F.EXAMPLE PROJECTS WHICH BEST ILLUSTRATE FIRM'S QUALIFICATIONS FOR THIS SERVICE CATEGORY
<br /> (Present no more than 10 projects, with emphasis on previous City projects. Complete one Section F for each project)
<br /> 21.TITLE AND LOCATION (City and State) 22.YEAR COMPLETED
<br /> Kauai Emergency Flood Repairs and Cleanup at Various Locations April 2018, PROFESSIONAL SERVICES CONSTRUCTION (If applicable)
<br /> Northern and Eastern Kauai, Island of Kauai, Hawaii 2018 2019
<br /> 23. PROJECT OWNER'S INFORMATION
<br /> a.PROJECT OWNER b.POINT OF CONTACT NAME c.POINT OF CONTACT TELEPHONE NUMBER
<br /> Hawaii Department of Transportation, Larry Dill (808) 241-3006
<br /> Highways Division
<br /> 24. BRIEF DESCRIPTION OF PROJECT AND RELEVANCE TO THIS CONTRACT (Include scope, size, and cost)
<br /> Mid-April 2018, record rains,wind, and flooding triggered landslides and undermined portions of Kuhio Highway,forcing its closure from
<br /> Hanalei to Kee. WSP assisted HDOT in the response to this unprecedented disaster through the preparation of Detailed Damage
<br /> Inspection Reports, environmental documents and permit applications, construction and permanent easement maps, and plans and
<br /> specifications for the recovery efforts spanning more than 26 individual sites. Sites included seventeen (17)slope clean-up sites with
<br /> slope faces as high as 70 feet; 3 roadway stabilizations,2 historic bridge replacements, 1 historic bridge rehabilitation, 1 CRM Wall
<br /> replacement, and repair of 2 stream/river crossings. Innovative methods were employed using a fiber reinforced polymer(FRP)to
<br /> rehabilitate the historic Waioli Bridge and negotiate the Section 106 Memorandum of Agreement.
<br /> WSP coordinated and prepared documentation for environmental clearances in NHPA Section 106 (including a Section 106 MOA), ESA
<br /> Section 7, Section 4(f), CWA Section 404 (4 letters of No Permit Required;5 Pre-Construction Notices/404 Permits), NEPA Categorical
<br /> Exclusions, and CWA Section 402 NPDES permits.
<br /> All clearances were obtained with 6 months. A summary of the repairs and locations are listed below.
<br /> Haena to Hanalei
<br /> 1. Kuhio Highway(Route 560), Milepost(MP) 10 at Kee State Park: Reconstruct roadway
<br /> 2. Limahuli Stream Crossing (Route 560), MP 9.55,: Repair concrete section lost in flooding. Resurface entire ford crossing;
<br /> 3. Kuhio Highway(Route 560), MP 8.87 at Haena Beach Park: Repair roadway shoulder;
<br /> 4. Manoa Stream Ford Crossing (Route 560), MP 8.76 near Haena Beach Park: Repair the entire crossing;
<br /> 5. Kuhio Highway(Route 560), MP 6.5 (Repair Site 2): Roadway stabilization area with only 1 lane remaining: Debris removal, slope
<br /> wall installation including soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair;
<br /> 6. Kuhio Highway(Route 560), 15 locations or more from MP 6.5 through MP 4.4: Debris removal, slope scaling, slope stabilization,
<br /> guardrail replacement, pavement repairs;
<br /> 7. Kuhio Highway(Route 560), MP 5.8: Stockpile area;
<br /> 8. Kuhio Highway(Route 560), MP 4.5 (Repair Site 1): Roadway stabilization area: Debris removal, slope wall installation including
<br /> soil nails, foot of slope revetment, guardrail/sign replacement, pavement repair;
<br /> 9. Kuhio Highway (Route 560), MP 4.4: Stockpile area;
<br /> 10. Waikoko Bridge (Route 560): Replace existing bridge;
<br /> 11. Waipa Bridge (Route 560): Replace existing bridge;
<br /> 12. Kuhio Highway (Route 560), MP 3.7: Staging area;
<br /> 13. Waioli Bridge (Route 560): Replace existing bridge; debris removal from under bridge
<br /> 14. Kuhio Highway (Route 560), MP 1: Debris removal, slope scaling, guardrail replacement, minor pavement repair;
<br /> 15. Kuhio Highway (Route 560), MP 0.5: Debris removal;
<br /> Kalihiwai
<br /> 16. Kuhio Highway(Route 56), MP 25: Debris removal, slope scaling;
<br /> 17. Kuhio Highway(Route 56), MP 24.9: Debris removal from under bridge, and concrete rubble masonry(CRM)wall replacement;
<br /> Wailua
<br /> 18. Wailua Bridge (Route 56): Debris removal from river under bridge.
<br /> Contract Value: $1.1 million
<br /> 25. FIRMS FROM SECTION C INVOLVED WITH THIS PROJECT
<br /> (1)FIRM NAME (2)FIRM LOCATION(City and State) (3)ROLE
<br /> a. WSP USA Inc. Honolulu, Hawaii Subconsultant
<br /> (1)FIRM NAME (2)FIRM LOCATION(City and State) (3)ROLE
<br /> b. KSF, Inc. Honolulu, Hawaii Prime Consultant
<br /> AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 330 PAGE 13