from upslope rock sources. Table 17 provides a summary of the proposed phases and scopes of mitigation work along the roadway. Table 17. Mitigation Phasing Summary Construction Mitigation Phase Section(s)/ Subgroups Mitigation Type(s) Area of Slope Addressed Description of Work Estimated Duration1 Phase 1 – General Excavation 1, 2 Hazards Removal by Excavation Saprolitic areas along Slope Face Remove scallops, loose material, trim root mats, and cut trees 5 Weeks Phase 2 – Rock Stabilization 2A - 7, 8, 9 2B - 10, 11 2C - 5, 6 2D -3, 4 Hazards Removal by Rock Scaling & Installation of Draped Mesh Slope Face and Crest Scale loose Rock Packages and install draped mesh as needed 57 Weeks Phase 3 – Rockfall Attenuation 6, 8, 9 Rockfall Attenuator Fence Systems Upslope Rock Source Areas Install rockfall impact fence systems 48 Weeks 1 The Estimated Durations only includes active construction and does not include support activities such as materials acquisition, mobilization, demobilization, etc. In addition to the work outlined in Table 17, rock dowel installation may be utilized as a precaution if construction destabilizes an area not able to be remediated by scaling or mesh alone. The specifications and design of the dowels will be based on observed rock sizes and models of rockfall in the design phase. Design of the draped mesh and impact fence systems will require further calculations and modeling to establish limits of absorption. Proprietary design of mesh systems varies between each manufacturer and a final design for material properties will be based on criteria provided by us, although will require a stamped design from the contractor’s engineer. Valley Road Evaluation Project 30 September 2022 Page 15 8 Schedule and Duration The County has requested estimated durations for the proposed phases and subphases. The durations by section were estimated using the approximated section mitigation lengths and coverages, and then were compared to similar types of recent local Haley & Aldrich projects. The estimated durations have been provided in weeks and include only active construction and do not include support activities such as materials acquisition, mobilization, demobilization, etc. Table 17 above provides a summary of the estimated duration of each Phase of work, and Table 18 below provides an estimated duration in weeks for by each phase, subphase, and section. Table 18. Estimated Minimum Durations in Weeks Phase Subphase Section(s) Estimated Minimum Duration1 (Weeks) Phase 1 1 1 1 Phase 1 1 2 4 Phase 1 Subtotal 5 Phase 2 2A 7 6 Phase 2 2A 8 6 Phase 2 2A 9 6 Phase 2 2B 10 6 Phase 2 2B 11 6 Phase 2 2C 5 6 Phase 2 2C 6 6 Phase 2 2D 3 3 Phase 2 2D 4 4 Phase 2 Subtotal 49 Phase 3 3 6 19 Phase 3 3 8 16 Phase 3 3 9 13 Phase 3 Subtotal 48 1 The Estimated Durations include only active construction and does not include support activities such as materials acquisition, mobilization, demobilization, permitting, etc. Valley Road Evaluation Project 30 September 2022 Page 16 9 Cost Estimates To estimate mitigation costs where sufficient information was available, we considered typical mitigation methods for each hazard and what the most likely method would be at each section. We concluded that the following methods of mitigation would most likely be required to address the identified hazard areas. MECHANICAL EXCAVATION As discussed in our Initial Evaluation, mechanical excavation of the slope would remove the loose rock, soil, and overhanging trees posing a risk above or adjacent to the roadway. The soil and rock mass adjacent to the roadway can be removed by using conventional excavating equipment if the rock mass is highly weathered and “rippable.” This type of work is highly invasive and has the potential to create larger issues if care is not taken. Unit prices of $2 to $5 per square foot were used in our cost estimates. ROCK SCALING As discussed in our Initial Evaluation, rock scaling is the procedure of removing loose rocks from the hillside and cliff face. Scaling is not considered a permanent mitigation and would typically need to be conducted every 5 to 10 years to maintain its effectiveness, dependent on the site. Scaling should not be considered as reliable as structural methods since there is typically some subjectivity in selecting which rocks to remove. In addition, it is not always apparent what rocks are likely to fail within a specific period. Scaling can be conducted mechanically if equipment can safely reach the specific rock areas from the roadway (e.g., overhangs directly adjacent to the road), though scaling is often done by hand by workers rappelling down the cliff face and prying rocks loose. Unit prices of $6 to $13 per square foot were used in our cost estimates. DRAPERY NETTING As discussed in our Initial Evaluation, rockfall drapery netting consists of high strength steel fabric, laid over the slope/source area and connected to the slope by cables and rock bolts that are usually installed along the top of the cliff. Generally, a fallout area is included in the design and the netting placed to allow rocks to drop behind the netting into the fallout area at the base of the cliff/source. This allows for maintenance/removal of rocks as needed and maintains the useful life of the netting. Rockfall netting is designed based on rock size, slope gradient, and area covered. Netting is selected that can control rocks of the size expected to be generated from the specific site. The netting and anchorage must also be of sufficient strength to support the weight of rocks that might lodge between the slope and netting, along with its own weight, a function of the slope gradient, as well as the dimensions of the area netted. Since netting is typically more expensive than fencing and more difficult to install, netting is typically used only where site conditions do not provide sufficient room for fence installation, such as along narrow stretches of the Lower Section of Waipi‘o Valley Road. Drapery netting is the most economical measure where an adequate ditch is already located at the base of the slope, so drapery netting was selected for such locations. If there is no ditch, a ditch may be constructed where there is adequate shoulder space or routine monitoring and maintenance would Valley Road Evaluation Project 30 September 2022 Page 17 need to be performed. Unit prices of $8 to $20 per square foot were used in our cost estimates. A conceptual design detail for Drapery Netting is shown on Figure 25. ROCKFALL IMPACT FENCE As discussed in our Initial Evaluation, rockfall fences consist of high-strength fences installed at the toe of a slope to “catch” falling rocks. The fences are manufactured from steel components that have built-in energy dissipation/absorption capabilities. Typically, steel rings and sacrificial components are integrated into the fencing, which deform elastically and then plastically to stop rocks that impact the fence. The fences are generally constructed of posts that are connected to concrete footings or placed into concrete filled holes (where rock is present at the surface). The posts are guyed together laterally, and often in the upslope direction with steel cables. High-strength steel fabric runs between the posts and is the primary element that the rock impacts. The rock energy is transferred to the fabric, which transfers it to the posts, cables, and ground anchors/foundations. Some energy is also dissipated by plastic deformation of the rockfall fence components. Rockfall fencing is designed based on three main characteristics: rock impact energy, rock bounce height, and site soil conditions. Rock impact energy and bounce height were estimated from the computer program RocFall, as noted in Section 4.3 of the Initial Evaluation. Foundation conditions were not determined under the scope of this report but would be determined as part of additional work if fencing is selected as a mitigation strategy. Additionally, precise fence locations and lengths will need to be determined in the design phase, which may affect the estimated lengths provided in this cost estimate. Unit prices of $800 to $4,500 per linear foot were used in our cost estimates. A conceptual design detail for a Rockfall Impact Fence is shown on Figure 25. ROCK BOLTING As discussed in our Initial Evaluation, localized stabilization methods target rockfall source zones and include rock dowels, cable lashing, shotcrete, and anchored netting systems. Rock dowels are fully grouted steel bars that are not post-tensioned and secure specific unstable rock blocks. Cable lashing systems typically use wire rope to stabilize rock blocks that cannot be doweled. Shotcrete (concrete propelled by a nozzle) can stabilize shear zones or highly weathered and fractured rock masses and are often paired with dowels or anchors. Anchored netting with erosion control matting, which is secured by boundary cables, cable anchors and patterned or targeted soil nails/rock dowels, can be used on combination soil and rock slopes or larger fractured rock masses. These methods would likely be used in conjunction with other mitigation methods. Individual rock bolting, lashing or other measures may be necessary in lieu of or to supplement netting, but determining the need for such measures would require additional consideration. Unit prices of $5,000 to $6,500 each would be anticipated, but cost estimates could not be developed for these measures at this conceptual stage and were not included in the cost estimates matrix below. Provisions for rock bolting, lashing, or other measures for incidental rock stabilization will be considered in the project plans and specifications. Waipi o Valley Road Evaluation Project 30 September 2022 Page 18 OTHER NON GEOLOGIC ROADWAY IMPROVEMENTS Surface drainage improvements and road realignment costs are not included in the cost estimates below; however, the County may want to consider additional non geologic roadway improvements, such as, widening, striping, grade changes, guardrails, vertical and horizontal alignment changes. SUMMARY OF COSTS Appendix D details the estimated costs for rockfall mitigation. Mitigation costs for other hazards could not be characterized sufficiently to allow for a reasonable estimation of costs at this conceptual stage. We appreciate the opportunity to support the County of Hawai’i on the Waipi o Valley Road project. Please contact us if you have any questions. Sincerely yours, HALEY & ALDRICH, INC. Christopher M. Eddy Technical Specialist Daniel Trisler, P.E. Principal Geotechnical Engineer Attachments: Figure 1 – Project Locus Figure 2 – Site Plan Figures 3 through 13 – Sections Figures – Site Features Figures 14 through 24 – Sections Figures – Mitigation Features Figure 25 – Conceptual Details Appendix A – Photo Log AppendixB–GPSFieldData Appendix C – Features Data by Section Appendix D – Rockfall Mitigation Measures and Estimated Costs by Section \\haleyaldrich.com\share\pdx_data\Notebooks\0203303 001_Waipio_Valley_Geotechnical_Design\Deliverables\Reports\Waipio Valley Road Phase 1 Final\2022_0930_HAI_Waipio Valley Road Phase 1_F.docx Daniel Trisler,P.E. FIGURES SITE 155°35'0"W155°36'0"W155°37'0"W155°38'0"W 20°8'0"N 20°7'0"N 20°6'0"N 20°5'0"N 20°4'0"N GIS: \\haleyaldrich.com\share\pdx_data\Notebooks\0203303-001_Waipio_Valley_Geotechnical_Design\GIS\Maps\2022_07\203303_001_0001_PROJECT_LOCUS.mxd - khaskins - 7/1/2022 2:31:57 PMMAP SOURCE: ESRISITE COORDINATES: 20°06'54"N, 155°35'29"W WAIPIO VALLEY ROAD EVALUATIONHONOKAA, HAWAII PROJECT LOCUS FIGURE 1APPROXIMATE SCALE: 1 IN = 4000 FT 2022 BASE MAP SERVICES Ideal scales forsite vincity figures 1 : 108,000Scale bar = 4 miles 1 : 54,000Scale bar = 2 miles 1 : 24,000 (default) 1 : 13,500Scale bar = 0.5 mile HI 500 550600650700750 800 850 900 50 150 200 250 300 350 400 300 350 400450 500 550600650700[][][] [][] [] [][] [] [][][][][][][][][][][][][] SET M AG N A IL 466,41 6 .0 8 N OR TH 1,611, 5 39 . 08 EA STELEV.=8 81 . 25 E E E E 0+00 1+002+003+004 + 0 0 5+0 0 6+00 7+00 8+00 9+00 10+0 0 11+0 0 12+0 0 13+0 0 14+0 0 15+0 0 16+00 17+00 18+0 0 19+0 0 20+0 0 21+0022+0023+00 24+0025+0 0 26+00 27+0028+0 0 29+00 30+0 0 31+00 32+0033+00 34+0035+0036+0 0 37+00 38+0 0 39+0039+67.54 FIGURE 13 FIGURE 12 FIGURE 11 FIGURE 10 FIGURE 7 FIGURE 6 FIGURE 5 FIGURE 4 FIGURE 3 FIGURE 9 FIGURE 8 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0002_SITE_PLAN.DWGSLIVNYAK, OLEG00029/30/2022 4:38 PMLayout:Printed:FIGURE 2 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SITE PLAN SCALE: AS SHOWN SEPTEMBER 2022 0 150 300 450 600 SCALE IN FEET LEGEND EDGE OF ROAD GUARD RAIL 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR NOTES 1.ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2.DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3.SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. [] 870 880 89 0 900 910 920 860 870 880 890 900 840 850 860 87 0 880 890 900 840850860870870880[][][][][][][][][][][][][][][][][][][][][][][][][][][] [][][][][][] [] [] [][][][][][][][]SET MAG NAIL 466,416.08 NORTH 1,611,539.08 EAST ELEV.=881.25 STATION=0+00.00 OFFSET=0.00 NORTHING=466437.15 EASTING=1611567.73 SECTION-01 START SECTION-01 END 0+ 0 0 0+50 1+00 1+50 2 + 0 0 2+50 3+00 3+50 STATION=0+32.23 OFFSET=9.54R NORTHING=466416.08 EASTING=1611539.08 UTILITY POLE, TYP. GUARD RAIL, TYP. EDGE OF ROAD, TYP. S02U SW-14 TP-1 GC-1 SW-15 Culvert-Outlet Culvert-InletS01L S01U CS-1 CS-2 OH-1 STATION=2+15.00 OFFSET=0.00 NORTHING=466246.78 EASTING=1611509.29 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-019/30/2022 4:38 PMLayout:Printed:FIGURE 3 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION1 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE [] MATCHLINE - SEE SHEET 4 87088089090091092086087088089090084 0850860870880890900840 850 860 870 870 880 7207307407507 6 0770780790800810820830840850860870880890900 770 770 780 780 790 790 800 800 810 810 820 820 830 840 850 860 870 880 890 900 910 [][][][][][][ ][][][][][][ ][][][][][][][][][][][][]SET MAG NAIL466,416.08 NORTH1,611,539.08 EASTELEV.=881.25SC-4 0+000+501+001+502+002+503+003+ 5 0 4+00 4+50 5+00 5+50 6+00 6+507+007+508+008+50SECTION-02 START SECTION-02 END GUARD RAIL, TYP. STATION=2+15.92 OFFSET=0.00 NORTHING=466247.20 EASTING=1611508.47 EDGE OF ROAD, TYP. S02U CS-3 TP-3 SW-12 TP-2 SW-11 SW-13 DG-10 DG-11 DG-12 SW-14 TP-1 GC-1 SW-15 Culvert-Outlet Culvert-Inlet S01L S01U S02L CS-1 CS-2 SC-1 CS-4 Tree-1 Tree-2 Tree-3 S03U SC-6 Tree-4 Tree-5 Tree-6 OH-3RP-1 OH-2 SC-5SC-4 SC-3SC-2 OH-1 STATION=7+35.00 OFFSET=0.00 NORTHING=466426.33 EASTING=1611132.67 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-029/30/2022 4:38 PMLayout:Printed:FIGURE 4 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION2 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 20 40 60 80 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 3 MATCHLINE - SEE SHEET 5 600 610 620 630 640 650 660 670 680 690 70 0 71 0 72 0 730 740 750 760 770 780 790 800 810 820 830 840 850 640 650 660 670 680 690 720 730 740 750 760770 78 0 79 0 80 0 810 820 830 6+00 6+ 5 0 7+ 0 0 7+ 5 0 8+ 0 0 8+ 5 0 9+ 0 0 9+5 0 10+ 0 0 10+ 5 0 11+ 0 0 11 + 5 0 12 + 0 0 SECTION-03 END EDGE OF ROAD, TYP. UTILITY POLE, TYP. SET MAG NAIL STATION=11+16.15 OFFSET=7.02R NORTHING=466233.63 EASTING=1610803.31 TP-5 Boulder GC-2 SW-9 TP-4 SW-10 TP-3 SW-12 SW-11 DG-10 S02L Tree-1 Tree-2 Tree-3 S03U SC-6 Tree-4 Tree-5 Tree-6 RP-2 S03L S04U RP-3 RP-4 OH-6 OH-5 OH-4 OH-3 RP-1 OH-2 SC-5 STATION=7+35.00 OFFSET=0.00 NORTHING=466426.33 EASTING=1611132.67 SECTION-03 START STATION=11+50.00 OFFSET=0.00 NORTHING=466209.28 EASTING=1610781.27 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-039/30/2022 4:38 PMLayout:Printed:FIGURE 5 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION3 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 20 40 60 80 SCALE IN FEET LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. [] MATCHLINE - SEE SHEET 4 MATCHLINE - SEE SHEET 6 370 380 390 400 410 420 430 440 450 460470 480 490 500 510 520 530 540550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 400 410 42 0 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 560 570 580 590 600 610 620 630 640 65 0 660 670 680 690 700 710 720 730 740 750 [][][][][][]EEEEEEEEEEEEEEEEEEEEEE11+ 0 0 11 + 5 0 12 + 0 0 12+ 5 0 13+ 0 0 13+ 5 0 14+ 0 0 14+ 5 0 15 + 0 0 15 + 5 0 16 + 0 0 16+ 5 0 17+0 0 17+5 0 18+0 0 18+ 5 0 19 + 0 0 19 + 5 0 20+ 0 0 20+ 5 0 21+00 SET MAG NAIL SECTION-04 START SECTION-04 END EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. HIGH TENSION OVERHEAD WIRE STATION=11+16.15 OFFSET=7.02R NORTHING=466233.63 EASTING=1610803.31 STATION=20+84.54 OFFSET=0.30R NORTHING=465687.31 EASTING=1610011.35 DG-9 TP-9 SW-1 SW-2 SW-3 SW-4 TP-8 GC-3 SW-5 SW-6 TP-7 Tree-7 SW-7 TP-6 SW-8 TP-5 Boulder GC-2 SW-9 RP-14 S03L S04U RP-3 RP-5 RP-6 RP-7 RP-8 RP-9 Tree-8 Tree-9 RP-13 RP-15 Tree-10 S04L S05U RP-16 RP-12 OH-8 RP-11 RP-10 OH-7 RP-4 OH-6 OH-5 STATION=11+50.00 OFFSET=0.00 NORTHING=466209.28 EASTING=1610781.27 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-049/30/2022 4:38 PMLayout:Printed:FIGURE 6 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION4 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 30 60 90 120 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 5 MATCHLINE - SEE SHEET 7 30 0 310 3 3 0 3 4 0 3 5 0 3 6 0 37 0 240 250 260 27 0 28 0 300 31 0 330 34 0 35 0 36 0 3 7 0 3 8 0 390 40 0 410 42 0 430 440 450 46 0 300 310 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 48 0 49 0 500 51 0 520 5 3 0 36 0 37 0 380 390 400 410 4 2 0 430 440 450 46 0 470 480 490 50 0 510 23 0 24 0 2 5 0 26 0 270 280 300 310 330 340 350 360 370 380 3 9 0 4 0 0 4 1 0 4 2 0 43 0 44 0 4 5 0 4 6 0 4704 8 0 4 9 0 500 5 1 0 520 530 540 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]EEEEEE1 9 + 5 0 20 + 0 0 20 + 5 0 21+00 21+50 22+ 0 0 22 + 5 0 2 3 + 0 0 23+ 5 0 24+00 24 + 5 0 25 + 0 0 25+ 5 0 2 6 + 0 0 STATION=20+84.05 OFFSET=0.00 NORTHING=465687.56 EASTING=1610011.87 STATION=22+85.56 OFFSET=8.89R NORTHING=465549.70 EASTING=1609879.38 TP11 DG-7 UG-6 Headwall-3 TP-10 GC-4 DG-8 UG-7 TP-9 SW-1 SW-2 RP-14 Tree-13 Tree-9 RP-15 Tree-10 S04L S05U RP-16 DE-1 Tree-11 Tree-12 RP-17 RP-20 S05L S06U DE-3 RP-21 RW-1 DE-4 RW-2 DE-5 DE-2 RP-19 RP-18 OH-9 STATION=24+85.00 OFFSET=0.00 NORTHING=465406.11 EASTING=1609746.10 SECTION-05 END SECTION-05 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. SET MAG NAIL GUARD RAIL, TYP.\\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-059/30/2022 4:38 PMLayout:Printed:FIGURE 7 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION5 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 20 40 60 80 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 6 MATCHLINE - SEE SHEET 8 220 230 240 250 260 270 280 300 310 260 270 280 300 310 330 340 350 360 370 380 390 400 410 420 300 310 330 340 350 360 370 380 390 400 410 420 430 440 450 460 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]25+00 25+50 26+00 26+50 27+00 27+50 SECTION-06 START SECTION-06 END EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. TP11 DG-7 UG-6 DG-6 UG-5 Headwall-3 Tree-13 S05L S06U DE-3 RP-21 RW-1 DE-4 RW-2 DE-5 RP-22 DE-6 S06L S07U RP-24 RS-1 RP-23 DE-2 STATION=24+85.00 OFFSET=0.00 NORTHING=465406.11 EASTING=1609746.10 STATION=27+70.00 OFFSET=0.00 NORTHING=465225.90 EASTING=1609535.83 RS-1 RS-1 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-069/30/2022 4:38 PMLayout:Printed:FIGURE 8 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION6 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 7 MATCHLINE - SEE SHEET 9 17 0 180 20 0 220 230 24 0 25 0 26 0 270 280 30 0 310 330 34 0 350 360 370 170 180 200 220 230 240 250 260 270 280 300 310 330 340 350 360 370 380 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]27+50 28+00 28+50 29+00 29 + 5 0 30+00 30+5 0 SECTION-07 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-07 END TP-13 Headwall-2 TP12 RP-26 Tree-14 S06L S07U RP-25 RP-24 S08U S07L Tree-15 Tree-16 RS-2 DE-7 RS-1 STATION=27+70.00 OFFSET=0.00 NORTHING=465225.90 EASTING=1609535.83 STATION=29+95.00 OFFSET=0.00 NORTHING=465130.19 EASTING=1609343.83 RS-1 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-079/30/2022 4:39 PMLayout:Printed:FIGURE 9 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION7 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 8 MATCHLINE - SEE SHEET 10 170 180 200220 230 240 250 260 270 280 300 310 170 180 200 220 230 240 250 260 270 280 300 310 330 340 350 360 370 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]RS-4 29+00 29+5 0 30+00 30+50 31+00 31+ 5 0 32+00 SECTION-08 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-08 END Headwall-1 TP-13 UG-4 DG-5 Headwall-2 Tree-14 S08U S07L Tree-15 Tree-16 Tree-17 S08L S09U Tree-18 RP-27 RP-28 DE-8 RS-3 RS-4 RS-2DE-7 STATION=29+95.00 OFFSET=0.00 NORTHING=465130.19 EASTING=1609343.83 STATION=31+25.00 OFFSET=0.00 NORTHING=465077.58 EASTING=1609225.26 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-089/30/2022 4:39 PMLayout:Printed:FIGURE 10 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION8 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 9 MATCHLINE - SEE SHEET 11 150 160 170 180 200 220 230 240 150 160 170 180 200 220 230 240 250 260 270 2 8 0 170 180 200220230 240250260270280 300 310 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]RS-4 31+00 31+50 32+00 32+50 33+00 33+50 34+0 0 SECTION-09 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-09 END SET MAG NAIL, TYP. STATION=32+60.62 OFFSET=6.23R NORTHING=465075.25 EASTING=1609092.83 Headwall-1 DG-3 TP-14 UG-3 GC-5 DG-4 UG-4 DG-5 S08L S09U Tree-18 RP-27 RP-28 DE-9 DE-10 Tree-19 S09L S10U Tree-20 RP-30 DE-8 RS-3 RP-29 RS-4 STATION=31+25.00 OFFSET=0.00 NORTHING=465077.58 EASTING=1609225.26 STATION=33+45.00 OFFSET=0.00 NORTHING=465042.70 EASTING=1609014.16 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-099/30/2022 4:39 PMLayout:Printed:FIGURE 11 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION9 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. MATCHLINE - SEE SHEET 10 MATCHLINE - SEE SHEET 12 50 60 70 90110120 130 150 160 170 180 200 110 120 130 150160170 180 200 220 230 240 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]33+50 34+00 34+50 35+00 35+50 36+00 36+50SECTION-10 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-10 END TP-16 TP-15 UG-2 DG-3 UG-3 S09L S10U Tree-20 RP-30 RP-32 Tree-21 Tree-22 RP-33 Tree-23 RP-34 Tree-24 S10L S11U RP-35 RP-34RP-31 RP-29 STATION=33+45.00 OFFSET=0.00 NORTHING=465042.70 EASTING=1609014.16 STATION=36+35.00 OFFSET=0.00 NORTHING=465019.16 EASTING=1608733.63 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-109/30/2022 4:39 PMLayout:Printed:FIGURE 12 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION10 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 11 MATCHLINE - SEE SHEET 13 40 50 60 70 90 110 120 130 150 160 170 50 60 7090 304050 60 70 90 11 0 120 130 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]36+50 37+ 0 0 37+50 38+00 38+50 39+00 39+5 0 SECTION-11 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-11 END SET MAG NAIL DG-2 STATION=37+47.86 OFFSET=6.38R NORTHING=465001.01 EASTING=1608621.73 TP-17 DG-1 GC-6 S10L S11U Tree-25 RW-3 RW-4 Tree-27 RP-37 S11L UG-1 TP-18 TREE 26RP-36 OH-10 RP-35 STATION=36+35.00 OFFSET=0.00 NORTHING=465019.16 EASTING=1608733.63 STATION=39+50.00 OFFSET=0.00 NORTHING=464878.06 EASTING=1608465.87 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0003_0013_RHRS_GPS.DWGSLIVNYAK, OLEGSECTION-119/30/2022 4:39 PMLayout:Printed:FIGURE 13 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION11 SITE FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET NOTES 1. ACCURACY FOR GPS POINT AND LINE FEATURES WERE LIMITED DUE TO POOR SATELLITE CONNECTIVITY RELATED TO TOPOGRAPHIC AND VEGETATIVE OBSTRUCTIONS ALONG THE ROADWAY. THUS, GPS FEATURE LOCATIONS ARE APPROXIMATE AND NOT INTENDED FOR SURVEY OR CONSTRUCTION USE. 2. DUE TO LIMITED ACCURACY FOR GPS LINE FEATURES CAPTURED IN THE FIELD, GPS LINE FEATURES WERE SIMPLIFIED TO BE SHOWN AS LINES APPROXIMATELY PARALLEL TO THE ROADWAY ALIGNMENT CENTERLINE WITH START AND END POINT TAKEN FROM THE ORIGINAL LINE. 3. SEE TABLES 2, 3, AND 5 IN REPORT FOR ACRONYM DEFINITIONS. LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR GPS POINTS ADJUSTED GPS POINTS GPS TRAVERSE LINES UPSLOPE ROCK SOURCE CONCRETE[] MATCHLINE - SEE SHEET 12 870 880 89 0 900 910 920 860 870 880 890 900 840 850 860 87 0 880 890 900 840850860870870880[][][][][][][][][][][][][][][][][][][][][][][][][][][] [][][][][][] [] [] [][][][][][][][]SET MAG NAIL 466,416.08 NORTH 1,611,539.08 EAST ELEV.=881.25 STATION=0+00.00 OFFSET=0.00 NORTHING=466437.15 EASTING=1611567.73 SECTION-01 START SECTION-01 END 0+ 0 0 0+50 1+00 1+50 2 + 0 0 2+50 3+00 3+50 STATION=0+32.23 OFFSET=9.54R NORTHING=466416.08 EASTING=1611539.08 UTILITY POLE, TYP. GUARD RAIL, TYP. EDGE OF ROAD, TYP. STATION=2+15.00 OFFSET=0.00 NORTHING=466246.78 EASTING=1611509.29 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-019/30/2022 4:39 PMLayout:Printed:FIGURE 14 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION1 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL CONCRETE MATCHLINE - SEE SHEET 15 87088089090091092086087088089090084 0850860870880890900840 850 860 870 870 880 7207307407507 6 0770780790800810820830840850860870880890900 770 770 780 780 790 790 800 800 810 810 820 820 830 840 850 860 870 880 890 900 910 [][][][][][][ ][][][][][][ ][][][][][][][][][][][][]SET MAG NAIL466,416.08 NORTH1,611,539.08 EASTELEV.=881.250+000+501+001+502+002+503+003+ 5 0 4+00 4+50 5+00 5+50 6+00 6+507+007+508+008+50SECTION-02 START SECTION-02 END GUARD RAIL, TYP. STATION=2+15.92 OFFSET=0.00 NORTHING=466247.20 EASTING=1611508.47 EDGE OF ROAD, TYP. STATION=7+35.00 OFFSET=0.00 NORTHING=466426.33 EASTING=1611132.67 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-029/30/2022 4:39 PMLayout:Printed:FIGURE 15 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION2 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 20 40 60 80 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL CONCRETE MATCHLINE - SEE SHEET 14 MATCHLINE - SEE SHEET 16 600 610 620 630 640 650 660 670 680 690 70 0 71 0 72 0 730 740 750 760 770 780 790 800 810 820 830 840 850 640 650 660 670 680 690 720 730 740 750 760770 78 0 79 0 80 0 810 820 830 6+00 6+ 5 0 7+ 0 0 7+ 5 0 8+ 0 0 8+ 5 0 9+ 0 0 9+5 0 10+ 0 0 10+ 5 0 11+ 0 0 11 + 5 0 12 + 0 0 SECTION-03 END EDGE OF ROAD, TYP. UTILITY POLE, TYP. SET MAG NAIL STATION=11+16.15 OFFSET=7.02R NORTHING=466233.63 EASTING=1610803.31 STATION=7+35.00 OFFSET=0.00 NORTHING=466426.33 EASTING=1611132.67 SECTION-03 START STATION=11+50.00 OFFSET=0.00 NORTHING=466209.28 EASTING=1610781.27 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-039/30/2022 4:39 PMLayout:Printed:FIGURE 16 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION3 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 20 40 60 80 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 15 MATCHLINE - SEE SHEET 17 370 380 390 400 410 420 430 440 450 460470 480 490 500 510 520 530 540550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 400 410 42 0 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 560 570 580 590 600 610 620 630 640 65 0 660 670 680 690 700 710 720 730 740 750 [][][][][][]EEEEEEEEEEEEEEEEEEEEEE11+ 0 0 11 + 5 0 12 + 0 0 12+ 5 0 13+ 0 0 13+ 5 0 14+ 0 0 14+ 5 0 15 + 0 0 15 + 5 0 16 + 0 0 16+ 5 0 17+0 0 17+5 0 18+0 0 18+ 5 0 19 + 0 0 19 + 5 0 20+ 0 0 20+ 5 0 21+00 SET MAG NAIL SECTION-04 START SECTION-04 END EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. HIGH TENSION OVERHEAD WIRE STATION=11+16.15 OFFSET=7.02R NORTHING=466233.63 EASTING=1610803.31 STATION=20+84.54 OFFSET=0.30R NORTHING=465687.31 EASTING=1610011.35 STATION=11+50.00 OFFSET=0.00 NORTHING=466209.28 EASTING=1610781.27 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-049/30/2022 4:40 PMLayout:Printed:FIGURE 17 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION4 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 30 60 90 120 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 16 MATCHLINE - SEE SHEET 18 30 0 310 3 3 0 3 4 0 3 5 0 3 6 0 37 0 240 250 260 27 0 28 0 300 31 0 330 34 0 35 0 36 0 3 7 0 3 8 0 390 40 0 410 42 0 430 440 450 46 0 300 310 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 48 0 49 0 500 51 0 520 5 3 0 36 0 37 0 380 390 400 410 4 2 0 430 440 450 46 0 470 480 490 50 0 510 23 0 24 0 2 5 0 26 0 270 280 300 310 330 340 350 360 370 380 3 9 0 4 0 0 4 1 0 4 2 0 43 0 44 0 4 5 0 4 6 0 4704 8 0 4 9 0 500 5 1 0 520 530 540 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]EEEEEE1 9 + 5 0 20 + 0 0 20 + 5 0 21+00 21+50 22+ 0 0 22 + 5 0 2 3 + 0 0 23+ 5 0 24+00 24 + 5 0 25 + 0 0 25+ 5 0 2 6 + 0 0 STATION=20+84.05 OFFSET=0.00 NORTHING=465687.56 EASTING=1610011.87 STATION=22+85.56 OFFSET=8.89R NORTHING=465549.70 EASTING=1609879.38 STATION=24+85.00 OFFSET=0.00 NORTHING=465406.11 EASTING=1609746.10 SECTION-05 END SECTION-05 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. SET MAG NAIL GUARD RAIL, TYP.\\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-059/30/2022 4:40 PMLayout:Printed:FIGURE 18 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION5 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 20 40 60 80 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 17 MATCHLINE - SEE SHEET 19 220 230 240 250 260 270 280 300 310 260 270 280 300 310 330 340 350 360 370 380 390 400 410 420 300 310 330 340 350 360 370 380 390 400 410 420 430 440 450 460 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]25+00 25+50 26+00 26+50 27+00 27+50 SECTION-06 START SECTION-06 END EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. STATION=24+85.00 OFFSET=0.00 NORTHING=465406.11 EASTING=1609746.10 STATION=27+70.00 OFFSET=0.00 NORTHING=465225.90 EASTING=1609535.83 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-069/30/2022 4:40 PMLayout:Printed:FIGURE 19 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION6 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 18 MATCHLINE - SEE SHEET 20 17 0 180 20 0 220 230 24 0 25 0 26 0 270 280 30 0 310 330 34 0 350 360 370 170 180 200 220 230 240 250 260 270 280 300 310 330 340 350 360 370 380 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]27+50 28+00 28+50 29+00 29 + 5 0 30+00 30+5 0 SECTION-07 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-07 END STATION=27+70.00 OFFSET=0.00 NORTHING=465225.90 EASTING=1609535.83 STATION=29+95.00 OFFSET=0.00 NORTHING=465130.19 EASTING=1609343.83 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-079/30/2022 4:40 PMLayout:Printed:FIGURE 20 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION7 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 19 MATCHLINE - SEE SHEET 21 170 180 200220 230 240 250 260 270 280 300 310 170 180 200 220 230 240 250 260 270 280 300 310 330 340 350 360 370 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]29+00 29+5 0 30+00 30+50 31+00 31+ 5 0 32+00 SECTION-08 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-08 END STATION=29+95.00 OFFSET=0.00 NORTHING=465130.19 EASTING=1609343.83 STATION=31+25.00 OFFSET=0.00 NORTHING=465077.58 EASTING=1609225.26 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-089/30/2022 4:40 PMLayout:Printed:FIGURE 21 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION8 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 20 MATCHLINE - SEE SHEET 22 150 160 170 180 200 220 230 240 150 160 170 180 200 220 230 240 250 260 270 2 8 0 170 180 200220230 240250260270280 300 310 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]31+00 31+50 32+00 32+50 33+00 33+50 34+0 0 SECTION-09 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-09 END SET MAG NAIL, TYP. STATION=32+60.62 OFFSET=6.23R NORTHING=465075.25 EASTING=1609092.83 STATION=31+25.00 OFFSET=0.00 NORTHING=465077.58 EASTING=1609225.26 STATION=33+45.00 OFFSET=0.00 NORTHING=465042.70 EASTING=1609014.16 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-099/30/2022 4:40 PMLayout:Printed:FIGURE 22 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION9 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 21 MATCHLINE - SEE SHEET 23 50 60 70 90110120 130 150 160 170 180 200 110 120 130 150160170 180 200 220 230 240 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]33+50 34+00 34+50 35+00 35+50 36+00 36+50SECTION-10 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-10 END STATION=33+45.00 OFFSET=0.00 NORTHING=465042.70 EASTING=1609014.16 STATION=36+35.00 OFFSET=0.00 NORTHING=465019.16 EASTING=1608733.63 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-109/30/2022 4:40 PMLayout:Printed:FIGURE 23 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION10 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 22 MATCHLINE - SEE SHEET 24 40 50 60 70 90 110 120 130 150 160 170 50 60 7090 304050 60 70 90 11 0 120 130 [][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][][]36+50 37+ 0 0 37+50 38+00 38+50 39+00 39+5 0 SECTION-11 START EDGE OF ROAD, TYP. UTILITY POLE, TYP. GUARD RAIL, TYP. SECTION-11 END SET MAG NAIL STATION=37+47.86 OFFSET=6.38R NORTHING=465001.01 EASTING=1608621.73 STATION=36+35.00 OFFSET=0.00 NORTHING=465019.16 EASTING=1608733.63 STATION=39+50.00 OFFSET=0.00 NORTHING=464878.06 EASTING=1608465.87 \\HALEYALDRICH.COM\SHARE\PDX_DATA\NOTEBOOKS\0203303-001_WAIPIO_VALLEY_GEOTECHNICAL_DESIGN\CAD\FIGURES\WAIPIO VALLEY ROAD GEOTECH DESIGN\0203303_001_0014_0024_RHRS-MITIGATION.DWGSLIVNYAK, OLEGSECTION-119/30/2022 4:40 PMLayout:Printed:FIGURE 24 WAIPI‘O VALLEY ROAD GEOTECHNICAL DESIGN WAIPI‘O VALLEY ROAD HONOKA‘A, HAWAI‘I SECTION11 MITIGATION FEATURES SCALE: AS SHOWN SEPTEMBER 2022 0 10 20 30 40 SCALE IN FEET [] LEGEND SET MAG NAIL UTILITY POLE ROAD SIGN EDGE OF ROAD GUARD RAIL SECTION ALIGNMENT 2' TOPOGRAPHIC CONTOUR 10' TOPOGRAPHIC CONTOUR ROCKFALL FENCE HAZARDS REMOVAL DRAPED MESH CONCRETE MATCHLINE - SEE SHEET 23 APPENDIX A Photo Log Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 1 of 9 Photo 1: A corestone, CS-01. Photo 2: Differential erosion, DE-02. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 2 of 9 Photo 3: Overhang, OH-01. Photo 4: Rock package, RP-36. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 3 of 9 Photo 5: Root wedging, RW-01. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 4 of 9 Photo 6: Scallop, SC-02. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 5 of 9 Photo 7: Tree, Tree-02. Photo 8: Upslope gully, UG-05. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 6 of 9 Photo 9: Upslope rock source, RS-04. Photo 10: Downslope gully, DG-10. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 7 of 9 Photo 11: Boulder, Boulder-01. Photo 12: Culvert, Culvert-01. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 8 of 9 Photo 13: Headwall, Headwall-03. Photo 14: Telephone pole, TP-08. Waipio Valley Road Evaluation Project File No. 0203303 Date : May 16 Haley & Aldrich Inc. Page 9 of 9 Photo 15: Swale, SW-03. APPENDIX B GPS Field Data Field ID Photo Video #Shape Section Feature Name Feature Full Name 1 Point 11 TP 18 Telephone Pole 18 2 Point 11 DG 01 Downslope Gully 1 3 Point 11 TP 17 Telephone Pole 17 4 Point 11 DG 02 Downslope Gully 2 5 Point 11 GC 06 Ground Control 6 6 Point 10 TP 16 Telephone Pole 16 7 Point 10 TP 15 Telephone Pole 15 8 Point 10 UG 02 Upslope Gully 2 9 Point 10 DG 03 Downslope Gully 3 10 Point 9 TP 14 Telephone Pole 14 11 Point 10 UG 03 Upslope Gully 3 12 Point 9 GC 05 Ground Control 5 13 Point 9 DG 04 Downslope Gully 4 14 Point 9 Headwall 01 Headwall 1 15 Point 8 TP 13 Telephone Pole 13 16 Point 8 UG 04 Upslope Gully 4 17 Point 8 DG 05 Downslope Gully 5 18 Point 7 TP 12 Telephone Pole 12 19 Point 7 Headwall 02 Headwall 2 20 Point 6 TP 11 Telephone Pole 11 21 Point 6 DG 07 Downslope Gully 7 22 Point 6 UG 06 Upslope Gully 6 23 Point 6 DG 06 Downslope Gully 6 24 Point 6 UG 05 Upslope Gully 5 25 Point 6 Headwall 03 Headwall 3 26 Point 5 TP 10 Telephone Pole 10 27 Point 5 GC 04 Ground Control 4 28 Point 5 DG 08 Downslope Gully 8 29 Point 5 UG 07 Upslope Gully 7 30 Line Waipio Valley Road Waipio Valley Road 31 Point 4 TP 09 Telephone Pole 9 32 1465 Point 4 SW 01 Swale 1 33 1466 Point 4 SW 02 Swale 2 34 1467 Point 4 SW 03 Swale 3 35 1468 Point 4 SW 04 Swale 4 36 Point 4 TP 08 Telephone Pole 8 37 1469 Point 4 SW 05 Swale 5 38 Point 4 GC 03 Ground Control 3 39 1474 1475 Point 4 SW 06 Swale 6 40 Point 4 TP 07 Telephone Pole 7 41 Point 4 DG 09 Downslope Gully 9 42 1467 Point 4 SW 07 Swale 7 43 Point GC 00 Ground Control 0 44 Point 4 TP 06 Telephone Pole 6 45 1477 Point 4 SW 08 Swale 8 46 Point 3 TP 05 Telephone Pole 5 47 Point 3 Boulder Boulder 48 Point 3 GC 02 Ground Control 2 49 1478 1480 Point 3 SW 09 Swale 9 50 Point 3 TP 04 Telephone Pole 4 51 1481 1482 Point 3 SW 10 Swale 10 52 Point 2 TP 03 Telephone Pole 3 53 1483 Point 2 SW 11 Swale 11 54 1484 Point 2 SW 12 Swale 12 55 Point 2 TP 02 Telephone Pole 2 56 1485 1486 Point 2 SW 13 Swale 13 57 Point 2 DG 10 Downslope Gully 10 58 Point 2 DG 11 Downslope Gully 11 59 Point 2 DG 12 Downslope Gully 12 60 1489 1490 Point 2 SW 14 Swale 14 61 Point 1 TP 01 Telephone Pole 1 62 Point 1 GC 01 Ground Control 1 63 1491 Point 1 SW 15 Swale 15 64 Point 1 Culvert Outlet Culvert Outlet 65 Point 1 Culvert Inlet Culvert Inlet 66 Point 1 S01U Section 1 Upper 67 Point 1 S01L Section 1 Lower 68 1514 1515 Point 2 S02U Section 2 Upper 69 Point 2 S02L Section 2 Lower 70 1553 Point 2 CS 01 Corestone 1 71 1554 1557 Line 2 OH 01 Overhang 1 72 1558 Point 2 SC 01 Scallop 1 73 1559 Point 2 CS 02 Corestone 2 74 1561 1564 Line 2 SC 02 Scallop 2 75 1565 1567 Line 2 SC 03 Scallop 3 76 1560 Point 2 CS 03 Corestone 3 77 1568 Point 2 SC 04 Scallop 4 78 1568 Point 2 CS 04 Corestone 4 79 1568 Line 2 SC 04 Line Scallop 4 80 1570 Line 2 SC 05 Scallop 5 81 1571 1572 Point 2 Tree 01 Tree 1 82 1573 1576 Line 2 OH 02 Overhang 2 83 1577 Point 2 Tree 02 Tree 2 84 1577 Point 2 Tree 03 Tree 3 85 Point 3 S03U Section 3 Upper 86 1578 1586 Line 3 OH 03 Overhang 3 87 1587 Point 3 SC 06 Scallop 6 88 1588 Line 3 RP 01 Rock Package 1 89 1589 Point 3 Tree 04 Tree 4 90 1590 Point 3 Tree 05 Tree 5 91 1591 Point 3 Tree 06 Tree 6 92 1592 Point 3 RP 02 Rock Package 2 93 1593 1594 Line 3 OH 04 Overhang 4 94 1595 1596 Line 3 OH 05 Overhang 5 95 Point 3 S03L Section 3 Lower 96 Point 4 S04U Section 4 Upper 97 1597 Point 4 RP 03 Rock Package 3 98 1598 Line 4 OH 06 Overhang 6 99 1599 1601 Line 4 RP 04 Rock Package 4 100 1602 Line 4 OH 07 Overhang 7 101 1603 Point 4 Tree 07 Tree 7 102 1604 Point 4 RP 05 Rock Package 5 103 1605 Point 4 RP 06 Rock Package 6 104 1606 Point 4 RP 07 Rock Package 7 105 1607 1608 Point 4 RP 08 Rock Package 8 106 1609 1610 Point 4 RP 09 Rock Package 9 107 1611 1613 Line 4 RP 10 Rock Package 10 108 1614 1616 Line 4 RP 11 Rock Package 11 109 1617 1618 Line 4 OH 08 Overhang 8 110 1619 1626 Line 4 RP 12 Rock Package 12 111 1627 Point 4 Tree 08 Tree 8 112 1628 Point 4 RP 13 Rock Package 13 113 1629 Point 4 Tree 09 Tree 9 114 1630 Point 4 RP 14 Rock Package 14 115 1631 Point 4 RP 15 Rock Package 15 116 1632 Point 4 Tree 10 Tree 10 117 Point 4 S04L Section 4 Lower 118 Point 5 S05U Section 5 Upper 119 1633 Point 5 RP 16 Rock Package 16 120 1634 Point 5 DE 01 Differential Erosion 1 121 1635 Line 5 OH 09 Overhang 9 122 1636 Point 5 Tree 11 Tree 11 123 1637 Point 5 Tree 12 Tree 12 124 1638 1639 Point 5 RP 17 Rock Package 17 125 1640 1641 Line 5 RP 18 Rock Package 18 126 1642 1644 Line 5 RP 19 Rock Package 19 127 1645 Point 5 RP 20 Rock Package 20 128 1646 Line 5 DE 02 Differential Erosion 2 129 Point 5 S05L Section 5 Lower 130 Point 6 S06U Section 6 Upper 131 1647 Point 6 DE 03 Differential Erosion 3 132 1648 Point 6 RP 21 Rock Package 21 133 1649 Point 6 Tree 13 Tree 13 134 1650 Point 6 RW 01 Root Wedging 1 135 1651 Point 6 DE 04 Differential Erosion 4 136 1652 Point 6 RW 02 Root Wedging 2 137 1653 Point 6 DE 05 Differential Erosion 5 138 1654 Point 6 RP 22 Rock Package 22 139 1655 1657 Line 6 RP 23 Rock Package 23 140 1658 Point 6 DE 06 Differential Erosion 6 141 1659 Line 6 RS 01 Upslope Rock Source 1 142 Point 6 S06L Section 6 Lower 143 Point 7 S07U Section 7 Upper 144 1660 Point 7 RP 24 Rock Package 24 145 1661 Point 7 RP 25 Rock Package 25 146 1662 Point 7 RP 26 Rock Package 26 147 Point 7 S07L Section 7 Lower 148 Point 8 S08U Section 8 Upper 149 1663 Point 8 Tree 14 Tree 14 150 1664 1665 Line 8 DE 07 Differential Erosion 7 151 1666 Point 8 Tree 15 Tree 15 152 1667 Point 8 Tree 16 Tree 16 153 1668 Line 8 RS 02 Upslope Rock Source 2 154 1669 Point 8 Tree 17 Tree 17 155 Point 8 S08L Section 8 Lower 156 Point 9 S09U Section 9 Upper 157 1672 Point 9 Tree 18 Tree 18 158 1673 Point 9 RP 27 Rock Package 27 159 1675 Point 9 RP 28 Rock Package 28 160 1676 Line 9 RS 04 Upslope Rock Source 4 161 1677 Point 9 DE 09 Differential Erosion 9 162 1678 Point 9 DE 10 Differential Erosion 10 163 1679 Point 9 Tree 19 Tree 19 164 Point 9 S09L Section 9 Lower 165 Point 10 S10U Section 10 Upper 166 1680 Point 10 Tree 20 Tree 20 167 1681 1682 Line 10 RP 29 Rock Package 29 168 1683 Point 10 RP 30 Rock Package 30 169 1684 Line 10 RP 31 Rock Package 31 170 1686 Point 10 RP 32 Rock Package 32 171 1687 Point 10 Tree 21 Tree 21 172 1688 Point 10 Tree 22 Tree 22 173 1689 Point 10 RP 33 Rock Package 33 174 1690 Point 10 Tree 23 Tree 23 175 1691 1692 Point 10 RP 34 Rock Package 34 176 1691 1692 Line 10 RP 34 Rock Package 34 177 1693 Point 10 Tree 24 Tree 24 178 Point 10 S10L Section 10 Lower 179 Point 11 S11U Section 11 Upper 180 1694 1695 Line 11 RP 35 Rock Package 35 181 1696 Point 11 Tree 25 Tree 25 182 1697 1698 Point 11 RW 03 Root Wedging 3 183 1699 Point 11 RW 04 Root Wedging 4 184 1700 Line 11 RP 36 Rock Package 36 185 1701 Line 11 Tree 26 Tree 26 186 1702 Point 11 Tree 27 Tree 27 187 1703 Point 11 RP 37 Rock Package 37 188 1704 Line 11 OH 10 Overhang 10 189 Point 11 S11L Section 11 Lower 190 Point 12 S12L Section 12 Lower 191 Line 12 S12 Line Section 12 Line 192 Point 12 TP 25 Telephone Pole 25 193 Point 12 TP 24 Telephone Pole 24 194 Point 12 TP 23 Telephone Pole 23 195 Point 12 TP 22 Telephone Pole 22 196 Point 12 TP 21 Telephone Pole 21 197 Point 12 TP 20 Telephone Pole 20 198 Point 12 TP 19 Telephone Pole 19 199 Point 11 UG 01 Upslope Gully 1 200 1671 Point 8 DE 08 Differential Erosion 8 201 1670 Point 8 RS 03 Upslope Rock Source 3 APPENDIX C Features Data by Section Corestone Differential Erosion Downslope Gully Overhang Rock Package Root Wedging Scallop Tree Upslope Gully Upslope Rock Source 1 0+00 2+15 215 1 See note below. Culvert-Inlet/Outlet, SW-15, TP- 01, GC-01 2 2+15 7+35 520 CS-01, CS-02, CS-03, CS-04 DG-10, DG-11, DG-12 OH-01, OH-02 SC-01, SC-02, SC-03, SC-04, SC-05 Tree-01, Tree-02, Tree-03 17 SW-14, SW-13, SW-12, SW-11, TP-02, TP-03 3 7+35 11+50 415 OH-03, OH-04, OH-05 RP-01, RP-02 SC-06 Tree-04, Tree-05, Tree-06 9 Boulder, SW-10, SW-09, TP-04, TP-05, GC-02 4 11+50 20+85 935 DG-09 OH-06, OH-07, OH-08 RP-03, RP-04, RP-05, RP-06, RP-07, RP-08, RP-09, RP-10, RP-11, RP-12, RP-13, RP-14, RP-15 Tree-07, Tree-08, Tree-09, Tree-10 21 SW-08, SW-07, SW-06, SW-05, SW-04, SW-03, SW-02, SW-01, TP-06, TP-07, TP-08, TP-09, GC-03 5 20+85 24+85 400 DE-01, DE-02 DG-08 OH-09 RP-16, RP-17, RP-18, RP-19, RP-20 Tree-11, Tree-12 UG-07 12 TP-10, GC-04 6 24+85 27+70 285 DE-02, DE-03, DE-04, DE-05, DE-06 DG-06, DG-07 RP-21, RP-22, RP-23 RW-01, RW-02 Tree-13 UG-06, UG-05 RS-01 16 Headwall-03, TP-11 7 27+70 29+95 225 RP-24, RP-25, RP-26 Tree-14 4 Headwall-02, TP-12 8 29+95 31+25 130 DE-07, DE-08 Tree-15, Tree-16, Tree-17 UG-04 RS-02, RS-03 8 TP-13 9 31+25 33+45 220 DE-09, DE-10 DG-04, DG-05 RP-27, RP-28 Tree-18 RS-04 8 Headwall-01, TP-14, GC-05 10 33+45 36+35 290 DG-03 RP-29, RP-30, RP-31, RP-32, RP-33, RP-34, Tree-19, Tree-20, Tree-21, Tree-22, Tree-23, Tree-24 UG-03, UG-02 15 TP-15, TP-16 11 36+35 39+50 315 DG-01, DG-02 OH-10 RP-35, RP-36, RP-37 RW-03, RW-04 Tree-25, Tree-26, Tree-27 UG-01 12 TP-17, TP-18, GC-6 Total Hazard Features Other Features 1 While no hazards were mapped within Section-01, there is a noted sloughing of soil along the embankment between Sta. 0+00 and Sta. 2+15. The heavy vegetation obscures much of the failing scarp but evidence of outwash and small cobbles is present along the side of the road. Section Start Station End Station Length (ft) Hazard Feature Types APPENDIX D Rockfall Mitigation Measures and Estimated Costs by Section Table 1. Rockfall Mitigation Measures and Estimated Costs by Section Section Mitigation Units Unit Costs per sq ft* Subtotal Costs Section Total Cost 1 Hazards Removal 2,500 ft2 $2 – $5 $5,000 – $13,000 $5,000 – $13,000 2 Hazards Removal 13,500 ft2 $2 – $5 $27,000 – $68,000 $27,000 – $68,000 3 Rock Scaling 6,000 ft2 $6 – $13 $36,000 – $78,000 $84,000 – $198,000 Drapery Netting 6,000 ft2 $8 – $20 $48,000 – $120,000 4 Rock Scaling 16,500 ft2 $6 – $13 $99,000 – $215,000 $231,000 – $545,000 Drapery Netting 16,500 ft2 $8 – $20 $132,000 –$330,000 5 Rock Scaling 4,000 ft2 $6 – $13 $24,000 – $52,000 $56,000 – $132,000 Drapery Netting 4,000 ft2 $8 – $20 $32,000 – $80,000 6 Rock Scaling 1,500 ft2 $6 – $13 $9,000 – $20,000 $101,000 – $500,000 Drapery Netting 1,500 ft2 $8 – $20 $12,000 – $30,000 Rockfall Impact Fence 100 ft $800 – $4,500 per linear foot $80,000 – $450,000 7 Rock Scaling 1,500 ft2 $6 – $13 $9,000 – $20,000 $21,000– $50,000 Drapery Netting 1,500 ft2 $8 – $20 $12,000 – $30,000 8 Rock Scaling 1,000 ft2 $6 – $13 $6,000 – $13,000 $94,000 –$483,000 Drapery Netting 1,000 ft2 $8 – $20 $8,000 – $20,000 Rockfall Impact Fence 100 ft $800 – $4,500 per linear foot $80,000 – $450,000 9 Rock Scaling 2,000 ft2 $6 – $13 $12,000 –$26,000 $108,000 – $516,000 Drapery Netting 2,000 ft2 $8 – $20 $16,000 – $40,000 Rockfall Impact Fence 100 ft $800 – $4,500 per linear foot $80,000 – $450,000 10 Rock Scaling 3,000 ft2 $6 – $13 $18,000 – $39,000 $42,000 – $99,000 Drapery Netting 3,000 ft2 $8 – $20 $24,000 – $60,000 11 Rock Scaling 3,000 ft2 $6 – $13 $18,000 – $39,000 $42,000 – $99,000 Drapery Netting 3,000 ft2 $8 – $20 $24,000 – $60,000 Notes: * Unit costs are provided per square foot except where noted. 1 Phases 2 and 3 will require clearing and grubbing, which are included in the estimates for the installation of the noted systems. 2 The above mitigation cost estimates are approximate and should not be considered “Engineer Estimates”, but rough order of magnitude costs suitable for conceptual planning purposes only and do not account for ancillary permitting or construction costs related to the construction of these given measure. 3 Further evaluation may be required to confirm the needs for mitigation and for design of mitigation measures.