HomeMy WebLinkAbout2011-05-31 Report of Change Orders Authorized REPORT OF CHANGE ORDERS AUTHORIZED
FOR THE PERIOD OF:5/16/115/31/11
legend:
CO Change Order
SA Supplemental Agreement
PS Professlonal Services
C Construction
PTA Price Term Agreement
GS Other Goads&Services
original original %of Cummulative %of
Execution job Contract Project Contract Dept. Contract Contract Co/SA CO/SA prig Co/SA prig Contractor Project Project Purpose
Date # # Title Type Amount Date No. Amount Coat Total Cont Manager Status
Willi To address unforeseen issues
511 312 0 1 1 SW-3965 0.002785 Pahoa Recycling& C DEM $3,907,494.10 51612010 2 $26,410.21 0.68% $38,651.21 0.99%Construction Torn Gloor Open regarding saftey and protection of
Transfer Station both users and structures at the New
Corp. Transfer Station.
Housing Standard Dominador L This Is to extend for one option year
511 812 0 1 1 RFP-2598 GS(PTA) Inspections PTA Housing $0.00 51912011 1 $0.00 #DIVIO! 50.00 #DIVIO! Coloma dba NIA Open as allowed in original contract.
DC Consultant I lThmuqh 04122112.
DPW Facilities ADA Site James
5118/2011 B-3765 C.002564 Compliance and C DPW $4,118,169.00 712912009 3 $O.00 0.00 $10,193.00 0.25%Engineering Imanaka, Open Add additional contract working days.
Improvements-Phase Inc. Building
Division
Kaloko Housing Isemoto Additional relocation work of parking
511 8120 1 1 H-3964 0.002781 project,Phase C Housing $3,324,738.00 412712010 2 $29,645.00 0.89% -$61,803.00 -1.86%Contracting Co.Dan Russell Open lot(Bldg A)due to proximity to
Ltd. cultural cave.
Required change In antenna design
0.001371, Pacific Wireless Steve to withstand high winds.Cumulative
5/18/2011 IFB2326 Fire Dept. Radio Maintenance GS Fire $148,940.12 911812007 5 $5,019.76 3.37/ $130,295.13 87.48%Communication Wilhelm Open total Includes 2nd year maintenance
Portion. Inc. cost on multi year contract of
$120,025.37(HFD's Portion)
Kau CDP Steering Ron Time extension to complete Kau
512412011 NIA 0.002352 Committee Recorder GS Planning $5,400.00 61812009 1 $O.DO O.OD% $o.DD 0.00%Isobel Donovan Whitmore Open CDP process.
512612011 NIA 0.002775 Puna CDP Community PS Planning $16,497.00 61112010 1 $0.00 0.00% $0.00 0.00%Elizabeth J. Larry Brawn Open No cost extension for additional year
Planning Assistant Hultman-Salfen to May 30,2012.
REPORT OF CHANGE ORDERS AUTHORIZED
FOR THE PERIOD OF:5/16/115/31/11
original original %of Cummulative I %of
Execution job Contract Project Contract Dept. Contract Contract Ca/SA Ca/SA Ong Ca/SA Brig Contractor Project Project Purpose
Date I # I # Title Type I Amount Date I No. I Amount I Cant I Total Coul Manager I Status
Total#of Total original Contract Total Co/SA
Contracts Amount $11,521,238.22 for Period 7
TolalCUSA $61,074.97
Amount for Period