HomeMy WebLinkAbout2012-06-15 Report of Change Orders Authorized REPORT OF CHANGE ORDERS AUTHORIZED FOR THE PERIOD OF: 6/1/12-6/15/12 Legend: Change Order CO Supplemental Agreement SA Professional Services PS Construction C Price Term Agreement PTA Other Goods & Services GS OriginalOriginal % ofCumulative% of ExecutionJob Contract ProjectContractDept.ContractContractCO/SACO/SAOrigCO/SAOrigContractorProjectProjectPurpose Date##TitleTypeAmountDateNo.AmountContTotalContManagerStatus Ane Keohokalole Hwy, Ben Ishii, Bio-retention basins must be installed Hina Lani Street to Engineering based on the environmental 6/13/2012P-3944C.002698CDPW$29,893,336.762/22/201017$128,557.860.43%$4,678,648.5115.65%Nan, Inc.Open Palani Rd. FAP No. Div.assessment. ARR-1880(1) Modify Scope of Work to relocate Naalehu and Pahala Wastewater Treatment Plant in Fukunaga & Wastewater Collection 6/14/2012N/AC.001454PSDEM$971,350.0010/11/20072$239,483.0024.65%$461,910.0047.55%Lyle HirotaOpen Associates, Inc.Naalehu due to the identification of & Treatment System significant archeological sites in area. Supplemental agreement for an Kalapana Lava Viewing Jan-Guard Gilbert additional 90 day extension period 6/14/2012RFP-2657C.002995GSParks$145,848.9812/15/20104$65,670.5745.03%$328,351.71225.13%Open ServiceHawaii IncBenevides while new specification and bid completed. JM Consulting RFP-Health and Educational Pauline Option year extension from (6 month 6/13/2012C.003274GSAging$55,000.009/6/20111$0.000.00%$0.000.00%Open Services 103FServicesFukunagaextension only at this time). Planning, Design and Isemoto Casey Construction of Island Contracting Co. 6/13/2012E-4066BC.003315CDPW$599,000.0010/10/20111$0.000.00%$0.000.00%OpenNumber of working days increased. Yanagihara Wide Bus Stops and Ltd. Shelters, Part B Planning, Design and Isemoto Casey Construction of Island Contracting Co. 6/13/2012E-4066AC.003314CDPW$397,100.0010/10/20112$0.000.00%$5,817.391.46%OpenNumber of working days increased. Yanagihara Wide Bus Stops and Ltd. Shelters, Part A David Engineering Services Add electrical engineering services Engineering Yamamoto, for DPW Facilities for coordination with mechanical 6/14/2012B-3831C.001420PSDPW$47,100.008/27/20071$20,230.0042.95%$20,230.0042.95%Open Partners Inc Building Mechanical Systems.system design. Division REPORT OF CHANGE ORDERS AUTHORIZED FOR THE PERIOD OF: 6/1/12-6/15/12 OriginalOriginal % ofCumulative% of ExecutionJob Contract ProjectContractDept.ContractContractCO/SACO/SAOrigCO/SAOrigContractorProjectProjectPurpose Date##TitleTypeAmountDateNo.AmountContTotalContManagerStatus Reconstruction of additional pavement sections initially weakened Mamalahoa Highway from earthquake and further Isemoto Ben Ishii Earthquake Repairs. Contracting Co Engineering deteriorated; allow for price 6/13/2012P-3780C.002678CDPW$4,269,280.001/5/20106$218,351.255.11%$490,111.8111.48%Open Federal Aid Project No. Ltd.Divisionadjustment of short supply materials; ER-15(9) additional time required for additional excavation and additional paving. To address hidden structural damage Waimea Park Ballfield Jeff Ochi, to light poles' bases and ensure their 6/13/2012PR-4080C.003320CDPW$164,000.0010/14/20112$3,498.542.13%$19,003.6911.59%E Ten, Inc.Open Lights ReplacementP&R integrity upon reinstallation. Total # ofTotal Original Contract Total CO/SA 9$36,542,015.749 ContractsAmount for Period Total CO/SA $675,791.22 Amount for Period