Laserfiche WebLink
3/6/24, 12:06 PM Unite Here!Local 5 v.City and Cty.of Honolulu,231 P.3d 423-Haw: Supreme Court 2010-Google Scholar <br /> 430 '43o 2. Initial Approvals and Delays in the Project's Development <br /> As observed by the ICA: <br /> The[1985]EIS listed additional governmental approvals KDC needed to obtain in order to complete development of the[p]roject,including rezoning approval <br /> from the DLU,grading and building permits,a shoreline certification,a Special Management Area Use Permit[(SMP)],and subdivision approval. <br /> On March 27,1986,the Land Use Commission approved the reclassification of 236 acres of the property from[a]griculture...to[u]rban[d]istrict for resort and golf <br /> course uses. <br /> On May 23,1986,the DLU accepted KDC's application for a[SMP]and[s]horeline[s]etback[v]ariance.KDC sought to expand its resort by developing a master- <br /> planned resort community that would include hotels,dwellings,commercial areas,golf courses,parks,roadways;to replace two drainage culverts with open <br /> channels;and to conduct a desilting operation at Kawela Bay. <br /> On June 25,1986,a bill for an ordinance to rezone certain portions of the property to be developed under the[p]roject was introduced before the[City Council]. <br /> The bill incorporated the Unilateral Agreement and Declaration for Conditional Zoning([u]nilateral[a]greement),in which KDC agreed that the zoning change <br /> would be subject to conditions requiring,among other things,construction of a wastewater treatment plant,construction of low-to-moderate-income housing, <br /> improvements and modifications to roadways,the implementation of a shuttle service,and the establishment of a child care center,parks,public easements to <br /> and along the shoreline,and public parking.Like the[1985]EIS,the[u]nilateral[a]greement anticipated development to proceed in three phases,the last phase <br /> to be completed before 2000.The[u]nilateral[a]greement noted that development may deviate from the phased development schedule"due to the occurrence of <br /> changed economic conditions,lawsuits,strikes or other unforeseen circumstances." <br /> The City Council passed the rezoning bill on August 14,1986 and approved KDC's application for the[SMP]and[s]horeline[s]etback[v]ariance by resolution <br /> adopted on October 1,1986(the March 27,1986;August 14,1986;and October 1,1986 approvals are collectively referred to as the[p]roject[e]ntitlements). <br /> Over the next twenty years,only certain aspects of the[p]roject were completed.KDC constructed a wastewater treatment plant and water main between January <br /> 1989 and March 1990,the Opana Wells between February 1989 and March 1991,and the Palmer Golf Course between March 1989 and March 1991. <br /> Construction of improvements to Punahoolapa Marsh began in approximately March 1990.From 1990 through 1991,KDC obtained subdivision approvals for <br /> various parcels to be used for parks,roads,hotels,a golf course,and a golf clubhouse. <br /> In March 1999,Kuilima purchased the property underlying the[p]roject from KDC[,]and KDC assigned its interest in the[p]roject to Kuilima. <br /> In May 1999,the DPP drafted the Ko olau Loa Sustainable Communities Plan"to help guide public policy,investment,and decision-making through the 2020 <br /> planning horizon"in order to maintain and enhance"the region's ability to sustain its unique character,current population,growing[sic],families,lifestyle,and <br /> economic livelihood."The plan recognized and supported the[p]roject.The City Council adopted the plan on December 16,1999. <br /> Kuilima renovated the existing Fazio Golf Course between 2000 and 2002.In 2003,Kuilima obtained approval to renovate and expand existing portions of the <br /> Turtle Bay Resort.Between 2003 and 2005,Kuilima invested about$100 million in completing these renovations,which included the addition of nine resort <br /> condominium units. <br /> As of November 2005,construction on the major components of the[p]roject,including the hotel rooms and the[remaining]condominium units,had not begun. <br /> 431 '431 120 Hawaii at 460-61,209 P.3d at 1274-75(emphasis added). <br /> 3. Other Relevant Post-1985 EIS Traffic Studies <br /> After 1985,Kuilima solicited two additional traffic impact analysis reports-in 1991 and 2005.I21 Because the 1985 EIS considered projected traffic impacts through the year <br /> 2000,the 2005 updated traffic impact analysis[hereinafter,the 2005 report]and three addendums thereto,prepared in 2006,are particularly relevant. <br /> The 2005 traffic report focused on local traffic impacts,that is,impacts on the roadway fronting the property,including the internal roadways of the resort itself.Generally,the <br /> 2005 traffic report indicated that,even with the construction of certain traffic improvements(many of which overlap with the yet incomplete improvements suggested by the <br /> 1985 EIS),the expansion project,when completed,would result in increased local traffic impacts. <br /> As previously stated,the 2005 report was updated three times in 2006,focusing again on only local traffic impacts.Addendum No.1,dated February 15,2006,evaluated the <br /> initial design of the intersection of Kamehameha Highway and the project's Alpha Road(also known as the proposed West Kuilima Drive),including turning lanes and the <br /> recommended improvements to facilitate the traffic needs of that immediate area,projected out through 2008.The addendum concluded that, <br /> [a]s Turtle Bay Resort continues to expand beyond the Year 2008,the peak hour traffic operations at the intersection of Kamehameha Highway and Alpha Road <br /> are expected to deteriorate below satisfactory levels of service[(LOS)].Additional improvements at the study intersection,such as traffic signalization and lane <br /> modifications,may be required to mitigate the traffic impacts resulting from further development of the Turtle Bay Resort. <br /> (Emphasis added.) <br /> Addendum No.2,dated February 23,2006,evaluated the design of two-lane Alpha Road to determine when it should be widened to a four-lane roadway.It concluded that <br /> Alpha Road will be constructed as a private roadway and is expected to remain so in the foreseeable future.Traffic operations of the two-lane section of Alpha <br /> Road at peak hour volumes over 800[vehicles per hour]would result in a[below satisfactory LOS].In general,intersection operations are more critical than the <br /> operation of a continuous two-lane roadway.The proposed 108-foot right of way will provide adequate width as to construct turning lanes on the initial two-lane <br /> divided roadway at internal resort intersections,as needed.Widening sections of Alpha Road...would maintain[satisfactory]conditions or better as major[I]ots in <br /> the Turtle Bay Resort are developed.The remaining two-lane section of Alpha Road...is expected to operate at a satisfactory[LOS]at full build out and <br /> occupancy of the Turtle Bay Resort Master Plan. <br /> Addendum No.3,dated August 25,2006,analyzed the second phase of improvements on Kamehameha Highway,including traffic signalization at the Kamehameha <br /> Highway/Alpha Road intersection,improvements at the intersection of Kamehameha Highway and Kuilima Drive,and traffic signalization of the Kamehameha Highway/Kuilima <br /> Drive intersection,projected through 2011.The addendum concluded that <br /> [t]he Kamehameha Highway intersections at Alpha Road and Kuilima Drive are expected to require traffic signalization to accommodate the anticipated expansion <br /> of Turtle Bay Resort up to the Year 2011,when a total of 1,970 hotel rooms will be constructed.Lane modification at the study intersections,the extension of <br /> https://scholar.google.com/scholar_case?case=4308700817237546533&q=unite+here+local+5&hI=en&as_sdt=2006 3/17 <br />