• <br />• <br />• <br />When the contract plan includes a log of test borings showing a record <br />of the data obtained by the Departments investigation of subsurface conditions, <br />said log represents only the opinion of the Department as to the character of <br />material encountered by it in its test borings and there is no warranty, either <br />expressed or implied, that the conditions indicated are representative of those <br />existing throughout the work or any part of it, or that unforseen developments <br />may not occur. <br />Information respecting the site of the work given on the drawings or <br />specifications has been obtained by the Department and is believed to be reason- <br />ably correct, however, it is the responsibility of the bidder to verify all <br />such information Any utilities that the Contractor encounters during the <br />progress of the work, such as telephone ducts, electric ducts, water lines, <br />sewer lines, electric lines and drainage pipes, whether shown or not on the <br />contract plans, shall not be disturbed or damaged unless otherwise instructed in <br />the plans and specifications: The Contractor shall investigate, by actual <br />digging in the field, the location of the utility lines and their branch and <br />service lines. <br />In the event the utilities are damaged or disturbed by the Contractor, <br />the Contractor shall be held liable for the damaged or disturbed utilities which <br />were: <br />a, Shown on the plan or called for in the specification <br />b. Located and exposed on the job as it progressed <br />c. Pointed out to the Contractor in the field <br />The contractor shall repair the damaged or disturbed utilities to the existing <br />condition at no cost to the County or the project, Any damage claims due to the <br />disruption of service caused by the utilities being damaged shall be paid by the <br />Contractor who shall save harmless the County from all suits, actions or claims <br />of any character brought on account of such damages. <br />In the event utilities which were not shown on the plans and specifications <br />are damaged or disturbed by the Contractor, the Contractor shall not be held <br />liable but shall notify the Engineer. Upon instruction from the Engineer, the <br />Contractor shall repair all damages which shall be considered to be additional <br />work as covered by Section 4-2(c) "ADDITIONAL WORK". The Contractor shall have, <br />however, checked with and verified utility locations with the respective agencies. <br />Utilities which must be relocated due to construction and not indicated <br />in the plans and specifications shall also be considered to be additional work <br />as covered by Section 4.2(c) ''ADDITIONAL WORK". The Contractor shall not in <br />any case if he encounters underground utilities proceed with any work until he <br />has notified the Engineer, <br />No information derived from such inspection of records ef.'subsurface <br />investigations made by the Department or from the Engineer or from his autho- <br />rized representative or from maps, plans; specifications or drawings will in - <br />any way relieve the Contractor from any risk or from properly fulfilling all <br />the terms of the contract- The log test borings if included in the plans are <br />only for the convenience of the bidder and do not constitute a part of the <br />contract_ <br />Section 2 <br />Page 7 <br />