Loading...
HomeMy WebLinkAbout2013-04-30 Report of Change Orders AuthorizedREPORT OF CHANGE ORDERS AUTHORISED FOR THE PERIOD OF, 0 4/16/13 f®r 4/30/13 Legend: CO Change Order SA Supplemental Agreement PS Professional Services C Construction PTA Price Term Agreement GS Other Goods &Services Original Original %01 Cumulative %01 EX-ecution Job Contract Project Contract D ept. Contra ct Contract CO /SA CO /SA orig CO /SA orig Contractor Project Project Purpose Date # # Title Type Amount Date No. Amount Cont Total Cont Manager Status Kailua Recycling and William C. Move and erect Reuse bamboo 4/1612013 SW- C.003492 Transfer Station C DEM $1333838011 .00 7/3/2012 2 $433 14.00 0.32% $10,655.00 0.80% Loeffler Ryan Dixon Open structure from Hilo to Kailua Transfer 4053R Repairs and Construction Station. Enhancements 11 11 Planning, Design and 11 11 Isemoto 4/1912013 E -4066A C.003314 Construction of Island C DPW $397,100.00 10/10/2011 6 $0.00 0.00% $25,650.04 6.46% Contracting Co C asey Open Completion date extended to Ma y Wide Bus Stops and Ltd Yanagihara 31, 2013. Shelters Waimea District/ Required revisions to the Master 4/1912013 N/A C.002045 Regional Park Master PS P &R $287,400.00 9/23/2008 4 $4,000.00 1.39% $106,002.71 36-88% PBR Hawaii and James O pen Plan Report Archaeological Planning Project Associates, Inc. (oma a Inventory Survey and Environmental Assessment. 4/29/2013 RFP 2298 C .001308 Landfill Diversion RFP DEM $309,750.00 11/29/2007 7 $0.00 0.00% $470,275.00 151.82% Atlas Recycling Chris Chin- Open Extend the current contract for an In centive P ro r am Center, LLC Chance a dditional 180 Structural Engineering Wiss Janney 4/25/2013 E -4069 C.003296 Services for the Reed's PS DPW $506,529.00 9/16/2011 1 $212,000.00 41.85% $212,000.00 41.85% EIstner Robert Open Additional costs relating to analysis s land Bridge Associates, Inc. Yanabu and design services. Rehabilitation Planning, Design and Isemoto 4/25/2013 E -40666 C.003315 Construction of Island C DPW $599,000.00 10/10/2011 4 $0.00 0.00 % $81,261.96 13.57% Contracting Co. Casey Open Contract term is extended for 20 ide Bus Stops and Ltd. (anagi ara CCD due to unanticipated delays. Shelters, Part B McCorriston Additional funds to provide 4/25/2013 N/A C.002620 Special Council - PS Corp. $25,000.00 11/27/2009 2 $25,000.00 100-00% $75,000.00 300.00% Miller Mukai Lincoln Open assistance and advice regarding Hokuli'a Counsel MacKinnon LLP As hida ban kruptcy proceeding involving Oceanside. PTC Partners - Ken Van 4/29/2013 N/A C.000775 Puainako Office and GS DEM / DIT $260,958.00 6/29/2006 9 $28,678.00 10.99% $1,671,132.00 640.38% PTC Partners Bergen Open Extend lease agreement. Warehouse REPORT OF CHANGE ORDERS AUTHORISED FOR THE PERIOD OF, 0 4/16/13 f®r 4/30/13 Total CO /SA dp Amount for Period $2 3,992.00 Original Original %01 Cumulative %01 Execution lob Contract Project Contract Dept. Contract Contract CO /SA CO /SA orig CO /SA orig Contractor Project Project Purpose Date # # Title Type Amount Date No. Amount Cont Total Cont Manager Status Total # of Total Original Contract T011111111111431 CO /SA C ontracts 8 Amount X3,724,538.00 for Period 8 Total CO /SA dp Amount for Period $2 3,992.00