Laserfiche WebLink
4. WASTEWATER CAPITAL IMPROVEMENTS <br />A. NĀ‘ĀLEHU LARGE CAPACITY CESSPOOL REPLACEMENT: <br />• Based on feedback from the community, alternative potential sites are being <br />investigated. <br />• The State Environmental Assessment process is to be completed prior to <br />selection of land for the treatment/disposal facility. <br />• Schedule for continued public outreach meetings to be determined. <br />• Closure of the large capacity cesspools as mandated by the EPA will occur <br />once the treatment and disposal system has been constructed and properties <br />have been connected to the new collection system. <br />• The project is funded by Clean Water State Revolving Funds (CWSRF) <br />monies. <br /> <br />B. PĀHALA LARGE CAPACITY CESSPOOL REPLACEMENT: <br />• Schedule for continued public outreach meetings to be determined. <br />• As a result of EPA funding for this project, the NEPA process in addition to the <br />State EA process are required. Both processes are to be completed prior to <br />selection of land for the treatment/disposal facility. <br />• The WWD has been teleconferencing with the EPA and their consultants on a <br />bi-weekly basis to ensure all items in the NEPA process are completed. <br />• Closure of the large capacity cesspools as mandated by the EPA will occur <br />once the treatment and disposal system has been constructed and properties <br />have been connected to the new collection system. <br />• The project is funded by Clean Water State Revolving Funds (CWSRF) <br />monies and partially by a federal EPA grant. <br /> <br />C. NORTH KONA SEWER AND EFFLUENT REUSE UPGRADE: <br />• The fully executed MOU has been received by DEM. The project itself is <br />about 95% complete. The only remaining wastewater project item in progress <br />is the manhole rim adjustments to final grade. <br />• The State DOT began the overall project construction in September 2015. <br />Currently, the anticipated completion date is August 2018. <br />• The project is funded by Clean Water State Revolving Fund (CWSRF) monies. <br /> <br />D. LONO KONA SEWER IMPROVEMENT DISTRICT: <br />• Project re-bid opening took place on 3/29/18. The County is securing USDA <br />concurrence on the contract awardee in accordance with the terms of their <br />Letter of Conditions associated with the USDA funding. <br />• Loan closing is in progress. Construction NTP is estimated to be issued July <br />2018. <br />• The USDA Rural Development has obligated loan and grant funds of <br />$2,437,000 and $4,024,800 respectively to this project. <br /> <br />E. KEALAKEHE AERATION UPGRADE AND SLUDGE REMOVAL: <br />• Final approval of the project will be issued pending the submittal of all close- <br />out documents. <br />8 <br /> <br />