EXECUTIVE SUMMARY
Funding for the Affordable Housing Production (AHP) Program is made possible through
Ordinance 22-77, which appropriates at least $5,000,000 per year for the Office of Housing and
Community Development (OHCD) to facilitate programs that support affordable housing
production in the County of Hawaiʻi (County).
In Fiscal Years (FY) 2022-23 and FY2023-24, the OHCD was appropriated a total of $18,000,000
for the AHP Program. The OHCD successfully developed the Administrative Rules for the AHP
Program, issued a Request for Proposals (RFP) with the combined appropriation from the two
fiscal years, and awarded seven projects totaling $17,324,559.46. These projects are currently at
various stages of predevelopment and development. The purpose of this report is to provide
transparency and accountability regarding the use of funds and the progress of the awarded
projects, as outlined in the AHP Program Administrative Rules Section § 2-2 Annual Report.
Key Statistics
Total Appropriation: $18,000,000
Total Funds Awarded: $17,324,559.46
Total Projects Awarded: 7
FY2023-24 SUMMARY OF THE FUNDED PROJECTS
Project Name Total Amount
Requested
Total Amount
Funded
Units
Added/Impacted District
Na Hale Makoa $2,000,000 $2,000,000 140 9
Manago Mauo $5,500,000 $5,500,000 72 6
Land Trust Pa Ali'i
Street $300,000 $300,000 1 5
Land Trust University
Heights $300,000 $300,000 1 2
Hoʻomalu at Waikoloa $3,000,000 $3,000,000 229 9
Kamakoa Nui
Workforce Housing $5,400,000 $5,400,000 643 9
Hale Ola O Mohouli $2,000,000 $824,559.46 90 2
Total of 7 projects $18,500,000 $17,324,559.46 1,176
2
3
INTRODUCTION:
In its first year post-award, the OHCD established a strong foundation for the future success of
the AHP Program and its projects. While no housing units were completed this year, substantial
progress was made through the initiation and advancement of each funded project to increase
the affordable housing availability in the County. The strategic allocation of funds facilitated
housing developments directly supported by the County for the first time while encouraging further
private and public investments and partnerships. This approach has accelerated progress on
multiple fronts, making the housing development process more streamlined and effective.
FY2023-24 SUMMARY OF THE PROJECT STATUS:
Project Environmental
Compliance
Grant
Agreement
Obligation of
Funds
Anticipated
Start
Na Hale Makoa Completed In Progress Q3 2024
Manago Mauo* Completed - - -
Land Trust Pa Ali'i
Street Completed Completed Completed In Progress
Land Trust University
Heights Completed Completed Completed In Progress
Hoʻomalu at Waikoloa Completed Pending Q2 2025
Kamakoa Nui
Workforce Housing Completed In Progress Q3 2024
Hale Olaʻ O Mohouli Completed Pending Q2 2025
* (see page 6)
FY2023-24 SUMMARY OF THE ADMINISTRATIVE EXPENDITURE:
Per the AHP Program Administrative Rules §1-3 (5): On an annual basis, up to 10% of the
fund's appropriation shall be used for administrative expenses by the OHCD.
For the combined allocation of FY2022-23 and FY2023-24, the OHCD has allocated
approximately 3.75% for this purpose.
FY2022-23 & FY2023-24
Administrative Allocation Expenditure Total Remaining
$ 675,440.54 $ 412,784.20 $ 262,656.34
4
NA HALE MAKOA
Organization: Pacific Housing Assistace Corporation (PHAC) dba
Kamakoa Nui Limited Partnership
Funds Awarded: $2,000,000
Location: Waikoloa Village, South Kohala, HI
Project Type: New Construction (Rental)
Units: 140 (including one manager’s unit)
Affordability Period: 61 years
Report Period: FY2023-24
Current Status:
Pre-construction Phase.
Milestones and Achievements:
Additional Funding Secured: Secured additional Funding from the Hawaiʻi Housing Finance
and Development Corporation (HHFDC), ensuring financial viability for the project's
subsequent phases.
Upcoming Activities:
Ground Lease: Finalize and Execute the Ground Lease.
Grant Agreement and Obligation of Funds: Execute the AHP Program Grant Agreement and
obligate funds with the relevant provider.
Close Financing: Complete all necessary steps to close financing, enabling the project to
proceed to construction.
Expenditure Report:
N/A, the project has yet to begin.
5
NA HALE MAKOA
6
MANAGO MAUO
Organization: Mental Health Kokua (MHK)
Funds Awarded: $5,500,000
Location: Captain Cook, South Kona, HI
Project Type: Property Acquisition, Converting Hotel Units into Affordable Rentals
Units: 72 (including one manager’s unit)
Affordability Period: Perpetuity
Report Period: FY2023-24
Current Status:
Project Unable to Proceed: The parties could not agree on the terms of the purchase
contract. As a result, the funds will be reallocated for future projects.
7
LAND TRUST PA ALIʻI STREET
Organization: Housing and Land Enterprise of Hawaii County dba
Hale o Hawaii County
Funds Awarded: $300,000
Location: Royal Hawaiian Estates, Volcano, HI
Project Type: New Construction (For-Sale)
Units: 1
Affordability Period: Perpetuity
Report Period: FY2023-24
Current Status:
Construction Phase.
Milestones and Achievements:
Building Permit: Approved.
Grant Agreement and Obligation of Funds: Executed the AHP Program Grant Agreement
and obligated funds with the relevant provider.
Upcoming Activities:
Finalize Construction.
Anticipated Completion: Q4 2024.
Expenditure Report:
Total Award Total Expenditure Total Remaining
$300,000 - -
Picture from: https://www.hpmhawaii.com/homes.
8
LAND TRUST UNIVERSITY HEIGHTS
Organization: Housing and Land Enterprise of Hawaii County dba
Hale o Hawaii County
Funds Awarded: $300,000
Location University Heights, Hilo, HI
Project Type: New Construction (For-Sale)
Units: 1
Affordability Period: Perpetuity
Report Period: FY2023-24
Current Status:
Construction Phase.
Milestones and Achievements:
Building Permit: Approved
Grant Agreement and Obligation of Funds: Executed the AHP Program Grant Agreement
and obligated funds with the relevant provider.
Upcoming Activities:
Finalize Construction.
Anticipated Completion: Q4 2024.
Expenditure Report:
Total Award Total Expenditure Total Remaining
$300,000 - -
Picture from: https://www.hpmhawaii.com/homes.
9
HO’OMALU AT WAIKOLOA
Organization: Stanford Carr Development LLC dba Ho’omalu at Waikoloa LP
Funds Awarded: $3,000,000
Location: Waikoloa, South Kohala, HI
Project Type: New Construction (Rental)
Units: 229 (including one manager’s unit)
Affordability Period: 65 years
Report Period: FY2023-24
Current Status:
Pending financing.
Milestones and Achievements:
Funding Secured: Secured Rental Housing Revolving Funds (RHRF) from the Hawaiʻi
Housing Finance and Development Corporation (HHFDC).
Subsidy Secured: Secured Project-Based Housing Choice Vouchers to ensure the project's
long-term sustainability.
Submitted the funding application to the HHFDC.
Upcoming Activities:
Pending Funding Decision from HHFDC: Results expected for Low Income Housing Tax
Credit (LIHTC) and Hula Mae Multi-Family Program (HMMF) in July/August 2024.
Grant Agreement and Obligation of Funds: If awarded, execute the AHP Program Grant
Agreement and obligate funds with the relevant provider.
Closing Financing: If awarded HHFDC funds, complete all necessary steps to close financing,
enabling the project to proceed to construction.
Expenditure Report:
N/A, the project has yet to begin.
10
HO’OMALU AT WAIKOLOA
11
KAMAKOA NUI WORKFORCE HOUSING-MINI LOOP ROAD AND
INFRASTRUCTURE DEVELOPMENT
Organization: Office of Housing and Community Development (OHCD) –
Community Development Division
Funds Awarded: $5,400,000
Location: Waikoloa, South Kohala, HI
Project Type:
Infrastructure road development, providing access to 9 parcels.
The parcels will be offered to developers through a Request for
Proposals (RFP) process for the construction of approximately 643
residential units.
Units: 643 Units: 318 rental and 325 for-sale units
Affordability Period: Minimum 20 years (rentals) or 10 years (for-sale) with potential for
extension through the RFP process.
Report Period: FY2023-24
Current Status:
Planning and Design.
Milestones and Achievements:
Funding Secured: Secured additional funding from the Capital Improvement Project (CIP)
Fund.
Planning and Design: Contracted with Sam O. Hirota, Inc. to plan the infrastructure
development.
Upcoming Activities:
Finish Planning and Design.
Grant Agreement and Obligation of Funds: Execute the AHP Program Grant Agreement and
obligate funds with the relevant provider.
Construction Start.
Expenditure Report:
N/A, the project has yet to begin.
12 KAMAKOA NUI WORKFORCE HOUSING-MINI LOOP ROAD AND INFRASTRUCTURE DEVELOPMENT
13
HALE OLAʻ O MOHOULI
Organization: Hawaii Island Community Development Corporation (HICDC) dba
Hale Ola O Mohouli LLLP
Funds Awarded: $824,559.46
Location: Hilo, HI
Project Type: New Construction (Rental)
Units: 90 (including one manager’s unit)
Affordability Period: 61 years
Report Period: FY2023-24
Current Status:
Pending financing.
Milestones and Achievements:
Funding Secured: Successfully secured funding from the HOME Investment Partnerships
Program, Housing Trust Fund (HTF), and the Hawaiʻi Housing Finance and Development
Corporation (HHFDC) Rental Housing Revolving Funds (RHRF).
Upcoming Activities:
Pending Funding Decision from HHFDC: Results expected for Low Income Housing Tax
Credit (LIHTC) and Hula Mae Multi-Family Program (HMMF) in July/August 2024.
Grant Agreement and Obligation of Funds: If awarded, execute the AHP Program Grant
Agreement and obligate funds with the relevant provider.
Closing Financing: If awarded HHFDC funds, complete all necessary steps to close financing,
enabling the project to proceed to construction.
Expenditure Report:
N/A, the project has yet to begin.
14