TAKEMOTO: Roy Takemoto. I’m with PBR Hawai‘i. We are the planning consultants to the
<br />applicant, the Church. Address: 1719 Haleloki Street, Hilo.
<br />
<br />BEAUDET: Please proceed with your presentation.
<br />
<br />TAKEMOTO: The applicant is in agreement with the staff report, the recommendations and the
<br />conditions, as amended. We have also seen the letter from DOE, and we can address those now or
<br />after testimony from the DOE, however pleases you. Maybe, let’s, we can quickly address those
<br />since it’s before you now. You have the testimony.
<br />
<br />BEAUDET: I would prefer that we address them now. And then if we feel that there is need for
<br />comments subsequent to testimony, then we can ask you to return.
<br />
<br />TAKEMOTO: Okay. There are three concerns. On concern No. 1, the access, the site plan that we
<br />showed, maybe not on this one but another exhibit in the application, it showed an Easement A and
<br />an Easement B. So this is Lot E-4 that is the subject of the letter, and Easement B is this one and
<br />Easement A is where the driveway would be located. Lot E-4 is intended to be part of the Onouli
<br />Road right-of-way; so eventually, although DOE owns it now, I think the idea and the hope is that
<br />Onouli Road and Lot E-4 would be dedicated to the County at some point. But at this time
<br />Easement A has been created and we’ve given a copy of the warranty deed that gave title to the
<br />Church that included Easement A, easement rights to Easement A. Easement B was something
<br />desired by the Church but never pursued and there was no grant of easement, so Easement B does
<br />not exist. So easement rights, the only question would be Easement A and the rights had been
<br />secured.
<br />
<br />On concern No. 2, which is the traffic, the concern raised in the letter was the potential concurrent
<br />activities with after-school and high traffic activity at the church. Those times would be, if they
<br />ever occur, would be very rare. The mitigation offered in the letter is to comply with the six
<br />conditions of the Traffic Impact Report, the TIAR, which is also Condition No. 5, I believe, of the
<br />existing conditions – no, let’s see, not that one, No. 3, No. 9 – it’s existing Condition No. 9. And
<br />the sixth condition of the TIAR addresses that; that should there be an exceptional queuing along
<br />Onouli Road due to the traffic occurring either at the church or the school, if there is queuing caused
<br />by the church, that there would be an attendant at the access point to help guide the traffic in and out
<br />to moderate and mitigate the problem during that event, which should be very rare.
<br />
<br />The third concern was drainage. The school experienced flooding in their parking lot in this area
<br />here, and it was apparently an extreme flooding event, a 100-year storm. And we believe that the
<br />Church will actually mitigate a recurrence of the flooding in the following ways. One is that
<br />although the engineering standard and what is required by the County is to accommodate the
<br />10-year flood on site, the Church actually would be doing more; they would be intersecting some of
<br />the flow, off-site flow, that’s coming onto the property, which they by right can just pass through,
<br />but they will be intercepting some of that, and accommodating that flow onto their drywells on site
<br />by designing the drainage to a 50-year storm rather than a 10-year storm. Additionally, there would
<br />be -. In the previous flooding, the existing condition, the undeveloped condition, brought a lot of
<br />debris with it. So by developing and maintenance of the landscaping and the yards here, there will
<br />be a substantial reduction in debris. And there also will be, as a possible buffer, there will be a
<br />retaining wall on the boundary, the easement boundary, with the school. That retaining wall is
<br />necessary to provide the access to the church, but the retaining wall will be raised about a foot
<br />above grade where it would be able to, whatever flow does make it down to this point, would be,
<br />4
<br />EXHIBIT B
<br />
<br />
|