HomeMy WebLinkAboutB-4944 - Evaluation Tabulation (Bid Results) (2)County of Hawaii
Public Works
Wesley R Segawa, Director
25 Aupuni Street, Suite 1101, Hilo, HI 96720
EVALUATION TABULATION
IFB No. B-4944
AUPUNI CENTER SEWER JUNCTION REPAIRS
RESPONSE DEADLINE: September 10, 2026 at 2:00 pm
Report Generated: Thursday, September 10, 2026
SELECTED VENDOR TOTALS
Vendor Total
Stan's Contracting, Inc. $223,500.00
Jas. W. Glover, Ltd. $320,300.00
Isemoto Contracting Co.,
Ltd.
702,377.00
B-4944 - BASE BID
PART A. MOBILIZATION AND GENERAL WORK (NOTE: Bidders must complete all unit prices and amounts. Failure to do so may be
grounds for rejection of bid)
B-4944 - BASE BID Isemoto Contracting Co., Ltd. Jas. W. Glover, Ltd. Stan's Contracting, Inc.
Selected Line Item Description Quantity Unit of
Measure
Unit Cost Total Unit Cost Total Unit Cost Total
X 1 Mobilization (shall not
exceed 5% of the overall
base bid amount).
1 Lump Sum $30,414.00 $30,414.00 $11,000.00 $11,000.00 $5,000.00 $5,000.00
EVALUATION TABULATION
IFB No. B-4944
AUPUNI CENTER SEWER JUNCTION REPAIRS
EVALUATION TABULATION
Invitation For Bid - AUPUNI CENTER SEWER JUNCTION REPAIRS
Page 2
B-4944 - BASE BID Isemoto Contracting Co., Ltd. Jas. W. Glover, Ltd. Stan's Contracting, Inc.
Selected Line Item Description Quantity Unit of
Measure
Unit Cost Total Unit Cost Total Unit Cost Total
X 2 General Requirements:
project engineer, clerical
support,
foreman/superintendent,
utilities, temporary
toilets, etc. (shall not
exceed 10% of the
overall basic bid
amount).
1 Lump Sum $58,886.00 $58,886.00 $23,000.00 $23,000.00 $3,000.00 $3,000.00
X 3 Barricades: furnish,
erect, install, and
maintain perimeter
barricades and warning
signs throughout the
project; remove then
restore area upon
project completion.
1 Lump Sum $25,426.00 $25,426.00 $40,000.00 $40,000.00 $6,000.00 $6,000.00
X 4 Demolition: Saw cut slab,
excavation, including soil
abatement measures.
Nighttime work.
1 Lump Sum $55,204.00 $55,204.00 $80,700.00 $80,700.00 $56,500.00 $56,500.00
X 5 Removal of sewer snake
obstruction, waterjet and
flush sewer lines and all
incidental work to
complete. Nighttime
work.
1 Lump Sum $388,741.00 $388,741.00 $54,000.00 $54,000.00 $63,500.00 $63,500.00
X 6 Restore Area: Patch back
area to existing
conditions perdrawings
and specifications, add
new cleanout. Nighttime
work.
1 Lump Sum $48,977.00 $48,977.00 $22,000.00 $22,000.00 $8,000.00 $8,000.00
EVALUATION TABULATION
IFB No. B-4944
AUPUNI CENTER SEWER JUNCTION REPAIRS
EVALUATION TABULATION
Invitation For Bid - AUPUNI CENTER SEWER JUNCTION REPAIRS
Page 3
B-4944 - BASE BID Isemoto Contracting Co., Ltd. Jas. W. Glover, Ltd. Stan's Contracting, Inc.
Selected Line Item Description Quantity Unit of
Measure
Unit Cost Total Unit Cost Total Unit Cost Total
X 7 Record Documents: Tone
existing sewer line,
submit video camera
inspection, update
record drawing.
1 Lump Sum $12,229.00 $12,229.00 $2,000.00 $2,000.00 $4,000.00 $4,000.00
X 8 De-mobilization. Final
site/facility cleanup (shall
not exceed 2.5% ofthe
overall basic bid amount.
1 Lump Sum $12,973.00 $12,973.00 $5,000.00 $5,000.00 $2,500.00 $2,500.00
Total $632,850.00 $237,700.00 $148,500.00
B-4944 - ALLOWANCE
PART B. Disposal, shipping and handling of soil identified as hazardous waste.
B-4944 - ALLOWANCE Isemoto Contracting Co., Ltd. Jas. W. Glover, Ltd. Stan's Contracting, Inc.
Selected Line Item Description Quantity Unit of Measure Unit Cost Total Unit Cost Total Unit Cost Total
X 1 Allowance:
Disposal,
shipping and
handling of soil
identified as
hazardous
waste.
1 Allowance $75,000.00 $75,000.00 $75,000.00 $75,000.00 $75,000.00 $75,000.00
Total $75,000.00 $75,000.00 $75,000.00
B-4944 - ALTERNATE BID NO. 1
PART C. BASE BID. (DEDUCTIVE) (NOTE: Bidders must complete all unit prices and amounts. Failure to do so may be grounds for
rejection of bid)
EVALUATION TABULATION
IFB No. B-4944
AUPUNI CENTER SEWER JUNCTION REPAIRS
EVALUATION TABULATION
Invitation For Bid - AUPUNI CENTER SEWER JUNCTION REPAIRS
Page 4
B-4944 - ALTERNATE BID NO. 1 Isemoto Contracting Co., Ltd. Jas. W. Glover, Ltd. Stan's Contracting, Inc.
Selected Line Item Description Quantity Unit of Measure Unit Cost Total Unit Cost Total Unit Cost Total
X 1 DEDUCTIVE
ALTERNATE:
Daytime work,
Monday to
Friday, eight (8)
hour workday,
between the
time frame of
7:00 A.M. to
4:30 P.M. a)
Provide a
deductive price
less than the
base bid) to
perform the
work during
normal business
hours.
1 Lump Sum -$5,473.00 -$5,473.00 $7,600.00 $7,600.00 $0.00 $0.00
Total -$5,473.00 $7,600.00 $0.00
B-4944 - TOTAL LUMP SUM BASIC BID WITH ALLOWANCE AND BID ALTERNATE
PARTS A. THROUGH C.
B-4944 - TOTAL LUMP SUM BASIC BID WITH ALLOWANCE AND BID ALTERNATE Isemoto Contracting Co., Ltd. Jas. W. Glover, Ltd. Stan's Contracting, Inc.
Selected Line Item Description Quantity Unit of Measure Unit Cost Total Unit Cost Total Unit Cost Total
X 1 PART A.
SUBTOTAL
1 Lump Sum $632,850.00 $632,850.00 $237,700.00 $237,700.00 $148,500.00 $148,500.00
X 2 PART B.
SUBTOTAL
1 Allowance $75,000.00 $75,000.00 $75,000.00 $75,000.00 $75,000.00 $75,000.00
X 3 PART C.
SUBTOTAL
1 Lump Sum -$5,473.00 -$5,473.00 $7,600.00 $7,600.00 $0.00 $0.00
Total $702,377.00 $320,300.00 $223,500.00